1 / 19

CMSC Initiatives Update

CMSC Initiatives Update. WTBA & WisDOT Contractor Engineer Conference January 21, 2010. Evaluation of WisDOT’s Transparency Effort. Gary Whited Jera Jo Pashouwer Professor Awad Hanna. Overview. Background Pilot program goals and projects Project demographics

lena
Télécharger la présentation

CMSC Initiatives Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CMSC Initiatives Update WTBA & WisDOT Contractor Engineer Conference January 21, 2010

  2. Evaluation of WisDOT’s Transparency Effort Gary Whited Jera Jo Pashouwer Professor Awad Hanna

  3. Overview • Background • Pilot program goals and projects • Project demographics • Study methodology • Results so far

  4. Transparency Effort Goals • WisDOT managed construction projects and • Consultant managed projects are viewed as • being the same • Faster and more timely decision making • Consultant project managers have ready • access to the design consultant

  5. Pilot Project Selection • Multiple state and Local Program projects in • each Region • Mix of bridge and roadway projects • Mix of complex, large, medium and small • projects • Variety of contracting methods for retaining • design firm

  6. Project Demographics

  7. Project Demographics

  8. Project Demographics

  9. Project Demographics • Transparency design contracts range from 0.03 – 0.45% of construction contract award amount • Overall approximately 0.1% of construction contract award amount • About $124,000 total transparency design contract amount

  10. Goals for our Research Project • Determine the effectiveness and benefits experienced by the effort • Suggest improvements that could make the program better • Determine the most effective way to contract for the design involvement • Make recommendations regarding continued use

  11. Study Methodology

  12. Phone Interviews • Design Team • Contractors • Design Consultants • Consultant Project Leaders • WisDOT Project Managers

  13. Contractor Responses • Most were unaware their project was a pilot • Most did not submit RFI’s to the Project Leader • Almost all felt they received timely responses • and there were no project impacts • Most felt their project was straight forward • with few issues • Most felt the transparency effort had value • and should continue

  14. Design Consultant Responses • Most designers have used less than half of the Transparency contract cap • Most said they would handle the questions anyway • About half admit they were more motivated to answer quickly because of the contract • All surveyed believe the effort would prove beneficial for future projects

  15. Observations So Far • Transparency Effort seems to have been well received • Some criticism of how the design contract was implemented • Recommendations to follow further research

  16. Next Steps • Continue interviews • Compile and analyze data • Review similar techniques/trends used in industry • Summarize and make recommendations

  17. Questions?

More Related