An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Caltrain Modernization CMAA September 18, 2014

  2. Caltrain Today

  3. Key Facts • Diesel commuter rail system • SF to SJ area • 77 mile corridor, 32 stations • 92 trains / weekday • Ridership: ~ 55,000+ weekday

  4. Caltrain Ridership Note: Bike Ridership 11 % increase (FY14)

  5. 2014 Top Ridership Trains Note: February 2014 counts (lower ridership season)

  6. Caltrain Modernization

  7. Advanced • Signal System (2015)

  8. Project Description Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) Fiber Optic Network Project Requirements Includes federal mandate (PTC) Improves Caltrain performance Project Partners FRA, UP, CHSRA, JPB

  9. Project Total Cost and Milestones

  10. Peninsula Corridor Electrification Project (2019)

  11. PCEP Project Description* *Proposed project not yet approved, pending environmental clearance

  12. Key Milestones* *Schedule subject to change

  13. Funding Plan Note: 2009 cost estimate

  14. Key Regional Benefits

  15. High-Speed Rail • Partnership

  16. Blended System Vision *Based on LTK computer model simulation (March 2012)

  17. Incremental Investments State of Good Repair & Reliability/Capacity Improvements CalMod Program CBOSS PTC 2015 Corridor Electrification 2019 Downtown Extension (led by TJPA) Additional HSR Improvements HSR Stations Passing Tracks Maintenance Facility System Upgrades (110mph) Additional Caltrain Improvements Longer Trains/ Platforms Level Boarding Note: Orange has no funding plan; Green has funding plan

  18. Q/A