This update addresses key issues within the TX SET framework, including the misuse of the CSA By-Pass flag by Customer Representatives (CRs) without established Customer Service Agreements (CSAs). Important new issues are introduced, such as the need for indicators on enrollment responses and usage transactions for Advanced and Master Meters (I077), and the establishment of the REF~JH~I designation for Distributed Renewable Generation (I078). The change control process is outlined, noting approvals, nullified controls, and upcoming discussions. The TX SET meeting is scheduled for June 17-18.
E N D
TX SET Update to RMS June 11, 2008
Issues Under Review • I075 – CSA-By Pass flag is being used by CRs when they do not have a CSA established • Language in the 814_24 Move-out guide states: “The owner of CSA could use the code to de-energize a premise (Only if the CSA REP is also the REP of Record at the time of the Move-Out effective date).”
Which By-pass Flag was used?2W (CSA By-pass) or B44 (Remove meter)?
New Issues • I077 – Add an indicator to enrollment response and usage transactions to indicate presence of an Advanced Meter and or Master Meter • I078 – Establish that the REF~JH~I (“Ignore Loop”) is designated for Distributed Renewable Generation monthly out-flow only
Change Control Call • 1 Change Control Nullified • 13 Change Controls Approved • 3 Change Controls Tabled for Further Discussion See TX SET website to for Change Controls
Distributed Renewable Generation Draft RMGRR • Draft RMGRR was emailed out to TX SET and PWG list serves on May 22 requesting comments • Original goal was to submit the RMGRR by June 17th for RMS vote on July 9th • The schedule has been postponed due to the DG Task Force reconvening to resolve how to handle IDR metering for DRG <50 KW • DGTF to meet on June 24th at ERCOT
Other Work in Progress • Implementation Guide Examples • Update Transaction Examples and Prepare to Pull Examples Out of I.G.s at Next Release • Review of Nodalized Protocol Sections 19 and 15 • Review/Clean-up of RMG Section 7 to ensure consistency with TX SET v3.0 • Monitoring Advanced Metering Project for TX SET Changes
The next TX SET meeting will be held on June 17 – 18 at Green Mountain Energyin downtown Austin Any questions?