30 likes | 170 Vues
In the recent FAST Site meeting, Eric Takasugi from UCLA shared updates on the current status of testing at the site. A new chamber is operational and testing has commenced with two tests passed and one failed. The tests included Slow Control and AFEB connectivity assessments. Additionally, new ALCT firmware has been loaded onto several chambers, with plans for further deployments post-meeting. Continuous monitoring and improvements are underway to ensure robust performance and integration of the systems.
E N D
FAST Site Update Eric Takasugi UCLA ME 4/2 Meeting
FAST Site Status • New chamber in place (203) • Testing has begun • Pass on 2 tests • 9, Slow Control Test • 13, AFEB Threshold and Analog Noise Test • Fail on 1 test • 12, AFEB Connectivity and Noise Test ME 4/2 Meeting
Otherwise • DOC Shift • Loaded some new ALCT firmware on a few of the chambers • Plan to load the new ALCT firmware onto more chambers after tomorrow ME 4/2 Meeting