ecology and environment, inc. International Specialists in the Environment Georganna B. Collins, gcollins@ene.com. Current Issues in Dredged Material Disposal COPRI BUDM Subcommittee. Outline. Federal Laws Governing Disposal Common Disposal Methods Beneficial Use Examples

knoton
Télécharger la présentation

ecology and environment, inc.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ecology and environment, inc. International Specialists in the Environment Georganna B. Collins, gcollins@ene.com

  2. Current Issues in Dredged Material Disposal COPRI BUDM Subcommittee

  3. Outline • Federal Laws Governing Disposal • Common Disposal Methods • Beneficial Use Examples • Confined Disposal Facilities • Innovative CDF Re-use • Ways to Increase Beneficial Use • CDF Harvesting

  4. Federal Laws Governing Dredged Material Disposal • 300 million cy annually • $500 million to $1 billion spent annually between 2005 to 2011 • Marine Protection, Research, and Sanctuaries Act of 1972 • Clean Water Act • NEPA • Rivers and Harbors Act; Coastal Zone Management Act; Fish and Wildlife Coordination Act; and Endangered Species Act

  5. Common Dredged Material Disposal Methods • Ocean Disposal • In-river Disposal • In-stream • capped • CDFs • Approx 80% • Beneficial Use • Approx 15%

  6. Beneficial Use as Beach Nourishment

  7. Confined Disposal Facilities • Engineered diked impoundments to provide containment and control dredging operation produced water • three types of CDFs: Upland, Shoreline, and Island. • Managed over time to gain additional capacity through DMMP • Eventually run out of capacity • ERDC 2010 Study • Sustainable Confined Disposal Facilities for Long-term Management of Dredged Material (ERDC TN-DOER-D10).

  8. CDF Construction

  9. Innovative CDF Re-Use

  10. Increase Beneficial Use • Multi-purpose dredging projects • Policy, Process, Practice • National Dredging Team • Regional Dredging Team • Local Planning Groups • Houston-Galveston Navigation Channels Texas Project • Cost Benefit Evaluation & Application of Federal Standard

  11. CDF Harvesting • ERDC three factors: • 1. Minimize dredging volume placed into the CDF. • 2. Manage the CDF to maximize capacity. • 3. Maximize recovery/removal of material. • Material readily available • Avoids comparison with Federal Standard • Issues to Resolve

  12. Issues to Resolve • Volume and suitability • Access • Ownership • Others

  13. Case Studies 1969, Philadelphia District excavated from CDFs to provide more capacity New York District is investigating feasibility of centralized public dredged material processing facility where material is brought, processed, and distributed Seattle District tests material for BU and supports interagency forum for re-use Mobile District has a full time PM dedicated to finding BU opportunities since they are out of capacity Galveston District constructing CDFs 20 years ahead of schedule due to excess sediments

  14. Great Lakes Commission CDF Harvesting • 2003 USACE/EPA Study & Report on Great Lakes CDFs • Effects on ecosystem and concern for potential contaminant leaking and harm to wildlife using a CDF • 90 million cy contaminated sediments removed from the ecological system and 99.9% contaminants contained • Potential for harvesting clean sediments for re-use • Web site and report

  15. Current CDF Harvesting Plan for Coastal Louisiana • 60% dredged volume in Gulf of Mexico region • Severe sediment deficit for marsh restoration • CDFs at or reaching capacity

  16. Current Disposal Issues For example: Calcasieu Ship Channel Project does not have adequate dredged material disposal capacity, gross dredging to be 97 million cy, current CDF capacity is 5 million, DMMP looked at 4 alternatives: A. no action B. create 6,306 ac marsh and expand CDF C. create 10,030 ac marsh and expand CDF D. ocean dredged material disposal Alternative B was preferred with cost estimate of $865,863,000

  17. Estimated Dredged Material Volumes • 650 million cy • vs 49.5 -100 million cy needed annually for marsh restoration • Additional future sediments from annual maintenance dredging • NO District 91 million cy • Galveston 25.9 million cy • Mobile 27 million cy