1 / 59

Ch. 9: Capital Budgeting Decision Criteria

Ch. 9: Capital Budgeting Decision Criteria.  2002, Prentice Hall, Inc. Capital Budgeting : the process of planning for purchases of long-term assets. example : Suppose our firm must decide whether to purchase a new plastic molding machine for $125,000. How do we decide?

Télécharger la présentation

Ch. 9: Capital Budgeting Decision Criteria

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ch. 9: Capital BudgetingDecisionCriteria  2002, Prentice Hall, Inc.

  2. Capital Budgeting: the process of planning for purchases of long-term assets. • example: Suppose our firm must decide whether to purchase a new plastic molding machine for $125,000. How do we decide? • Will the machine be profitable? • Will our firm earn a high rate of return on the investment?

  3. Decision-making Criteria in Capital Budgeting How do we decide if a capital investment project should be accepted or rejected?

  4. Decision-making Criteria in Capital Budgeting • The Ideal Evaluation Method should: a) include all cash flows that occur during the life of the project, b) consider the time value of money, c) incorporate the required rate of return on the project.

  5. Payback Period • How long will it take for the project to generate enough cash to pay for itself?

  6. (500) 150 150 150 150 150 150 150 150 8 7 0 1 2 3 4 5 6 Payback Period • How long will it take for the project to generate enough cash to pay for itself?

  7. (500) 150 150 150 150 150 150 150 150 8 7 0 1 2 3 4 5 6 Payback Period • How long will it take for the project to generate enough cash to pay for itself? Payback period = 3.33 years.

  8. Payback Period • Is a 3.33 year payback period good? • Is it acceptable? • Firms that use this method will compare the payback calculation to some standard set by the firm. • If our senior management had set a cut-off of 5 years for projects like ours, what would be our decision? • Accept the project.

  9. Drawbacks of Payback Period • Firm cutoffs are subjective. • Does not consider time value of money. • Does not consider any required rate of return. • Does not consider all of the project’s cash flows.

  10. (500) 150 150 150 150 150 (300) 0 0 8 7 0 1 2 3 4 5 6 Drawbacks of Payback Period • Does not consider all of the project’s cash flows. • Consider this cash flow stream!

  11. (500) 150 150 150 150 150 (300) 0 0 8 7 0 1 2 3 4 5 6 Drawbacks of Payback Period • Does not consider all of the project’s cash flows. • This project is clearly unprofitable, but we would accept it based on a 4-year payback criterion!

  12. Discounted Payback • Discounts the cash flows at the firm’s required rate of return. • Payback period is calculated using these discounted net cash flows. Problems: • Cutoffs are still subjective. • Still does not examine all cash flows.

  13. (500) 250 250 250 250 250 1 2 3 4 5 0 Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.30

  14. (500) 250 250 250 250 250 1 2 3 4 5 0 Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.301 year 280.70

  15. (500) 250 250 250 250 250 1 2 3 4 5 0 Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.301 year 280.70 2 250 192.37

  16. (500) 250 250 250 250 250 1 2 3 4 5 0 Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.301 year 280.70 2 250 192.372 years 88.33

  17. (500) 250 250 250 250 250 1 2 3 4 5 0 Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.301 year 280.70 2 250 192.372 years 88.33 3 250 168.74

  18. (500) 250 250 250 250 250 1 2 3 4 5 0 Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.301 year 280.70 2 250 192.372 years 88.33 3 250 168.74 .52 years

  19. (500) 250 250 250 250 250 1 2 3 4 5 0 The Discounted Payback is 2.52 years Discounted Payback Discounted YearCash FlowCF (14%) 0 -500 -500.00 1 250 219.301 year 280.70 2 250 192.372 years 88.33 3 250 168.74 .52 years

  20. Other Methods 1) Net Present Value (NPV) 2) Profitability Index (PI) 3) Internal Rate of Return (IRR) Each of these decision-making criteria: • Examines all net cash flows, • Considers the time value of money, and • Considers the required rate of return.

  21. n t=1 S FCFt (1 + k) NPV = - IO t Net Present Value • NPV = the total PV of the annual net cash flows - the initial outlay.

  22. Net Present Value • Decision Rule: • If NPV is positive, accept. • If NPV is negative, reject.

  23. NPV Example • Suppose we are considering a capital investment that costs $250,000 and provides annual net cash flows of $100,000 for five years. The firm’s required rate of return is 15%.

