This document presents a detailed breakdown of costs associated with steel beams, including material, labor, and equipment expenses. The calculations demonstrate material costs based on weight and conversions from pounds to tons. Key elements such as sales tax, overhead and profit (O&P), labor tax, and equipment costs are considered for accurate budget estimation in metal work projects. This analysis serves as a guide for engineers and contractors in estimating project costs efficiently.
E N D
MetalsHomework #4 Frank Schornagle
RS Means • 05 12 23.77 0201New Material Cost: 100%*$2250 + $2250 = $4500 • 05 12 23.77 5399New Labor Cost: 100% * $273 + $273 = $546
7-1 Walk Through - Part A • Weight of beam: 40 lb/ft x 20 ft = 800 lb • Conversion lb -> tons: 800lb / 2000 lb = 0.4 tons • Sales Tax: 6% x $1800 = $108 • O&P: 15% x $2226.8 = $334.02 • Material Cost: $4500 x 0.4 = $1800 • Equipment Cost: $251 x 0.4 = $100.40 • Labor Cost: $546 x 0.4 = 218.40
Beam Measurements http://www.flangebar.com/?content=barinfo&pdata=d_flangesizes
Materials List W12 x 35 C1 -> C2 : 300” –8.06” – (11.94”/2) = 285.97” Conversion: 285.97 in * 1ft/12in = 23.831 ft W12 x 35 C1 -> C2 : 300” –(6.535”/2) – (8.005”/2) = 292.73” Conversion: 292.73 in * 1ft/12in = 24.394 ft
7-6, 7-7 24.311' long W12 x 72 Beam 24.311 ft x 72lb/ft = 1750.392 lb
RS Means • 05 12 23.77 0201New Material Cost: 50%*$2250 + $2250 = $3375 • 05 12 23.77 5396New Labor Cost: 25% * $273 + $273 = $341.25
7-5, 7-6, 7-7 Full Solution • Conversion lb -> tons: 32787.353lb / 2000 lb = 16.394 tons • Sales Tax: 6% x $55328.66 = $3319.72 • Labor Tax: 28% x $5594.34 = $1566.42 • O&P: 22% x $69923.95 = $15383.27 • Material Cost: $3375 x 16.394 tons = $55328.66 • Equipment Cost: $251 x 16.394 tons = $4114.81 • Labor Cost: $341.25 x 16.394 tons = $5594.34