An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Washington’s Tolling ProgramLessons Learned from Project DelaysUJoint Legislative and Audit and Review CommitteeAugust 14, 2013David Dean, Deputy Director of Performance AuditSusan Hoffman, Principal Performance Auditor

  2. Tolling across the United States Washington is one of four states to adopt statewide all-electronic tolling

  3. Audit Question What lessons can be learned from WSDOT’s development and implementation of statewide all-electronic tolling?

  4. Complicating factors • WSDOT’s comprehensive accounting requirements were new to the tolling industry • Internal project stakeholders disagreed: • Purchasing a toll collection service • Developing an IT and accounting system to collect tolls • WSDOT feared losing federal grant funds if they did not meet deadlines

  5. What we found Fully assess and manage project risks Identified risks were not fully incorporated Proactively manage and monitor the work Ineffective project and vendor management • Hold the vendor accountable to the contract Delayed assessing damages

  6. 1 – Risks not fully integrated into planning WSDOT recognized some project risks but… • Consensus scoring diminished the advice of subject-area experts • Proposal scoring was not weighted to align with identified risks

  7. 1 – Identified risks were not fully integrated into planning High risk areas should be given added weight in scoring

  8. 1 – Identified risks were not fully integrated into planning High risk area received lowest score

  9. 2– Ineffective project management WSDOT developed a sound project management plan, but follow-through was ineffective • Project staff response to vendor problems: reduce reviews, take on some of the vendor’s work • Some WSDOT managers ignored the plan, dealing directly with the vendor • Changes to the project management structure created more confusion, for staff and vendor alike

  10. 3– Delayed assessing damages The project contract tied damages to major milestones • WSDOT feared applying damages could: • Risk losing federal funding • Lead vendor to withdraw • In 2011, WSDOT reduced vendor payments by $1.5 million • In June 2012, WSDOT and the vendor reached a financial settlement valued at up to $6.4 million

  11. Lessons learned: New division needed clarity, authority • The Toll Division lacked clear roles, responsibilities, and decision-making authority • The Toll Division lacked executive support in managing the vendor • The Toll Division lacked policies and procedures to guide the effective development and implementation of the project The Toll Division was created in 2009, responsible for development and operation of tolling systems

  12. Recommendations • The Secretary ensure roles, responsibilities, and decision-making authority are clear for projects managed by the Toll Division • The Assistant Secretary for Tolling establish policies and procedures to guide developing and implementing new tolling projects • The Department report on its progress as required in the 2013-2015 transportation budget

  13. Contacts • Susan Hoffman • Principal • (360) 725-9719 • Susan.Hoffman@sao.wa.gov Website:www.sao.wa.gov