An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Commercial Points for 93rd OCC meeting

  2. Change in Bank a/c • New Account for Deviation Settlement opened in Axis Bank • Name of the A/C : Power System Operation Corporation Ltd -SRPC Deviation Pool Fund Account. • Name of Bank : AXIS Bank • Name of Brach: Majestic Branch, Bangalore • Account Number: • IFSC code • RTGS code: All payments for Deviations from 17-02-14 to be paid to new a/c

  3. Tamil Nadu TN opened LC for Rs.8.49Cr only in lieu of Rs.32.84Cr LKPPL Rs.2.44 Lakhs Due to delay of wk40(31.12.12-06.01.13) UI payment OPENING OF LC DUE TO DELAYED UI PAYMENT Beneficiary a/c details to be changed in existing LC

  4. Number of Instances of delay in Weekly SEM data receipt at SRLDC during February 2014 In case not received in time, SRLDC will be constrained to approach higher Forum

  5. Time Drift Statement Not Received from the following stations during February 14

  6. Time Drift Statement Not Received from the following stations during February 14

  7. PoC Data for Q1 of 2014-15 (April 14-June14) • Validation Committee meeting scheduled on 07.03.2014. • DICs may participate from NLDC or SRLDC through Vedio Conferencing.

  8. PoC Data for Q1 of 2014-15 (April 14-June14) All the DICs has to furnish (1) the technical details of new transmission elements, generating units which are expected to commence commercial operation from April 14-June14 (2) Yearly Transmission charges (3) node wise MW/MVAR and (4) forecast generation and demand data Henceforth all DICs are requested furnish the full data required for computations at least by two quarters in advance without waiting for reminders from NLDC.

  9. Status of Data for Q1 2014-15

  10. Forecasting & Scheduling of Wind and Solar • As per CERC order dt 07-01-14 in Petition No. 356/SM/2013: • the commercial mechanism shall remain suspended till further orders. • the forecasting and scheduling of wind generation shall continue as per the provisions of the Grid Code and RRF procedure approved vide our order dated 9.7.2013 • All SLDCs are requested to comply.

  11. RRF Schedule data details • AP sent the RRF Schedule data for following periods : • 18-11-13 to 02-02-14 • 03-02-14 to 09-02-14 • 10-02-14 to 16-02-14 • 17-02-14 to 23-02-14