1 / 21

Server Virtualization: Navy Network Operations Centers

Server Virtualization: Navy Network Operations Centers. Lucas Taber July 13 th , 2006 University of San Diego GSBA 573 IT Project Management. Introduction. The Navy maintains several Network Operations Centers (NOCs) that are critical to their mission.

joelle
Télécharger la présentation

Server Virtualization: Navy Network Operations Centers

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Server Virtualization:Navy Network Operations Centers Lucas Taber July 13th, 2006 University of San Diego GSBA 573 IT Project Management

  2. Introduction • The Navy maintains several Network Operations Centers (NOCs) that are critical to their mission. • The NOCs are overwhelmed by the rapid growth of information system: • Space • Heat • Power • This project will address this issue through the application of server virtualization technology.

  3. Problem • Navy NOC #1 has reached capacity ahead of schedule. • Plant facilities require immediate and expensive upgrades to support additional systems. • Modernized systems must be installed to reduce costs and improve capabilities, but existing systems cannot be immediately decommissioned. • Operating at capacity is an operational risk to the Navy.

  4. Project Objectives • Implement server virtualization technology to reduce the number of physical servers: • Eliminate the risk of systems failure • Overheating • Power Failure • Eliminate the cost of interim fixes and schedule delay • Keep Projects on Schedule • Reduce the cost of future installations. • Future Server Deployment • Future Facility Upgrades (NOC #2)

  5. Stakeholders • The facilities management team at NOCs 1 and 2. • The operations staff. • The engineering team. • The shore modernization team. • The Fleet Readiness Certification Board (FRCB). • The security Certification and Accreditation (C&A) team. • The Navy Designated Approval Authority (DAA). • All Navy Customers.

  6. Project Justification • Current server utilization is very low. • Industry estimate = 5% on average. • Additional capacity is wasted and wastes resources. • Servers can be consolidated on a 10 to 1 ratio (maximum). • Navy estimate = 4 to 1 • Consolidation can recover as much as 75% of the current facilities resources. • Cost Avoidance • Risk Reduction

  7. Project Requirements • The project must achieve a minimum server consolidation ratio of 2 to 1. • Consolidated server hardware resource utilization will not exceed 80%. • Navy Designated Approval Authority (DAA) must approve the security certification and accreditation package. • Fleet Readiness Certification Board (FRCB) must approve the installation. • Consolidation efforts must not degrade the level of service provided by the servers or increase long-term operational risk. • Overall maintenance costs must decrease within the following fiscal year. • Virtualization technology will only be deployed at the two primary NOCs. • No server installations will be performed to achieve the consolidation, only existing server hardware can be used. • Additional Storage Area Network (SAN) materials can be procured if cost savings can still be achieved. • Planned system downtime will not exceed three hours.

  8. Deliverables • Project Management-Related Deliverables • Work Breakdown Structure (WBS) • Plan of Action and Milestones (POA&M) • Project Budget • Weekly Activity Reports • Bill of Materials • Product Related Deliverables • Concept of Operations • Site Survey Report • Test Plan Document • Test Plan Results • System Security Authorization Agreement (SSAA) Package • Installation Guide • Training Curriculum • Implementation Plan • Recommended Standard Operating Procedures (RSOP) • System Operation Verification Test (SOVT) • Trip Report / Lessons Learned • Virtualized Server Systems

  9. Success Criteria • Success Criteria • The project is completed by February of 2007 (prior to the next scheduled installation). • The facilities team for NOC 1 can avoid an emergency facilities upgrade. • Operational risk is the same or lower. • No additional manpower is required to operate the new software.

  10. WBS: Phase 1 - Concept • Concept • Hold Kick-Off Meeting • Identify Potential Solutions • Prepare Analysis of Alternatives • Contact Product Vendors • Research on the Internet • Generate Preliminary Cost Estimate • Write Concept of Operations • Write Document • Perform Document Q & A

  11. WBS: Phase 2 - Development • Development • Engineering • Select Software Product and Software Version • Select Server Hardware or Identify Existing Resources • Perform Site Survey of NOC • Identify Server Virtualization Candidates • Generate Site Survey Report • Write Document • Perform Document Q & A • Develop Implementation Plan • Write Document • Perform Document Q & A • Review Implementation Plan With Site • Obtain Implementation Plan Approval From Site • Write Installation Guide • Write Document • Perform Document Q & A • Write Recommended Standard Operating Procedures (RSOP) • Write Document • Perform Document Q & A • Write Systems Operation Verification Test (SOVT) • Write Document • Perform Document Q & A • Lab Testing • Download and Assemble Software • Write Test Plan • Write Document • Perform Document Q & A • Install Software in Lab • Execute Test Plan • Produce Test Results and Analysis

  12. WBS: Phase 2 - Development • Security • Perform independent security evaluation • Generate security test results and analysis • Write SSAA • Write Document • Perform Document Q & A • Submit SSAA to DAA • Obtain Authority To Operate (ATO) • Training • Develop Training Curriculum • Write Document • Perform Document Q & A • Train Site Operators • Obtain FRCB Fielding Approval • Generate CASE Form • Write Document • Perform Document Q & A • Procurement • Generate Budgetary Cost Estimate • Obtain Funding • Procure Software and Hardware • Receive and Process Software and Hardware • Record Products in Configuration Management Database • Deliver Software to Installers • Ship Hardware to Site.

  13. WBS: Phase 3 - Implementation • Implementation • Travel to NOC • Perform In-brief with Site • Hardware and Software Implementation • Measure Existing Resource Utilization • Install New Hardware • Install Virtualization Software • Virtualize Existing Servers and Migrate to New Hardware • Monitor Performance • Site Acceptance • Conduct SOVT • Obtain Site Acceptance • Perform Out-brief with Site • Return Travel

  14. WBS: Phase 4 – Close Out • Close-Out • Generate Trip Report / Lessons Learned • Write Document • Perform Document Q & A • Transition Program to Operations

  15. Staffing • Project Manager • Lead Engineer • Test Engineer • Technical Writer • Security Analyst • Security Tester • Trainer • Buyer • Installer • Logistician

  16. Schedule

  17. Communication Management • Daily Coordination • Email • Weekly Progress Monitoring • Staff Meeting / Teleconference • Weekly Action Report • Project Details / Requirements • Formalized Documentation (e.g., CONOPS, Test Plan, SOVT).

  18. Risk Management • The project will use a risk register to monitor risk areas and apply mitigation strategies.

  19. Expected Benefits Short-term benefits Long-term benefits

  20. Expected Costs Short-term Costs Long-term Costs

  21. Summary • An rapid deployment of server virtualization technology will provide significant benefit to the Navy. • Cost Avoidance: Present and Future • Risk Reduction • Increased Capacity

More Related