(n)QPS

(n)QPS. LHC: past, present and future. Mike Lamont for the LHC team. 2010 – main aims. Clear priority to lay the foundations for 2011 and the delivery of 1 fb -1 . Peak luminosity target 1x10 32 cm -2 s -1

kareem
Télécharger la présentation

(n)QPS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. (n)QPS LHC: past, present and future Mike Lamontfor the LHC team LHC status

  2. 2010 – main aims • Clear priority to lay the foundations for 2011 and the delivery of 1 fb-1. Peak luminosity target 1x1032 cm-2s-1 • Gain solid operational experience of injecting, ramping, squeezing and establishing stable beams • Steady running at or around 1 MJ for an extended period • Perform a safe, phased increase in intensity with validation and a running period at each step LHC status

  3. Performance ramp-up(368 bunches) Nominal bunch operation(up to 48) Initial luminosity run Nominal bunch commissioning Bunch trains Luminosity: 3 running periods Performance ramp-up made possible by a safe, staged commissioning. Meticulous preparation for unsafe beams! LHC status

  4. 2010 parameters LHC status

  5. Overall LHC efficiency in 2010 65%availability! Great achievement for the first year of operation! W. Venturini LHC status

  6. Physics operations ~30%Stable beams! W. Venturini LHC status

  7. 2010 - records Courtesy Atlas LHC status

  8. Status LHC Stored Energy Stored energy reached at 3.5 TeV:28.0 MJ 80 kg TNT Ralph Assmann LHC status

  9. Ions Protonsagain50 & 75 ns LHC status

  10. Lifetimes • Excellent single beam before collisions ~200 - 300 hours • Luminosity lifetime ~15 - 20 hours • Reasonably well given by emittance growth and intensity decay • Minimal drifts in overlap – beams very stable • Intensity lifetime ~90 hours • Luminosity burn, losses on collimators • Emittance growth (hor. ~ 30 hours, vert. ~ 20 to 40 hours) • Intra Beam Scattering • and something else – at least sometimes “the hump” LHC status

  11. Aperture LHC status

  12. Optics & magnetic machine • Optics stunningly stable • Machine magnetically and optically well understood • Excellent agreement with model and machine • Magnetically reproducible • Important because set-up remains valid from fill to fill LHC status

  13. Measured Cleaning at 3.5 TeV Making sure the hierarchy is respected (beam1, vertical beam loss, intermediate settings) Dump Protection Col. IR1 Momentum Cleaning IR8 IR2 IR5 LHC status

  14. LHC 2010 - summary • Excellent single beam lifetime • Ramp & squeeze essentially without loss • No quenches with beam above 450 GeV • Excellent performance of Machine Protection • Optics close to model (and correctable) • Excellent reproducibility • Aperture as expected • Better than nominal from injectors • Emittances, bunch intensity • Beam-beam: can collide nominal bunch currents • With smaller that nominal emittances And surprisingly good availability… LHC status

  15. PROBLEMS– TWO OF them LHC status

  16. UFOs – unidentified falling objects • Many sudden local losses have been recorded. • No quench, but preventive dumps • Rise time around of the order 1 ms. • Potential explanation: dust particles falling into beam creating scatter losses and showers propagating downstream • Distributed around the ring – arcs, inner triplets, IRs LHC status

  17. UFOs – a possible solution? • More events at higher intensities • Only 1? event observed at 450GeV • Signal shortens, i.e. the losses are faster with intensity • Signal amplitude does not increase with intensity  • Revision of thresholds on superconducting magnets could make the UFO effects acceptable • More detailed analysis needed to understand discrepancies with current simulations + additional quench tests to benchmark B.Dehning, E. Holzer, A.Nordt, M.Sapinski LHC status

  18. Electron cloud Schematic of electron cloud build up in LHC arc beam pipe due to photoemission and secondary emission [F. Ruggiero] Reflection Secondary emission yield [SEY] • Very much dependent on bunch spacing: • 150 ns. – local signs in common beam pipe • 75 ns. – some first signs • 50 ns. – vacuum valves in LHC status

