Class Answers to Effort “Estimation”(Fall 2010) • 8 (two-week sprints) of 7 people - (personal exp.) • 1,174 person hours - (WBS and personal experience) • 48 person weeks - (assume the rest of the semester) • 8.74 pers-months - (COCOMO – 1.2KLOC) • 18.72 pers-months - (COCOMO – 5KLOC) • 127 pers-months - (COCOMO – 20KLOC) • No estimate number – just a schedule