Weekly Status Update Data Conversion

Weekly Status Update Data Conversion. AP-MY Data conversion 9/23/2011. Agenda. Executive Summary Status Update Overview – AP-MY. Executive Summary. Overall Summary Previous Week Highlights Mapping and cleansing continued Next key activities Continue Data Cleansing

linh
Télécharger la présentation

Weekly Status Update Data Conversion

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Weekly Status UpdateData Conversion AP-MY Data conversion 9/23/2011

  2. Agenda • Executive Summary • Status Update Overview – AP-MY

  3. Executive Summary • Overall Summary • Previous Week Highlights • Mapping and cleansing continued • Next key activities • Continue Data Cleansing • Catch up on all late functional and technical mappings • Complete mapping activities due this week • Watch Points • Missing functional mapping prevents build and unit test completion. This will impact our Mock 1 start date • Missing configin DEV-600

  4. AP-MY Preparation PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete

  5. AP-MY Design / Fit Gap PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete

  6. AP-MYData Conversion FIT / GAP Dashboard • Functional Mapping Completed 52/82 = 63% Overdue 20/72 = 28% • Data Construct Completed 32/81 = 40% Overdue 33/63 = 52% • Technical Design Completed 36/79 = 46% Overdue 33/69 = 48% • Total Completed = 50%

  7. AP-MY Build PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete

  8. AP-MYData Conversion BUILD Dashboard • Missing functional mapping prevents build and unit test completion. This will impact our Mock 1 start date and is reflected in the overdue CranSoft upload and DC rules overdue.

  9. MY Deploy PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete

  10. AP-MY Data Conversion • Detailed Status Update Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete