1 / 40

Toward a Proton Plan Eric Prebys Fermilab Accelerator Division

Toward a Proton Plan Eric Prebys Fermilab Accelerator Division. Outline. Finley Report Background Linac Booster Main Injector Proton Limitations Projected Proton Demands Experimental Requests Proton Economics Operational Issues and Current Performance Recent Improvements The Plan

kramerl
Télécharger la présentation

Toward a Proton Plan Eric Prebys Fermilab Accelerator Division

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Toward a Proton PlanEric PrebysFermilab Accelerator Division

  2. Outline • Finley Report • Background • Linac • Booster • Main Injector • Proton Limitations • Projected Proton Demands • Experimental Requests • Proton Economics • Operational Issues and Current Performance • Recent Improvements • The Plan • The process • Near term • Issues for the next year • Longer term decisions PAC Meeting, December 12, 2003 - Prebys

  3. Proton Team (“Finley Report”) • Group formed in early 2003 to study proton demands and needs for the “near” future (through ~2012 or so), in the absence of a proton driver. • Work culminated in a report to the director, available at www.fnal.gov/directorate/program_planning/studies/ProtonReport.pdf • This work will form the basis of “The Proton Plan”. • No big surprises [see P. Kasper “Getting Protons to NuMI (It’s a worry)”, 2001]. PAC Meeting, December 12, 2003 - Prebys

  4. Preac(cellerator) and Linac “New linac”- 800 MHz “p cavities” accelerate H- ions from 116 MeV to 400 MeV “Preac” - Static Cockroft-Walton generator accelerates H- ions from 0 to 750 KeV. “Old linac”- 200 MHz “Alvarez tubes” accelerate H- ions from 750 keV to 116 MeV Preac/Linac can deliver about 45 mA of current for about 40 usec at a 15 Hz repetition rate (not a bottleneck) PAC Meeting, December 12, 2003 - Prebys

  5. Booster • The 15 Hz cycle sets a fundamental clock rate for the entire complex. • One full booster “batch” sets a fundamental unit of protons throughout the accelerator complex (max 5E12). • 400 MeV Linac H- beam is injected into booster. • The lattice magnets in the Booster form a 15 Hz resonant circuit, setting the instantaneous cycle rate, but ramped elements limit the average repetition rate to somewhat lower. • From the Booster, beam can be directed to • The Main Injector • MiniBooNE • The Radiation Damage Facility (RDF) • A dump. PAC Meeting, December 12, 2003 - Prebys

  6. Main Injector • The Main Injector can accept 8 GeV protons OR antiprotons from • Booster • The anti-proton accumulator • The Recycler (which shares the same tunnel) • It can accelerate protons to 120 GeV (in a minimum of 1.4 s) and deliver them to • The antiproton production target. • The fixed target area. • (soon) The NUMI beamline. • It can accelerate protons OR antiprotons to 150 GeV and inject them into the Tevatron. • The Main Injector holds six booster batches, in the absence of exotic loading schemes (slip stacking, RF barrier, etc). • It’s envisioned that two slipstacked batches will be used for stacking and the rest for NUMI and/or switchyard 120. PAC Meeting, December 12, 2003 - Prebys

  7. What Limits Total Proton Intensity? • Maximum number of Protons the Booster can stably accelerate: 5E12 • Maximum average Booster rep. Rate: currently 7.5 Hz, may have to go to 10 Hz for NuMI+ (full) MiniBooNE • (NUMI only) Maximum number of booster batches the Main Injector can hold: currently 6 in principle, possibly go to 11 with fancy loading schemes in the future • (NUMI only) Minimum Main Injector ramp cycle time (NUMI only): 1.4s+loading time (at least 1/15s*nbatches) • Losses in the Booster: • Above ground radiation • Damage and/or activation of tunnel components Our biggest worry at the moment!!!! PAC Meeting, December 12, 2003 - Prebys

  8. Fermilab Program • Major proton consumers (in order of demand): • MiniBooNE • NuMI (starting 2005) • Pbar production • Switchyard 120 Interest in Continuing MiniBooNE (or other 8 GeV line exp.) PAC Meeting, December 12, 2003 - Prebys

