1 / 15

Managing the Project: The Supervisor’s Role Session 1: Understanding Project Delivery Systems

Managing the Project: The Supervisor’s Role Session 1: Understanding Project Delivery Systems Project Delivery Systems and Contracting Methods General Contracting Design-bid-build (Hard bid) Negotiated Construction Management At risk Agent (not at risk) Design/Build (and Assist)

johana
Télécharger la présentation

Managing the Project: The Supervisor’s Role Session 1: Understanding Project Delivery Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing the Project: The Supervisor’s RoleSession 1: Understanding Project Delivery Systems An AGC Construction Learning Tool

  2. Project Delivery Systems and Contracting Methods • General Contracting • Design-bid-build (Hard bid) • Negotiated • Construction Management • At risk • Agent (not at risk) • Design/Build (and Assist) An AGC Construction Learning Tool

  3. Special note regarding public (government) construction projects: • Statutes, rules and regulations vary from state to state and from type of public agency to type of public agency within a state • The following slides are intended to provide a general overview and do not pretend to cover every variation possible An AGC Construction Learning Tool

  4. General Contracting Overview • Also known as design-bid-build • Most traditional method • Currently 45% of non-residential construction • Owner contracts separately with design firm and general contractor • Construction contract may be bid or negotiated An AGC Construction Learning Tool

  5. General Contracting • Advantages: • If not negotiated, low bid is often sole selection factor • If not negotiated, owner receives best market price • Owner can know fixed price prior to start of work • Scope is defined prior to contractor pricing • Private sector owners can shortlist bidders list • Private sector owners can select a negotiated contractor based upon factors other than price • If negotiated, it is easier to pre-order long-lead items An AGC Construction Learning Tool

  6. General Contracting • Disadvantages: • Owner (and possibly designers) are responsible for change orders • Owner often has little power to select contractor on criteria other than price • No input from contractor during design phase • Difficult to pre-order long-lead-time items • Fosters conflict amongst project team members • Overall project schedule is extended An AGC Construction Learning Tool

  7. Construction Management (CM) Overview • Can have two forms: • CM at risk (CM may self-perform) • CM as agent (CM typically will not self-perform) • Currently 10% of non-residential construction • Owner contracts separately with design firm, CM and one or more prime contractors • CM contract may be negotiated or selected under Quality-Based Selection (QBS) • CM contract is never bid in the purest sense of the word An AGC Construction Learning Tool

  8. Construction Management • Advantages: • Allows for fast-track construction • Owner avoids general contractor markup on major subcontracts • CM input to the design process • Cooperation between design and construction teams promotes value engineering • If CM as agent form, the owner receives all of the benefits of competitive bidding of subcontracts • Change-order management is smoother for owner An AGC Construction Learning Tool

  9. Construction Management • Disadvantages: • Owner has multiple contracts to administer, with three the absolute minimum • Some argue that the owner pays double markup for little extra value, particularly if few prime contracts are awarded • Success depends largely upon cooperation and mutual respect of various parties to the project • High level of owner involvement often required An AGC Construction Learning Tool

  10. Design/Build (and Assist) (D/B) Overview • Owner contracts with one company for single-point responsibility for both design and construction services • Currently 45% of non-residential construction • D/B contract can be negotiated, selected with QBS or quasi-competitively bid • D/B assist is a variant of D/B in which the owner has a separate contract with the design firm • Architect and/or engineer (A/E) is a consultant to design/builder (contractor-led) unless the A/E is the design/builder (designer-led) or a partner in a joint venture An AGC Construction Learning Tool

  11. Design/Build (and Assist) • Advantages • Owner often knows the complete project price before detailed design work begins • Owner benefits from constructor input and management of design phase • Much faster overall project cycle time, as foundation work is often begun before anything else has been finalized in the design • Owner is responsible only for major scope change orders • Owner may still benefit from bidding of subcontractor work An AGC Construction Learning Tool

  12. Design/Build (and Assist) • Disadvantages • Owner does not receive competitive bids at the general contractor level • Some argue that quality can be compromised due to lack of checks and balances • Complex procurement process for public (government) agencies may not be a legal option for many • Scope must be well-defined very early in project An AGC Construction Learning Tool

  13. Basis for Understanding: Roles and Responsibilities of the Project Supervisor • In a broad sense, the project supervisor has three responsibilities on a project: • Manage tasks (scheduling, planning, etc.) • Manage relationships (motivate, lead, etc.) • Manage risk (safety, documentation, etc.) • How much time and effort is spent in each of these areas is largely a function of project delivery system and team characteristics An AGC Construction Learning Tool

  14. Relationships Tasks Risk Basis for Understanding: Roles and Responsibilities of the Project Supervisor • The Performance Profile: The supervisor’s role, or his/her expected performance for managing relationships, tasks and risks, will change on almost every project PROJECT 1 PROJECT 2 Relationships Tasks Risk An AGC Construction Learning Tool

  15. Basis for Understanding:Roles and Responsibilities of the Project Supervisor • In the previous slide, the project supervisor’s role is very different for Project 1 than for Project 2 • Project 1 could be a negotiated design-build job with a repeat client and a very experienced project manager and a field engineer assigned to the team • Project 2 could be a “hard bid” project with a public agency and an inexperienced project manager and limited field support due to tight budgets An AGC Construction Learning Tool

More Related