ST. Patrick Church Construction Progress Update

This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentation In Slide Show, click on the right mouse button Select “Meeting Minder” Select the “Action Items” tab

major
Télécharger la présentation

ST. Patrick Church Construction Progress Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentation • In Slide Show, click on the right mouse button • Select “Meeting Minder” • Select the “Action Items” tab • Type in action items as they come up • Click OK to dismiss this box • This will automatically create an Action Item slide at the end of your presentation with your points entered. ST. Patrick ChurchConstruction Progress Update JMA Architecture, Inc. Construction Progress Update

  2. Previous Goals For This Review • Goals discussed at last meeting • Specific items that will be done by the members of the committee • Make a determination on the Add Alternates • Select Interior Finishes • Issues that will be resolved by JMA and Parrish • Cost of the DOT Entrance Construction Progress Update

  3. Status Summary • The project is still on schedule for delivery as expected, despite recent in-climate weather. Although some individual tasks are about two weeks behind schedule • The Scheduled Date for Delivery is February 25, 2005 • Original GMP Amount $1,762,000.00 Current GMP Amount $ 1, 776,640.00 • Entrance to site has begun Construction Progress Update

  4. Images of Work in Progress • Precast entrance was erected on the 18th of October • Masonry veneer started one week later. • There is some unresolved issue with the quality of the precast entrance. The contractor is proposing a credit. Construction Progress Update

  5. Images of Work in Progress • View of precast entry showing the detail of the bull nose and the reveals • View from behind the precast illustrating the steel supports for the precast. Construction Progress Update

  6. Images of Work in Progress • Steel erectors erected the cross on the morning of the 21st of October. • The Cross is some 18’-0” tall and close to 1000# in total weight. Construction Progress Update

  7. Images of Work in Progress • Welders are preparing to secure the cross to the structure Construction Progress Update

  8. Images of Work in Progress • Sun breaking through the morning fog Construction Progress Update

  9. Image of work in progress Construction Progress Update

  10. Images of Work in Progress • View from Parking lot looking at the North East Corner. EIFS and Block are completed. Window Installation is underway. • View of Front Entrance with Cross in background. Construction Progress Update

  11. Images of Work in Progress • View of Skylight and ceiling framing in Narthex Construction Progress Update

  12. Images of Work in Progress • View from Kitchen looking towards the entrance into the auditorium. • View from Narthex into the Auditorium looking at the altar Construction Progress Update

  13. Images of Work in Progress • View of entrance into the main office. • View of Narthex from the doors to the Auditorium. Construction Progress Update

  14. Images of Work in Progress • Drywall subcontractor installing drywall in the Auditorium. • View of the window from the cry-room to the Auditorium. Construction Progress Update

  15. Images of Work in Progress • View of the Chapel looking from the entrance to the altar. • View of the Precast base detail at the base of the pilaster. This is located in the narthex. Construction Progress Update

  16. Schedule • Upcoming Project Milestones: • Building will be completely dried in by the end of this week. • EIFS will be complete at the end of the week. • Exterior Paint starting tomorrow • Ceiling Grid Starting in 2 weeks. • Sidewalk is about to start. • Tile Scheduled for Delivery on November 15th • Carpet Scheduled for Delivery in December. Construction Progress Update

  17. Costs • Cost Savings since last meeting not yet reflected in total cost • $4,500 (AIB, Ceiling in restrooms, thru-wall flashing) • $2,480(Pending Credit for the Precast Entry) • Future Expenditures • Pending review. Interior Exterior/ Light Fixtures $1260 (over Budget) Construction Progress Update

  18. Cost Summary • Current and Projected Information • Original GMP Amount $1,762,000.00 • Revised Contract Amount $1,776,640.00 • Net Change to Project to Date $14,640.00 = 1.008% of Original GMP Construction Progress Update

  19. Resources • Summarize project resources • JMA Architecture Inc. • JIM Mehserle, Principal In charge • Andrew M. Butler, Project Manager • Mike Froehlich, Don Frew, Father Roland • Parrish Construction Group Inc. • Kenna Scragg, Principal In Charge • Travis Miller, Project Manager • Monthly meetings with the Owner, Architect, and Contractor Next scheduled meeting is December 1, 2004. Construction Progress Update