  9. Preparing for the Neutrino Program • Shielding and new radiation assessment • Vastly improved loss monitoring. • Numerous hardware improvements • e.g new extraction septum and power supply • New tuning strategies. PAC Meeting, December 12, 2003 - Prebys

  10. Proton Demand PAC Meeting, December 12, 2003 - Prebys

  11. Demand: Summary • Pbar production • current: 0.9E16 p/hr • Max (slipstacking): 1.8E16 p/hr • MiniBooNE • current: ~3.5E16 p/hr • Request: 9E16 p/hr [5E20 p/yr] • NuMI • Baseline: 4.5E16 p/hr [2-2.5 p/yr] • Exotic loading schemes (~2006): ~7E16 p/hr [4E20 p/yr] • Occasionally claim: 14E16 p/hr [8E20 p/yr] • 2005 • Max pbar + MiniBooNE + baseline NuMI: ~16E16 p/hr (~4 times current limit!) What MINOS believes they are getting PAC Meeting, December 12, 2003 - Prebys

  12. Understanding Proton Economics: Proton Timelines • Everything measured in 15 Hz “clicks” • Minimum Main Injector Ramp = 22 clicks = 1.4 s • MiniBoone batches “sneak in” while the MI is ramping. • Some Booster elements require 2 null prepulses before each 15 Hz batch train. • Cycle times of interest • Min. Stack cycle: 1 inj + 22 MI ramp = 23 clicks = 1.5 s • Min. NuMI cycle: 6 inj + 22 MI ramp = 28 clicks = 1.9 s • Full “Slipstack” cycle (one, scenario, total 11 batches): 6 inject+ 2 capture (6 -> 3)+ 2 inject+ 2 capture (2 -> 1)+ 2 inject+ 2 capture (2 -> 1)+ 1 inject+ 22 M.I. Ramp----------------------39 clicks = 2.6 s (More protons but longer cycle time) PAC Meeting, December 12, 2003 - Prebys

  13. Proton Scenarios Booster Hardware Issues Booster Activation Issues PAC Meeting, December 12, 2003 - Prebys

  14. The Bad News: Booster Tunnel Radiation Levels Any further increase in protons must come without increasing losses. PAC Meeting, December 12, 2003 - Prebys

  15. Operational Issues: Limiting Booster Losses Maximum based on trip point 100 second running loss sums (normalized to trip point) Also limit total booster average power loss (B:BPL5MA) to 400W. Present rate PAC Meeting, December 12, 2003 - Prebys

  16. How Have we been doing Power loss Total Protons Energy loss per proton (reduced by >3!) BooNE turn-on August 2003 PAC Meeting, December 12, 2003 - Prebys

  17. Solving Problems: Extraction Doglegs • Each of the two Booster extraction septa has a set of vertical dogleg magnets to steer the beam around it during acceleration. • These magnets have an edge focusing effect which distorts the horizontal injection lattice: • 50% increase in maximum b • 100% increase in maximum dispersion. • Harmonic contributions. • This discovery was a direct result of increased Beam Physic involvement. • Effect goes like I2. Now tune to minimize. • Modified one of the two extraction regions during the recent shutdown to reduce problem (40% total reduction in lattice deviations) • Will do second next year • In then end, close to an 80% reduction in distortions Septum Dogleg Magnets PAC Meeting, December 12, 2003 - Prebys

  18. Solving Problems: New Collimator System • Should dramatically reduce uncontrolled losses Basic Idea… A scraping foil deflects the orbit of halo particles… …and they are absorbed by thick collimators in the next periods. PAC Meeting, December 12, 2003 - Prebys

  19. Other Major Shutdown Work • New Linac Lambertson • Should improve 400 MeV line optics • Simplifies linac tuning • Reduce losses • Four Large aperture Booster extraction magnets (EDWA) • Should reduce losses at extraction. • Complete vertical alignment network of Booster • First in ??? Years • Will be used to align entire machine • New power supply for second extraction region • Part of overall upgrade project • Linac water system upgrade • Booster vacuum system upgrade • Numerous other jobs PAC Meeting, December 12, 2003 - Prebys