  24. (250,000) 100,000 100,000 100,000 100,000 100,000 0 1 2 3 4 5 NPV Example • Suppose we are considering a capital investment that costs $250,000 and provides annual net cash flows of $100,000 for five years. The firm’s required rate of return is 15%.

  25. Net Present Value (NPV) NPV is just the PV of the annual cash flows minus the initial outflow. Using TVM: P/Y = 1 N = 5 I = 15 PMT = 100,000 PV of cash flows =$335,216 - Initial outflow:($250,000) = Net PV$85,216

  26. NPV with the HP10B: • -250,000 CFj • 100,000 CFj • 5 shift Nj • 15 I/YR • shift NPV • You should get NPV = 85,215.51.

  27. NPV with the HP17BII: • Select CFLO mode. • FLOW(0)=? -250,000 INPUT • FLOW(1)=? 100,000 INPUT • #TIMES(1)=1 5 INPUT EXIT • CALC 15 I% NPV • You should get NPV = 85,215.51

  28. NPV with the TI BAII Plus: • Select CF mode.

  29. NPV with the TI BAII Plus: • Select CF mode. • CFo=? -250,000 ENTER

  30. NPV with the TI BAII Plus: • Select CF mode. • CFo=? -250,000 ENTER • C01=? 100,000 ENTER

  31. NPV with the TI BAII Plus: • Select CF mode. • CFo=? -250,000 ENTER • C01=? 100,000 ENTER • F01= 1 5 ENTER

  32. NPV with the TI BAII Plus: • Select CF mode. • CFo=? -250,000 ENTER • C01=? 100,000 ENTER • F01= 1 5 ENTER • NPV I= 15 ENTER

  33. NPV with the TI BAII Plus: • Select CF mode. • CFo=? -250,000 ENTER • C01=? 100,000 ENTER • F01= 1 5 ENTER • NPV I= 15 ENTER CPT

  34. NPV with the TI BAII Plus: • Select CF mode. • CFo=? -250,000 ENTER • C01=? 100,000 ENTER • F01= 1 5 ENTER • NPV I= 15 ENTER CPT • You should get NPV = 85,215.51

  35. Profitability Index

  36. n t=1 S FCFt (1 + k) NPV = - IO t Profitability Index

  37. n t=1 S FCFt (1 + k) NPV = - IO t n t=1 S FCFt (1 + k) PI = IO t Profitability Index

  38. Profitability Index • Decision Rule: • If PI is greater than or equal to 1, accept. • If PI is less than 1, reject.

  39. PI with the HP10B: • -250,000 CFj • 100,000 CFj • 5 shift Nj • 15 I/YR • shift NPV • Add back IO: + 250,000 • Divide by IO: / 250,000 = • You should get PI = 1.34

  40. Internal Rate of Return (IRR) • IRR: the return on the firm’s invested capital. IRR is simply the rate of return that the firm earns on its capital budgeting projects.

  41. Internal Rate of Return (IRR)

  42. n t=1 S FCFt (1 + k) NPV = - IO t Internal Rate of Return (IRR)

  43. n t=1 S FCFt (1 + k) NPV = - IO t n t=1 FCFt (1 + IRR) S IRR: = IO t Internal Rate of Return (IRR)

  44. n t=1 FCFt (1 + IRR) S IRR: = IO t Internal Rate of Return (IRR) • IRR is the rate of return that makes thePV of the cash flowsequal to the initial outlay. • This looks very similar to our Yield to Maturity formula for bonds. In fact, YTM is the IRR of a bond.

  45. (250,000) 100,000 100,000 100,000 100,000 100,000 0 1 2 3 4 5 Calculating IRR • Looking again at our problem: • The IRR is the discount rate that makes the PV of the projected cash flows equal to the initial outlay.

  46. IRR with your Calculator • IRR is easy to find with your financial calculator. • Just enter the cash flows as you did with the NPV problem and solve for IRR. • You should get IRR = 28.65%!

  47. IRR • Decision Rule: • If IRR is greater than or equal to the required rate of return, accept. • If IRR is less than the required rate of return, reject.

  48. IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +) • Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

  49. (500) 200 100 (200) 400 300 0 1 2 3 4 5 • IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +) • Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +)

  50. (500) 200 100 (200) 400 300 0 1 2 3 4 5 • IRR is a good decision-making tool as long as cash flows are conventional. (- + + + + +) • Problem: If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. (- + + - + +) 1

More Related