1 / 41

Faculty of Applied Sciences, Dept of Computing, Engineering and Technology

Faculty of Applied Sciences, Dept of Computing, Engineering and Technology. ATF 202 – Project Risk Management. Alan Stafford Project Manager, AMAP/Digital Factory project. Faculty of Applied Sciences, Dept of Computing, Engineering and Technology. ATF 202 – Project Risk Management.

kiser
Télécharger la présentation

Faculty of Applied Sciences, Dept of Computing, Engineering and Technology

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Faculty of Applied Sciences, Dept of Computing, Engineering and Technology ATF 202 – Project Risk Management Alan Stafford Project Manager, AMAP/Digital Factory project

  2. Faculty of Applied Sciences, Dept of Computing, Engineering and Technology ATF 202 – Project Risk Management • Learning outcomes: • What is meant by the term risk in the context of projects • Be aware of the significance of risk and its role in project management • Understand the meaning of Hazard, Risk & Importance • Understand the elements and intent of Risk Analysis and purpose of a risk register • Understand the elements and intent of Risk Management • Cultural nature of risk management

  3. Introduction & reflection • We live with RISK every day • How do you assess risk? • 80 mph on motorway? • 40 mph past a primary school? • Aren’t you making a mental sum of the likelihood of an incident and the consequences? • Do you think differently for something new as opposed to a regular activity? • Do you reflect before action, during and after?

  4. Introduction & reflection • Are we rational about risk? Which is the greater risk, MMR vaccine, Nuclear Power, Flight or everyday Driving ? What about cycling in traffic?

  5. Introduction & reflection • If you were managing a project would the everyday way you deal with risk be good enough? • What if something went fatally wrong? • What if an occurrence adversely affected the project delivery and you incurred a penalty? • What if you left part way through the project?

  6. Risk in Projects What is different about Risk in projects and everyday life? Why are project managers particularly concerned with risk?

  7. Risk in Projects • Projects are one off undertakingsas opposed to operations where things are tried and tested. • Therefore greater likelihood of things going wrong • Consequences (magnitude) can be serious • Need to have a robust approach

  8. Basic concepts of Risk Terminology and concepts

  9. Basic concepts of Risk • What are the hazards, risks & importance for • The turkey? • The cooks “project”? A Hazard =something that has potential to cause harm or loss e.g. delays, cost, failure Risk = “The possibility of suffering harm or loss”(as a result of exposure to the hazard) Importance = Likelihood x Magnitude

  10. Physical financial Schedule Technical failure Acts of nature Human error Business failure due to Political, Economic, Technological, Social, Legal, Environmental changes Risk in Projects • What kinds of risk affect projects? Project Risks (internal) Business Risks (external) Consequence: Project becomes invalid Responsibility of Senior management Part of the Business Case Consequence: Deviation from the project

  11. Physical financial Schedule Technical failure Acts of nature Human error Risk in Projects • What kinds of risk affect projects? Project Risks (internal) Responsibility of the Project Manager Consequence: Deviation from the project

  12. Methodologies To ensure consistency and quality of approach it is normal to follow a recognised methodology

  13. Project Management Institute Methodologies • There are various frameworks and models to help deal with risk and they are all very similar

  14. Methodology All methods can be broken down into : “Risk Analysis” & “Risk Management” We will follow the Project Management Institute model

  15. Methodology

  16. Risk Analysis 1) Risk Identification2) Risk Quantification Two key concepts – Hazard and risk What is a hazard? A Hazard- something that has potential to cause harm to a project e.g. delays, cost, failure What is a Risk? Risk = “The possibility of suffering harm or loss from exposure to a hazard”.

  17. Risk Analysis 1) Risk Identification2) Risk Quantification • What would be the consequences? • For the individuals concerned? • For you & the firm? • For the delivery of the project? Two key concepts, Hazard and risk Hazard? Risk (magnitude x likelihood)?

  18. Risk Analysis 1) Risk Identification2) Risk Quantification Two key concepts, Hazard and risk Hazard? Risk (magnitude x likelihood)?

  19. Risk Analysis 1) Risk Identification2) Risk Quantification • Generic hazards, e.g. • People factors • experience and appropriateness of experience • skills, turn-over rate, level of absenteeism • cultural differences What is a hazard? • Project specific hazards, e.g. • Application specific factors • the nature of the application • complexity of the project • the size and cost of the project

  20. Risk Analysis 1) Risk Identification2) Risk Quantification Hazard & Risk? • Two main approaches • Use of checklists • Brainstorming When would you use each method? Generic hazards Project specific hazards • Knowledge based software is also available to help with the task of hazard identification

  21. Risk Analysis 1) Risk Identification2) Risk Quantification • Once identified risks should be assessed for their possible affect on the project • The level of importance or priority of a risk must also be established. • This is often done by assessing the risk value • Possible to use qualitative/quantitative methods

