Status Summary: NPP Ocean Color NOAA Unique Products Leads: K. Hughes (STAR) and A. Irving (OSPO)

Status Summary: NPP Ocean Color NOAA Unique Products Leads: K. Hughes (STAR) and A. Irving (OSPO). Kent H. Hughes August 22, 2011. PSDI Project: NPP Ocean Color NUPS. PSDI: Transition operational ocean color products, presently generated on Okeanos, from heritage platforms (MODIS) to NPP ,

lenora
Télécharger la présentation

Status Summary: NPP Ocean Color NOAA Unique Products Leads: K. Hughes (STAR) and A. Irving (OSPO)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Summary:NPP Ocean Color NOAA Unique ProductsLeads: K. Hughes (STAR) and A. Irving (OSPO) Kent H. Hughes August 22, 2011

  2. PSDI Project: NPP Ocean Color NUPS • PSDI: Transition operational ocean color products, presently generated on Okeanos, from heritage platforms (MODIS) to NPP, • ORS: Quality assessment of NPP generated ocean color NUPS, and • ORS: End user engagement and readiness for NPP sourced ocean color NUPS. August 22, 2011

  3. PSDI Project: NPP Ocean Color NUPS SOCD tasks: • Requirements (and user requests) analysis (Hughes). • Product generation (Keegstra). • Hardware / software readiness (Gu). • Quality assessment (Ramachandran). • Distribution (Vogel and Soracco). • Archive (TBD). • Risk assessment and mitigation (Kim) OSPO tasks: TBD August 22, 2011

  4. PSDI Project: NPP Ocean Color NUPS Schedule (key dates) and deliverablesin three phases: Development phase 1. Apr 2011 – Okeanos sizing. Ground Systems request by OSPO? Required by several product lines. 2. May 2011 – Project officially begins (Mod 7) 3. May 2011 – Hardware/software in place. Ready. 4. Aug 2011 – Requirements analysis begins. 5. Sep 2011 – Experiment distribution for evaluation via Tethys/STAR. Discussions beginning. 6. Oct 2011 – NPP launch. 7. Jan 2012 – - PDR scheduled (NESDIS milestone). - First data likely. - First products for evaluation: nLw, chl a (IDPS), NASA chl a (if s/w available), NOAA chl a (if s/w available), and HAB products. - Frontal and E. hux. as acceptable s/w becomes available. 8. Feb/Mar 2012 – First product quality assessment by CoastWatch. 9. Apr 2012 – User engagement and readiness (ocean color) meeting at NMM. 10. Summer 2012 – Okeanos equipment arrives. NPP OC NUP CDR. 11. Summer 2012 – Planned move from WWB to NCWCP. August 22, 2011

  5. PSDI Project: NPP Ocean Color NUPS Pre-operational phase: 1. Jul 2013 – Begin transition to Okeanos/PTS. 2. Sep 2013 – System Readiness Review (Okeanos) 3. Dec 2013 – Product quality review 4. Jan 2014 – User Readiness Review • Mar 2014 – - Okeanos ready for operations. -OCPOP/SPSRB briefed on operations readiness. Operational phase: 6. Mar 2014 – Begin ocean color operational production (Okeanos) using NPP data. August 22, 2011

  6. PSDI Project: NPP Ocean Color NUPS Backup Slides and Content Underdevelopment August 22, 2011

  7. PSDI Project: NPP Ocean Color NUPS Resource Utilization (under development) August 22, 2011

  8. NPP OC NUPS Risk Assessment Summary (under development) Requirements Assessment Hardware/Software Product Production (Exp) Product Production (Opns) MAY JUN JUL MAY JUN JUL MAY JUN JUL MAY JUN JUL G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST Y Y Y G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G G G G G G Y G Y R Y Y G G G Y Y G Y Y G G Y Y Y Y Y Y Y Y Y G G G G G G G G G Y Y Y G G G Quality Assessment Distribution Archive User Readiness MAY JUN JUL MAY JUN JUL MAY JUN JUL MAY JUN JUL G G G G G G G G G REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST REQUIREMENTS PROCUREMENT TECHNICAL SCHEDULE COST G G G G G G G G G G G Y Y Y Y R G G G Y Y Y Y R G G G Y Y Y Y Y Y G G G G G G G G G G G Y Y Overall OC NUP Readiness Assessment LEGEND NOV DEC JAN NOT STARTED G Y Y TECHNICAL SCHEDULE COST OVERALL GOOD SHAPE G Y Y Y MINOR PROBLEM Y G G G MAJOR PROBLEM R G Y Y