  20. How are we doing? • We’re getting there, but … Alignment problem found Protons/pulse to stacking Protons/pulse to MB p/hr total J/E12 Energy lost PAC Meeting, December 12, 2003 - Prebys

  21. Formulating a Plan • The lab has recognized that the proton demands of the experimental program are significant, if not daunting, and will require substantial efforts to meet. • As the financial burden of Run II begins to ease, it’s envisioned that financial resources on the order of $20M will be diverted to these efforts over the next few years. • We are in the process of putting together a plan with the maximum likelihood of reaching these goals. • Ultimate goal is to generate a project similar to Run II • However, because the future (MiniBooNE) is already here, such a plan will necessarily have near and long term components. PAC Meeting, December 12, 2003 - Prebys

  22. Near Term Priorities • Optimizing Booster for improved lattice: • Tuning and characterizing 400 MeV line (Linac to Booster). • Tuning Booster orbit to minimize losses. • Commission Collimators: • Once we have Booster optimized to the new lattice, we will begin to exercise the collimator system. • Estimate about 2 months to bring into standard operation. • Aperture Improvments: • Alignment • Complete (magnet) vertical network done over shutdown • Will analyze and effect moves when opportunities arise • Working on a systematic method for aligning straight sections. • Orbit control • Ramped orbit control program has been written. • Will be commissioned soon (new personnel) • Important now that collimator is in place. • Prototype RF Cavities • Two large aperture prototype cavities have been built, thanks to the help of MiniBooNE and NuMI universities. • We will install these as soon as they are ready to replace existing cavities which are highly activated. • It’s hoped this work will allow us to reach the MiniBooNE baseline this year. PAC Meeting, December 12, 2003 - Prebys

  23. Issues over the Next Year • Linac Characterization and Reliability • Increase instrumentation of old linac to study instabilities. • Develop set of performance parameters. • Booster improvements. • Prepare for modification of second extraction region • New septum • Modified dogleg magnets • On track for next year’s shutdown. • Injection Bump (ORBUMP) Power Supply • Existing supply a reliability worry. • Limited to 7.5 Hz • Building new supply, capable of 15 Hz. • Aiming for next year’s shutdown. • Under consideration: New ORBUMP Magnets • Existing magnets limited by heating to 7.5 Hz • Working on a design for cooled versions. • These, with a new power supply, will make the Booster capable of sustained 15 Hz operation. • Biggest decision for the near future. PAC Meeting, December 12, 2003 - Prebys

  24. Multibatch Timing • In order to Reduce radiation, a “notch” is made in the beam early in the booster cycle. • Currently, the extraction time is based on the counted number of revolutions (RF buckets) of the Booster. This ensures that the notch is in the right place. • The actual time can vary by > 5 usec! • This is not a problem if booster sets the timing, but it’s incompatible with multi-batch running (e.g. Slipstacking or NuMI) • We must be able to fix this total time so we can synchronize to the M.I. orbit. • This is called “beam cogging”. PAC Meeting, December 12, 2003 - Prebys

  25. Active cogging • Detect slippage of notch relative to nominal and adjust radius of beam to compensate. Allow to slip by integer turns, maintaining the same total time. • Efforts in this area have been recently increased, with the help of a Minos graduate student (R. Zwaska). • Aim to get working in the next few months PAC Meeting, December 12, 2003 - Prebys

  26. Long Term, Big $$ Ideas Under Consideration • New Booster RF system: • Larger aperture cavities (two prototypes will be installed soon). • New solid state preamps and modulators (would pay for itself in a few years). • New Linac front end: • Replace Preac and 200 MHz linac with RFQ feeding 400 MHz klystron-driven linac. • Addresses 7835 Amplifier Tube Problem • Possible part of proton driver? • Reduce Main Injector ramp time: • Still needs time to load protons • Needs to fit in with stacking. • Necessary to get the kind of protons that off-axis is talking about. PAC Meeting, December 12, 2003 - Prebys