  22. Risk Analysis 1) Risk Identification2) Risk Quantification Qualitative method of displaying risk Marginal - Minimal effect on project e.g. project approval delays Minor – Some effect on project e.g. delay, change in personnel/suppliers Intermediate – Significant effect on project e.g. cost overrun > 10% , equipment not fit for purpose Major - Severe effect on project e.g. project failure, major injury to personnel,

  23. Risk Analysis 1) Risk Identification2) Risk Quantification Advantage of qualitative methods is that they are easily understood from an overall point of view – showing those risks which need attention. Doesn’t show the “value” of the risk, i.e. the expected cost

  24. Risk Analysis 1) Risk Identification2) Risk Quantification Quantitative method of displaying risk Hazard Likelihood Impact Exposure 1 Changes to the requirements 1 8 8 specification during coding 2 Specification take longer than 3 7 21 expected 3 Staff sickness affecting 5 7 35 critical path activities 4 Staff sickness affecting 10 3 30 non-critical activities

  25. Risk Analysis 1) Risk Identification2) Risk Quantification Quantitative method of displaying risk, can be shown in monetary terms Hazard Likelihood Impact Exposure 1 Changes to the requirements 10% £8k £800 specification during coding 2 Specification take longer than 10% £6k £600 expected 3 Staff sickness affecting 30% £20k £6,000 critical path activities 4 Staff sickness affecting 60% £3k £1,800 non-critical activities

  26. Risk Analysis 1) Risk Identification2) Risk Quantification Output from this process is a Risk Register

  27. Methodology So we have covered the two elements of Risk Analysis using the PMI methodology And have a Risk Register

  28. Methodology Having identified & quantified the risk what are we going to do about it? That’s where Risk Management comes in

  29. Risk Management 3) Response Development4) response Control • Having identified the major risks and allocated priorities, the next task is to decide how to deal with them and there are 3 main options

  30. Risk Management 3) Response Development4) response Control • 3 options • Risk acceptance • Risk avoidance • Mitigation • Risk reduction • Risk transfer • Contingency

  31. Risk Management 3) Response Development4) response Control • Risk acceptance • Risk avoidance • Mitigation • Risk reduction • Risk transfer • Contingency • Unlikely occurrences • Things you can’t do anything about • “Acts of God” • Could also be something where the fix costs more than the problem!

  32. Risk Management 3) Response Development4) response Control • Risk acceptance • Risk avoidance • Mitigation • Risk reduction • Risk transfer • Contingency • Attempts to “Design Out” the risk • Avoid the activity or issue, but • by doing so may introduce another

  33. Risk Management 3) Response Development4) response Control • Risk acceptance • Risk avoidance • Mitigation • Risk reduction • Risk transfer • Contingency • Reduce either likelihood and/or the impact so that it is acceptable, e.g. • ensure expert is used to reduce risk of failure

  34. Risk Management 3) Response Development4) response Control • Risk acceptance • Risk avoidance • Mitigation • Risk reduction • Risk transfer • Contingency • Transfer the impact, e.g. • Insurance policy – known cost v impact • Particularly lends itself to physical risks • Your own car or house insurance • Penalty clause with supplier • Benefit: reduce likelihood & impact

  35. Risk Management 3) Response Development4) response Control • Risk acceptance • Risk avoidance • Mitigation • Risk reduction • Risk transfer • Contingency Activated when a trigger takes place, i.e. Response Control • Holding something in reserve – should the worst happen, e.g. • Reserve funds • Playing safe • Add additional time to uncertain process • Backup supplier/plan

  36. Risk Management 3) Response Development4) response Control Risk management plan is a response to, and an extension of, the Risk Register Details of responses are recorded and the trigger points that bring them into action

  37. Risk Management 3) Response Development4) Response Control Ongoing activity throughout the project, part of the plan-action-monitor-control cycle • No matter how thorough the Risk Analysis unforeseen events will arise. • Control can be broken down into • Passive & • Active responses

  38. Risk Management 3) Response Development4) Response Control • Passive control • Ensuring steps in Response Development are implemented at triggers • Active control • Constant monitoring of triggers • May be part of a risk calendar for example. • Work arounds for unseen occurrences • Last resort/necessary evil – to be avoided.

  39. Summary • Projects areone off undertakings • therefore more risk than normal operations • Terminology– Hazard, Risk, Importance • Methodology– Various standards • Typically consist of elements that can be broken down into: • An example is:

  40. Summary • Risk management is a culture • not a paper exercise or bolt on • has strategic implications, e.g. damage to reputation, loss of future business • Generally more successful if team based • Risk owned by individuals but all contribute • Contributes to “ownership” and “buy-in” • No-Fear culture, i.e. don’t shoot the messenger • Encourage a “learning organisation” • Not a cost but a saving

  41. Faculty of Applied Sciences, Dept of Computing, Engineering and Technology ATF 202 – Project Risk Management Q & A

More Related