1 / 16

Developing a cap and floor regime for the GB-Belgium Interconnector: NEMO

Developing a cap and floor regime for the GB-Belgium Interconnector: NEMO. Pascal Boucquey (CREG) & Charlotte Ramsay (Ofgem) 10 th FUI Stakeholder Group Meeting 11 th March, 2011. Contents. State of play in GB and Belgium: The challenge Current regulatory background

Télécharger la présentation

Developing a cap and floor regime for the GB-Belgium Interconnector: NEMO

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Developing a cap and floor regime for the GB-Belgium Interconnector: NEMO Pascal Boucquey (CREG) & Charlotte Ramsay (Ofgem) 10th FUI Stakeholder Group Meeting 11th March, 2011

  2. Contents • State of play in GB and Belgium: • The challenge • Current regulatory background • Drivers for change • Project NEMO • GB-Belgium interconnector • Details and status of development • Coordinated approach from GB & Belgium • Developing an alternative model for regulation • High level principles • Cap and floor, outline • Implications for GB and Belgium • Next Steps for Ofgem and CREG 10th FUI Stakeholder Group Meeting, 11/03/2011

  3. GB: Context for the challenge Nordpool Single Electricity Market Existing Construction Proposed 2.5 GW 4 GW >10 GW Central West Europe 10th FUI Stakeholder Group Meeting, 11/03/2011

  4. GB: Current regulatory regime (for interconnectors only) • “Light touch” regulation • Separate Interconnector licence • Merchant interconnection • Business case = congestion rents • All upside and downside borne by investors • Apply for exemption from EU legislation 10th FUI Stakeholder Group Meeting, 11/03/2011

  5. GB: Drivers for change • Regulatory “risk” of exemptions (BritNed case) • Need for risk sharing between consumers and investors • Exemptions the exception not the rule • European model, national TSOs deliver interconnector investment • Merchant-exempt route not possible for several project partners • Need for a common / coordinated approach to regulation of shared assets? • Potential for commercially viable interconnection • But pure merchant financing of projects less viable … 10th FUI Stakeholder Group Meeting, 11/03/2011

  6. Belgium: Context for the challenge 10th FUI Stakeholder Group Meeting, 11/03/2011

  7. Belgium: Current regulatory regime(for national TSO, including interconnection) • Interconnections are integrated in the (national) transmission system • No separate interconnector licence • Fully regulated regime • Interconnection included in the Regulated Asset Base • Remuneration of the investment based neither on the level of revenues received from auctioning its capacity nor on the level of costs related to it • The yearly fair margin available for the TSO’s shareholders is guaranteed and based upon the RAB • Congestion recycled in order to decrease tariffs 10th FUI Stakeholder Group Meeting, 11/03/2011

  8. Belgium: Drivers for change • Different risk profile of DC, subsea cables • Scale of investment • Complexity and risk of project • National TSO (Elia) requesting enhanced rate of return to reflect risks • In addition, project identified as bringing benefits for the security of supply, economic welfare and competition • Alternative regulatory approach envisaged to fill the regulatory gap BE-GB 10th FUI Stakeholder Group Meeting, 11/03/2011

  9. GB-Belgium interconnector:Project NEMO • Regulatory challenges: • Significant differences between current GB and Belgian regimes • With current national regimes, risk of asymmetric interests for investors involved in the shared interconnector project • Issues converge with “Project NEMO” • GB – Belgium interconnector • Press release from National Grid & Elia, Feb 2008 • More on NEMO … • And on solving the regulatory challenges … 10th FUI Stakeholder Group Meeting, 11/03/2011

  10. GB-Belgium interconnector:Project NEMO • 1 GW HVDC connection • Isle of Grain to Zeebrugge • Marine • Sub sea survey • MMO contact • Consents and permits (GB and Be Marine organisations) • Contact w. fisherman • Onshore work • Consents & permits (Planning, environmental surveys, etc) • Early preparation of landing site (GB) 10th FUI Stakeholder Group Meeting, 11/03/2011

  11. High level principles for the new regime • Developers should be exposed to the market's valuation of interconnector capacity, • Consumers should be protected from the cost implications of excessive returns or market power that might accrue to interconnector owners, • Developers should be exposed to levels of investment risk that are commensurate with the level of regulatory intervention to mitigate excessive revenues and market power, • Regulatory treatment of developers should be coordinated between Regulatory Authorities at either end of the shared asset, and • (For GB and future IC developments) Treatment of potential interconnector developers should be impartial and unbiased between TSOs and non-TSO developers 10th FUI Stakeholder Group Meeting, 11/03/2011

  12. What is a cap and floor ... • Recoup profits within bounds of pre-set revenue cap and floor • Returns over cap – paid back to consumers • Returns fall below floor – triggers payment from consumers • Allows revenue regulation, protects consumers from market power • Maintains element of market valuation of interconnection • Moves closer to regulated regime favoured by Third Package • Can provide tailored incentives on top of regulated regime 10th FUI Stakeholder Group Meeting, 11/03/2011

  13. Design of the cap and floor • What activates the cap and floor? • Profit or similar (e.g. revenue, IRR) • How often is it assessed? • > 1year, <lifetime of project • Cumulative perspective? • When is the cap paid back (or floor paid out)? • When is the cap/floor set? • Ex-ante, on forecast costs … • How long does the cap/floor persist? • Lifetime of investment? Lifetime of interconnector? • Should it be reassessed at any point? • Additional requirements/obligations: • standards for operational efficiency and IC availability • requirements for capacity allocation (e.g. price coupling) 10th FUI Stakeholder Group Meeting, 11/03/2011

  14. Plans for joint consultation • The drivers for change in regulation of new interconnector investment • The high level principles behind the regime and rationale for option(s) considered • Design of the cap and floor - setting out the different parameters for the regime (e.g. what is the cap/floor levied on? How often is it assessed etc.) • Indicative levels for the cap and floor (not specific to NEMO) • Additional requirements/obligations on the developer/operator • List of requirements for application to NRAs for a cap and floor (relevant for GB) 10th FUI Stakeholder Group Meeting, 11/03/2011

  15. Process & Next steps • Consultation • Launch: end of April / May 2011 • Conclusions: Q3 2011 • Work on integrating the cap and floor into the GB and Belgian regimes (ongoing): • GB (Licence amendments, integration into price control etc.) • Belgium (Necessary changes in current legal framework, transposition of Third Package still ongoing …) • Continue discussions with other NRAs (GB) • Links with other projects: North Seas Countries Offshore Grid Initiative, energy infrastructure package etc. 10th FUI Stakeholder Group Meeting, 11/03/2011

  16. Thank you for your attention!

More Related