Beam Schedule Scenarios 2007. Overview. Scenario C1 – with Kottmann et al. Disadvantage: (i) Beam Line + BTS dismantled & re-built (ii) 3 3/4 Months Running Time Advantages:
E N D
Beam Schedule Scenarios 2007 MEG Review February 2007
Overview • Scenario C1 – with Kottmann et al. • Disadvantage: • (i) Beam Line + BTS dismantled & re-built • (ii) 33/4 Months Running Time • Advantages: • (i) Full testing C-W & beam Line with Calorimeter (early) • (ii) Allows more time for DCs • Scenario D1 – Maximized MEG Run • Disadvantages: • (i) Does not allow initial testing of C-W with Calorimeter • (ii) Kottmann et al. cannot be included until end-of-year (not possible) • Advantages: • (i) Allows 41/2 Months Running Time MEG Review February 2007
Scenario C1 Kottmann et al. • Shifting Kottmann et al. to a later date correspondingly shifts: • BTS • Beam Commissioning (if we don’t want to re-build beam line several times) • MEG Beam Run MEG Review February 2007
Scenario D1 Max. MEG Run MEG Review February 2007