1 / 22

ATMES Spring Meeting April 26-27, 2012 Myrtle Beach, South Carolina International Projects

ATMES Spring Meeting April 26-27, 2012 Myrtle Beach, South Carolina International Projects . Finding the Right Project Delivery Model. Company History. | Acquisition of | exp. China. | Portland, OR. | Singapore. 1977. 2003. 2004. 2009. 2010. 2012. | Shanghai.

koen
Télécharger la présentation

ATMES Spring Meeting April 26-27, 2012 Myrtle Beach, South Carolina International Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATMES Spring Meeting April 26-27, 2012 Myrtle Beach, South Carolina International Projects

  2. Finding the Right Project • Delivery Model

  3. Company History |Acquisition of | exp. China |Portland, OR |Singapore 1977 2003 2004 2009 2010 2012 |Shanghai |C3 Eco Hospitality Design |Greenville, SC

  4. Project Delivery Project Delivery Options / Terminology • Conventional Contract (Design / Bid / Build) • EPC / Design & Build • Management Contract • EPCM – Engineering, Procurement & Construction Management (Agency – Not at Risk) • EPCM with Guaranteed Maximum Price (GMP) (At Risk)

  5. Project Delivery Key Drivers for Choice Project Delivery • Safety • Cost Certainty • Quality • Schedule / Program Delivery • Balance of Risk

  6. Project Delivery – Option 1 Option 1 – Conventional Contract - Design / Bid / Build Client Project Delivery Experience Main Contractor Design Consultant (Full Design) Sub Contractors Suppliers

  7. Project Delivery – Option 1 Option 1 – Conventional Contract - Design / Bid / Build • Client directly employs consultants • Client directly employs the main contractor • Main contractor employs subcontractors and suppliers • Main contractor has no design responsibility • Main contractor has a start and finish date • Main contractor provides a lump sum bid • Design must be complete before the main contractor tenders

  8. Project Delivery – Option 1 Option 1 – Conventional Contract - Design / Bid / Build • Advantages • Fixed lump sum offer (but not cost certainty) • Cost overruns are borne by contractor • Client controls his design • Disadvantages • Contractor prices full risk premium • Contractor will mark-up subcontractor/supplier prices • Client must clearly define scope • Changes are expensive for the client • Client at risk for disputes over claims and variations • Safety and quality may be compromised • Schedule is elongated due to tender process for main contractor • Client must provide a full team to manage the contract and main contractor

  9. Project Delivery – Option 2 Option 2 – Design & Build / EPC - (Fixed Price Lump Sum) Client Project Delivery Experience Design Consultant (Concept Only) D&B/EPC Contractor Design Team Sub Contractors Suppliers

  10. Project Delivery – Option 2 Option 2 – Design & Build / EPC - (Fixed Price Lump Sum) • Client directly employs consultants for concept • Client directly employs the main D&B contractor • D&B contractor employs design team, subcontractors and suppliers • Main contractor has design responsibility • Main contractor has a start and finish date • Main contractor provides a lump sum bid • Concept design must be complete before the main contractor tenders

  11. Project Delivery – Option 2 Option 2 – Design & Build / EPC - (Fixed Price Lump Sum) • Advantages • Fixed lump sum offer • One party (contractor) with overall cost and schedule • Disadvantages • Contractor prices full risk premium • Contractor will mark-up subcontractor/supplier prices • Risk of scope gaps if Client is not able to clearly define scope • Client has no visibility on design • Changes are expensive for the Client • Client at risk for disputes over claims and variations • Safety and quality may be compromised • Client must provide a full team to manage the contract and main contractor

  12. Project Delivery – Option 3 Option 3 – Management Contract Project Delivery Experience Client Management Contractor Design Consultant Sub Contractor Suppliers

  13. Project Delivery – Option 3 Option 3 – Management Contract • Client directly employs consultants • Client directly employs the management contractor • Management contractor employs subcontractors and suppliers • Management contractor has no design responsibility • Management contractor provides a detailed schedule • Management contractor provides a fixed fee for Indirects (staff, general conditions / preliminaries) together with mark-up % on packages • Design and construction can be overlapped to reduce the schedule

  14. Project Delivery – Option 3 Option 3 – Management Contract • Advantages • Client controls the design • Fixed fee on Contractors indirect (staff, GC’s, mark-up) • Disadvantages • Contractor prices risk premium on subcontractors performance • No incentive for contractor to keep costs down as he is paid a mark-up on subcontract packages • Client is responsible for scope gaps • Client is responsible for design deficiencies • Client is responsible for variations / claims etc. • No cost certainty until all packages are bought out • Changes are expensive for the Client

  15. Project Delivery – Option 4 Option 4 – EPCM (Agency) Client Project Delivery Experience EPCM Contractor Sub Contractors Suppliers

  16. Project Delivery – Option 4 Option 4 – EPCM (Agency) • Client directly employs consultant for Concept / Basic Design • Client directly employs the Engineering / Construction Manager • Client employs subcontractors and suppliers • EPCM contractor has design responsibility • EPCM contractor prepares a detailed schedule • Design and construction can be overlapped to reduce the program

  17. Project Delivery – Option 4 Option 4 – EPCM (Agency) • Advantages • Client is engaged in the design at concept and detailed phases • Maximum overlap between engineering design, procurement & construction • Ability to make scope changes without penalty • Client may supplement his team resources through EPCM contractor • Client can control fee budget on EPCM contractors personnel • GC’s are pass through cost to client • EPCM contractor is responsible for schedule • Procurement is open book • Cost of risk is borne by client (no premium by contractor) • Client can control “design to budget” (note 1) • Non-adversarial team approach • Disadvantages • No cost certainty until all packages are bought out (but see note 1) • Client has risk on subcontractor performance • Client retains risk for disputes, variations and claims

  18. Project Delivery – Option 5 Option 5 - EPCM (At Risk) - With Guaranteed Maximum Price Project Delivery Experience Client Technical Consultant (Concept) EPCM Contractor Sub Contractors Suppliers

  19. Project Delivery – Option 5 Option 5 - EPCM (At Risk) - With Guaranteed Maximum Price • Client directly employs consultant for Concept / Basic Design • Client directly employs the Engineering / Construction Manager • Client employs subcontractors and suppliers • EPCM contractor has design responsibility • EPCM contractor prepares a detailed schedule • EPCM contractor provides a fixed fee for staff, overheads and profit • Design and construction can be overlapped to reduce the program • Client agrees GMP with EPCM contractor at an agreed point during design / procurement phase • EPCM contractor takes responsibility for cost overrun on agreed formula • Client and contractor agree split on savings to agreed formula

  20. Project Delivery – Option 5 Option 5 - EPCM (At Risk) - With Guaranteed Maximum Price • Advantages • Client is engaged in the design at concept and detailed phase • Maximum overlap between engineering design, procurement & construction • GC’s are normally subject to mark-up or fixed lump sum • EPCM contractor is responsible for schedule • Disadvantages • No cost certainty until GMP is agreed • Risk of not being able to agree GMP • Client must fully define scope prior to agreement of GMP • Contractor will build risk premium into GMP • Post GMP changes may be expensive • Client at risk for disputes over claims and variations post GMP

  21. Project Delivery Options

  22. Century 3 Inc. One Century Place, Greer, S.C. 29651 USA Phone: 1 (864) 879-0123 I Fax: 1 (864)848-2505 www.century3inc.com

More Related