1 / 14

Bulding 245 schedule update

TE EPC. Bulding 245 schedule update. LIU Booster Meeting 13-09-2012 Serge Pittet, Fulvio Boattini TE-EPC. Building 245 Position. TE EPC. France. Limit for edification. France-Swiss border. Switzerland. Building 245 Preliminary D esign. TE EPC. HVAC room at ground floor

kelsie-kidd
Télécharger la présentation

Bulding 245 schedule update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TE EPC Bulding 245 schedule update LIU Booster Meeting 13-09-2012 Serge Pittet, Fulvio Boattini TE-EPC

  2. Building 245 Position TE EPC France Limit for edification France-Swiss border Switzerland TE-EPC - Serge Pittet, Fulvio Boattini

  3. Building 245 Preliminary Design TE EPC HVAC room at ground floor Control rooms at first floor Cooling towers Input Transformers Converter building Main entrance Storage capacitors TE-EPC - Serge Pittet, Fulvio Boattini

  4. MPSB Time Schedule TE EPC No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction 26 May 2016 Building Ready 14 April 2017 Start Commissioning on dummy load 17 October 2013 26 March 2015 FC 20 March 2014 18kV cabinets installation LV cabinets installation. Lights and other services Lights and electrical cabinets installed Overhead Crane installed Air conditioning and cooling pipes installation Cooling installation Cooling and Conditioning operating Fire alarm system installation Fire alarm system installation TE-EPC - Serge Pittet, Fulvio Boattini

  5. MPSB Time Schedule TE EPC No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction 26 May 2016 Building Ready 14 April 2017 Start Commissioning on dummy load 17 October 2013 26 March 2015 FC 20 March 2014 Power converter Design & specification Market Survey & Call for tender Power converter Design (supplier) Power converter construction Power converter Installation and cold commissioning Power converter commissioning on test magnets System commissioning on PSB magnets 20 June 2014 FC 25 August 2016 TE-EPC - Serge Pittet, Fulvio Boattini

  6. MPSB Time Schedule 2018 TE EPC Preliminary test of 1 MPS converter on half magnets string: 4 Weeks Is this slot feasible? Testing on spare magnets Tests of 1 MPS + 1 Trim on half magnet string: 4 weeks System Ready and Debugged Testing on spare magnets Commissioning testing of all converters: (8 Weeks) Of the utmost importance TE-EPC - Serge Pittet, Fulvio Boattini

  7. MPSB Time Schedule: Building construction TE EPC Integration is the first phase. Planned starting: October 2013 Required resources: 1 Engineer + 1 CAD designer for the most involved services Not a Full Time activity during the all integration phase Oct 2013 all services shall start to work to the integration DeadLine for building with services TE-EPC - Serge Pittet, Fulvio Boattini

  8. Bulding 245 schedule update TE EPC THANKS FOR THE ATTENTION QUESTIONS? TE-EPC - Serge Pittet, Fulvio Boattini

  9. SPARE SLIDES TE-EPC - Serge Pittet, Fulvio Boattini

  10. MPSB Technical Baseline TE EPC 64 BHZ Rings 1&4 GND • Overall voltage available increases and would allow a reduction of the RMS current using a faster ramping. • The capacitor bank totally absorbs the peak power on the 18kV network. Meyrin SVC would then become optional. • Spare sharing between MPS A and B and possibly with POPS. • Only a few new cables needed between the reference magnet (BCER) and the MPS. • New B-field regulation to minimize eddy currents and saturation effects impact at higher current and acceleration rate. • Some additional trim converters might be needed for shorter dipoles in the injection region. 128 QFO Rings 1,2,3&4 MPS A 2500V 5500A QFO 600V 450A Reference magnet Ring 1&4 Ring 1 B-filed measurement Reference magnet Ring 2&3 Ring 2 B-filed measurement 64 QDE Rings 1,2,3&4 MPS B 2500V 5500A QDE 600V 450A 64 BHZ Rings 2&3 GND TE-EPC - Serge Pittet, Fulvio Boattini

  11. MPSB Preliminary dimensioning TE EPC PAFEpk=2.8MW PDCDCpk=13.7MW PTrn=2.4MW Storage=0.25F@5kV Output ripple specification to be published soon Trim(s?) still to be dimensioned TE-EPC - Serge Pittet, Fulvio Boattini

  12. MPSB Time Schedule: Building construction TE EPC Doing the integration Now and until beginning LS1 will allow GS/SE to start with specification. GS/SE Engineering Building construction Services Installation (EL,CV…) Cooling station installation No ressources Services Integration (EL, CV,..) Building infrastructure & services ready TE-EPC - Serge Pittet, Fulvio Boattini

  13. MPSB Time Schedule TE EPC Services Installation No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction Cooling station installation First tests on PSB magnets 26 May 2016 Building ready 17 October 2013 26 March 2015 FC 20 March 2014 Converter manufactured and installed Converters performance commissioned and ready for operation TE-EPC - Serge Pittet, Fulvio Boattini

  14. MPSB Time Schedule TE EPC No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction 26 May 2016 Building Ready 14 April 2017 Start Commissioning on dummy load 17 October 2013 26 March 2015 FC 20 March 2014 18kV cabinets installation LV cabinets installation. Lights and other services Lights and electrical cabinets installed Overhead Crane installed Air conditioning and cooling pipes installation Cooling installation Cooling and Conditioning operating Fire alarm system installation Fire alarm system installation TE-EPC - Serge Pittet, Fulvio Boattini

More Related