  27. Summary • We have a good understanding of the proton demands over the next few years in the context of the limitations of the Fermilab accelerator complex. • We have made remarkable progress toward meeting these demands, but are still falling well short. • We are pursuing an ambitious plan to attempt to meet these demands, but cannot yet guarantee its success. • The next few months will be very important. PAC Meeting, December 12, 2003 - Prebys

  28. Extra Slides for Questions PAC Meeting, December 12, 2003 - Prebys

  29. Multi-turn Ion Injection 4 pulsed “ORBUMP” magnets Circulating Beam DC “Septum” Beam at injection 400 MeV H-beam from LINAC Stripping foil • At injection, the 40 mA Linac H- beam is injected into the Booster over several “turns” (1 turn ~5E11). • The orbit is “bumped” out, so that both the injected beam and the circulating beam pass through a stripping foil, after which they circulate together. • At the moment, heating in the ORBUMP and power supply magnets limit our average rep rate (including prepulses to ~7.5 Hz). PAC Meeting, December 12, 2003 - Prebys

  30. Booster RF System • 18 more or less original RF cavities and power supplies. • tunable from 38 to 53 MHz during acceleration. • 2 ¼” drift tube one of our primary aperture restrictions; new design being considered. • Existing cavities might overheat at >7.5Hz. Need to re-commission cooling • In-tunnel Power Amplifiers (PA’s) are by far the highest maintenance item in the Booster PAC Meeting, December 12, 2003 - Prebys

  31. Booster Extraction (Two Extraction Regions) DC “doglegs” work with ramped 3-bump (BEXBUMP) to maintain 40p aperture below septum Fast (~40 ns) kickers PAC Meeting, December 12, 2003 - Prebys

  32. Typical Booster Cycle Various Injected Intensities Transition Intensity (E12) Energy Lost (KJ) Time (s) PAC Meeting, December 12, 2003 - Prebys

  33. Differential Loss Monitor Example: Collimators in – Collimators Out Collimator Position Relative Loss Time Position PAC Meeting, December 12, 2003 - Prebys

  34. Dead Dog Studies • Took advantage of recent TeV Magnet failure to raise the Long 13 (dump) septum and turn off the associated dogleg. • Doglegs almost exactly add, so this should reduce the effect by almost half. • The mode of operation prevents short batching, booster study cycles and RDF operation. • Had about 36 hours of study in this mode. • Bottom Line: major improvement. PAC Meeting, December 12, 2003 - Prebys

  35. Transmission After Tuning March 6, 7 turns, 1 dog March 3, 7 turns, both dogs PAC Meeting, December 12, 2003 - Prebys

  36. Transmission with One Dogleg % Injected Charge (E12) PAC Meeting, December 12, 2003 - Prebys

  37. Record Running w/o Dogleg PAC Meeting, December 12, 2003 - Prebys

  38. The 7835 Power Triode – Our BIG Worry • Very complex technology • RF, material science, vacuum, chemistry • Similar to other tubes made by Burle • 4616 & 4617 • 7835 only used in the scientific community. • One military user for 4617 • Quality varies from decade to decade PAC Meeting, December 12, 2003 - Prebys

  39. Tube Throughput with Burle • Median lifetime: 16 months • Recent lifetime: Less! (possibly related to vacuum problems) • We need about 3.41 tubes/year to maintain • Assuming historical median • With present tubes: twice that. • Burle now can make/rebuild ~20/year • Critical path: Final bakeout; two stands, 3-5 weeks bakeout • Also of concern: Supplier delivery time (e.g., ceramics, cathode) • Recently had four failures for one success!! • Delivery time: ~8 months, • But, often 12 months! • This is obviously a worry. PAC Meeting, December 12, 2003 - Prebys

  40. Present 7835 Power Tube Situation • We’ve received 5 tubes since the last review • Only two delivered from Burle, after numerous failures • Two borrowed from BNL • One borrowed from Argonne • We now have one spare; we have frequently had zero; we have never had two. • Next one due “in August”. PAC Meeting, December 12, 2003 - Prebys

More Related