  19. Electron cloud effects Electron cloud effects occur both in the warm and cold regions. • Vacuum pressure rise (background in experiments) • Single-bunch instability • Multi-bunch instability • Incoherent emittance growth • Heat load in cold arcs (quenches in the limit) • Perturbation of beam diagnostics Well understood, very well studied (other machines, simulations…) LHC status

  20. Experience in 2010 • Vacuum activity started off in regions with common beam pipe at 450 GeV as we pushed up the number of bunches with 150 ns spacing • Test solenoids cured problem – electron cloud • Tried 50 ns bunch spacing • Things really kicked off • High vacuum activity in warm regions (single beam pipe) • Significant heat load in cold regions • Instabilities and beam size growth observed • Surface conditioning (‘scrubbing’) observed • Gas desorption rates and SEY drop • Time constant < 1 day • Situation a lot cleaner with 75 ns • incoherent effects seen – emittance blow-up • 800+ bunches injected into both beams LHC status

  21. Scrubbing strategy for 2011 • 2010 observations are certainly due to ~ 2 < SEY < 2.5, whereas 1.7 was usually the max value studied in the past • Expect to be able to reach 200-300 b with 75 ns without scrubbing • Scrubbing with large emittance (>3.5 mm), high intensity (>1.2e11), 4x36b of 50 ns beam • Time • 2-3 days needed to setup 50 ns at injection • 7 days of scrubbing • 1 day for validation and scrubbing result evaluation • Lots of wire wrapped around warm bits during the technical stop (solenoids) LHC status

  22. Solenoids between DFBX and D1 in IR1R LHC status

  23. 2011 Energy – stick at 3.5 TeV – we still worry about the splices LHC status

  24. 2011: main goals • Motivation is clear! • 1 fb-1 delivered to each of IP1, IP5 and IP8 at 3.5 TeV • Can probably do better for IP1 and IP5 • It will be a challenge to deliver 1 fb-1 to IP8 • Maximum luminosity : from 2e32 to 3e32 cm-2 s-1 • Luminosity leveling via separation required to get close • Alice • pp run: 5e29 < L < 5e30 cm-2 s-1, µ < 0.05 fast, secure and far-reaching Decided on beta* = 1.5 m in Atlas, CMS; 3 m in LHCb; 10 m in Alice LHC status

  25. Baseline scenario • Beam commissioning: 3 weeks • Exit - stable beams with low number of bunches • Ramp-up to ~200 bunches (75 ns): 2 weeks • Multi-bunch injection commissioning continued • Stable beams • Technical Stop: 4+1 days • Scrubbing run: 10 days including 50 ns injection comm. • [Intermediate energy run – 5 days] • Resume 75 ns operation and increase no. bunches: 3 weeks • 300 – 400 – 600 – 800 – 930 - MPS and OP qualification • Physics operation 75 ns: ~930 bunches • (50 ns. remains an option if things look good) LHC status

  26. 2011 LHC schedule Q1/Q2 LHC status

  27. 2011 Q3/Q4 LHC status

  28. Estimated Peak and Integrated Luminosity LHC status

  29. 2011 – progress so far Impressive re-commissioning, improvements across the board. Operation cycle now well optimized: faster ramp & squeeze, much fewer manual actions required by shift crews LHC status

  30. LHC status

  31. Machine still beautiful LHC status

  32. Conclusions 1/2 • Injection, ramp and squeeze fully operational • LHC magnetic model & optics excellent • Beam instrumentation in good shape. • Beam cleaning and collimation works reliably with predicted efficiency. • Machine protection excellent performance • Machine aperture looks good • Performance with beam (losses, lifetimes, luminosity, emittance growth etc.) is very encouraging We have a beautiful machine on our hands! LHC status

  33. Conclusions 2/2 • Machine availability is excellent – the hard work of numerous teams • There are problems • UFOs somewhat worrying • Electron cloud well understood – measures prepared • 2011 – another long year ahead… • 75 ns. bunch spacing – up to 930 bunches • Nominal intensities, beta* 1.5 m in Atlas and CMS • Should be good for 5 to 10 x 1032 cm-2s-1and 1 to 3 fb-1 • Progress so far is good… • Will run in 2012 • Attempt to measure splice resistance in 2011/2012 might open the way to 4 TeV or higher LHC status