Get the latest updates on the Intelligent Transportation Systems (ITS) projects from FDOT District 6. This report outlines advancements in programs including US 1/SR 5, I-395/SR A1A & Port of Miami, and SR 826. Key components include the installation of Dynamic Message Signs (DMS), CCTV cameras, and traffic detectors aimed at improving transportation efficiency and safety. Proposed operational updates also highlight staff transitions and contract management changes as of December 2007. For inquiries, contact Manuel Fontan, ITS Project Manager.
E N D
FDOT District 6ITS Project Update Manuel Fontan, E.I. ITS Project Manager
Outline • ITS Program Updates • Other Deployment Updates • ITS Operations Contract Updates • Operational Updates
ITS Program Updates • US 1/SR 5 • Estimated Completion Date: April 25, 2008 • 4 DMS • 17 CCTV • 6 Detectors
ITS Program Updates • I-395/SR A1A & Port of Miami • Letting Date: October 9, 2007 • 1 DMS (Port of Miami) • 8 CCTV (Mainline); 2 CCTV (Port of Miami) • 10 Detectors (Mainline)
ITS Program Updates • SR 826 • Letting Date: October 9, 2007 • 3 DMS • 6 New CCTV (4 on Interchanges and 2 for DMS Verification); 4 Existing • 37 Detectors
ITS Program Updates • ITS Technical Consultant Services • Letting Date: Approximately May 2008 • Executed: Approximately July 2008 • Budget Amount: $ 1.5 Million/5 Years
ITS Program Updates • 95 Express (Miami-Dade County) – Phase 1A (SR 112 to GGI) • Design Build Initiated • Equipment/Devices: • Tow • CCTV • Toll Rate Signs • Lane Status Signs (1 Line DMS) • Estimated Completion Date: Summer 2008 • Estimated Completion Date - All phases: Summer 2010 • Ramp Metering • Initial metering will be for the 8 NB ramps on the 95 Express Lanes limits • Turned on simultaneously with 95 Express Lanes
Other Deployment Updates • June 2008 • FDOT District 6 SunGuide™ TMC Intranet Release 2.0 • RRDIS Release 2.0
ITS Operations Contract Update Notice to Proceed: December 17, 2007 Staff Transitioned: January 14, 2008 24 positions • IT: 5 Positions • 1 IT/ITS Maintenance Manager • 1 Network Administrator • 2 IT Administrators • 1 Software Systems • TMC Operations: 16 Positions • 1 TMC Manager • 1 Assistant TMC Manager • 1 Road Ranger Contract Manager • 2 Shift Supervisor • 2 TMC Lead Operators • 9 TMC Operators • Contract Support: 3 Positions • 1 Contract Project Manager • 1 Office Manager • 1 Receptionist (Front Desk)
Operational Updates February 2008
Operational Updates February 2008
Operational Updates February 2008
Questions? Manuel Fontan, E.I. FDOT District 6 (305) 499 - 2493 Manuel.Fontan@dot.state.fl.us