LISD Board of Trustees. Status Report Presentation to the. by the. Facility Construction Department. March 27, 2002. Projects Under Construction (as of March 18, 2002). Campus Start Date Sta. Maria Elementary School Oct. 2001

lynette
Télécharger la présentation

LISD Board of Trustees

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LISD Board of Trustees Status Report Presentation to the by the Facility Construction Department March 27, 2002

  2. Projects Under Construction(as of March 18, 2002) Campus Start Date • Sta. Maria Elementary School Oct. 2001 • Farias Elementary School Oct. 2001 • Dovalina Elementary School Oct. 2001 • Sanchez/Ochoa Elem. School Oct. 2001 • J. W. Nixon High School Oct. 2001 • Milton Elementary School Jan. 2002

  3. Santa Maria Elementary School • Architect: Cavazos & Associates Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $4,862,700.00 • Construction Start: Oct. 31, 2001 • Start of School: Aug. 15, 2002 • Completion Date: Aug. 31, 2002 • Change Order(s): Addition of Single Sex Restrooms at PK & K.

  4. Financial Overview – Sta. MariaLeyendecker’s Contract

  5. Construction Time - Sta. MariaLeyendecker’s Contract

  6. Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. THIS IS A VIEW LOOKING NORTH FROM THE SOUTH WEST CORNER OF THE NEW CAMPUS

  7. Santa Maria Elementary School THIS IS A VIEW OF THE AIR CONDITIONING DUCT BEING ASSEMBLED FOR INSTALLATION

  8. Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. ZONE “A” AND “B”

  9. Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. KINDER AND FIRST GRADE

  10. Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. EAST SIDE ENTRANCE

  11. Farias Elementary School • Architect: Ashley Humphries, & Sanchez Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $4,926,997. • Construction Start: Oct. 31, 2001 • Days in Contract: 320 Calendar Days • Completion Date: Aug. 31, 2002 • Change Order(s): Addition of Single Sex Restrooms at PK & K.

  12. Financial Overview – FariasLeyendecker’s Contract

  13. Construction Time - FariasLeyendecker’s Contract

  14. Farias Elementary School FRONT VIEW OF BUILDING SECTION “E”

  15. Farias Elementary School FRONT VIEW OF BUILDING SECTION “F”

  16. Farias Elementary School INSIDE VIEW OF BUILDING SECTION “E”

  17. Farias Elementary School VIEW LOOKING SOUTH AT HE FRONTS OF SECTIONS “B” AND “C” FFROM THE FLOOR PLAN

  18. Farias Elementary School VIEW OF SECTION “A” LOOKING EAST FROM THE NORTH WEST CORNER OF THE SITE

  19. Farias Elementary School VIEW OF THE REAR AREA OF SECTION B

  20. Dovalina Elementary School • Architect: Design Group International, Inc. • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 2,801,900. • Construction Start: Oct. 31, 2001 • Number Contract Days: 304 • Completion Date: Aug. 31, 2002 • Change Order(s): None

  21. Financial Overview – DovalinaLeyendecker’s Contract

  22. Construction Time - DovalinaLeyendecker’s Contract

  23. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. THIS IS A VIEW LOOKING WEST AT THE HALF WALL THAT WILL DIVIDE THE GYMNASIUM AND THA CAFETERIA

  24. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. THIS IS A VIEW OF THE MASON’S FINISHING THE BLOCK WORK AROUND A STEEL COLUMN ON THE GYM SIDE WHERE THE FOLDING PARTITION WILL END

  25. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. THE A/C DUCT IS BEING PREPARED FOR INSTALLATION

  26. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. HALL NUMBER “7” LOOKING EAST

  27. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. ACCENTED CEILING INSIDE OF CLASSROOM #3, THE ART CLASSROOM

  28. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. ACCENTED CEILING INSIDE OF CLASSROOM #4, THE MUSIC AND FINE ARTS CLASSROOM

  29. Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. VIEW LOOKING WEST AT THE EAST WALL OF THE NEW GYMNASIUM

  30. Sanchez/Ochoa Elementary School • Architect: Sepulveda & Assoc. Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 5,132,719. • Construction Start: Oct. 31, 2001 • Number Contract Days: 320 • Completion Date: Sept. 16, 2002 • Change Order(s): None

  31. Financial Overview – Sanchez/OchoaLeyendecker’s Contract

  32. Construction Time – Sanchez/OchoaLeyendecker’s Contract

  33. Sanchez/Ochoa Elementary School FRONT VIEW OF SECTIONS “C” AND “D” FROM THE FLOOR PLAN

  34. Sanchez/Ochoa Elementary School VIEW LOOKING INTO SECTION “C” OF THE FLOOR PLAN

  35. Sanchez/Ochoa Elementary School VIEW LOOKING

  36. Sanchez/Ochoa Elementary School

  37. Sanchez/Ochoa Elementary School

  38. Sanchez/Ochoa Elementary School

  39. J. W. Nixon High School • Architect: Cavazos & Associates Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 9,298,985. • Construction Start: Jan. 30, 2002 • Number Contract Days: 551 • Completion Date: August. 15, 2003 • Change Order(s): None

  40. Financial Overview – Nixon HighLeyendecker’s Contract

  41. Construction Time – Nixon HighLeyendecker’s Contract

  42. J. W. Nixon High School

  43. J. W. Nixon High School

  44. J. W. Nixon High School

  45. J. W. Nixon High School

  46. PAD PREPARATION FOR NEW TWO STORY BUILDING

  47. FOUNDATION TRENCHING FOR TWO STORY BUILDING

  48. Milton Elementary School • Architect: Turner Hickey & Assoc. Arch. • General Contractor: To be determined • Asbestos/Demolition: M & M Contracting, Inc. • Contract amount: $ 183,978. • Construction Start: Jan. 27, 2002 • Number Contract Days: 47 Days • Completion Date: March 15, 2002 • Change Order(s): None