The Great Blackout. NOV 1, 2007. Booster MMPS Feed. Feed Down 0700-1900. Affects Booster MMPS only. LIPA to de-clutch motor drives to other switches during the work to minimize the possibility of unexpected outages. AGS: Feeder 911-17 outage: Nov 1, 0530-0830 hrs. Houses
E N D
The Great Blackout NOV 1, 2007
Booster MMPS Feed • Feed Down 0700-1900. • Affects Booster MMPS only. • LIPA to de-clutch motor drives to other switches during the work to minimize the possibility of unexpected outages.
AGS: Feeder 911-17 outage:Nov 1, 0530-0830 hrs • Houses • F10(water), H10(UPS, Water), E10, G-I ‘18’s. • AGS Ring Lights G-J. • Ring Crane. • HITL (I, II & III). • RF Lab 925. • 911 New Wing.
AGS II • Substation 1F 0900-1200 • “TRANSPARENT”.
MCR UPS • 2 Hours down 0830-1030hrs. • Affecting MCR and 911 B South Terminal Room - Timing, Video, Security etc.
NOV 1 Access • Booster 0700-1200. • AGS 1100-1300.
Scheduling Meeting • HERE (SNYDER) TOMORROW 1400hrs.
FYI • Test of RHIC fire Bells tonight 1645. • ACS Testing ongoing in the early morning and evenings. • EXPERIMENTAL ACCESS SHOULD NOT BE AFFECTED.