An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal

  2. US SRF Infrastructure Strength • Cavity Processing and Vertical Testing R&D Facility • Jlab (30 FY07, 40 FY08, 50 FY09) cycles/yr • ANL/FNAL ( 50 FY08, 60 FY09) cycles/yr • Cornell (12) cycles/yr • VTS @FNAL 70 cycles/yr (07) • Horizontal Test Stand • FNAL 24 cavities/yr • Cavity Dressing and Cryomodule Assembly • FNAL 12/yr (FY07) • Limited cavity fabrication capability in US industry

  3. US SRF Infrastructure Direction • Automated Cavity Tuning • 100+ Cavity/yr (FY09) • Processing and Vertical Testing (Pre-Production Next Generation Facility, with redundancy) • 100+ Cavity/yr (FY10) • Horizontal Test Stand • Additional 48 Test/yr (Maximum Capacity needed) • Cryomodule and RF Unit Assembly and Test without and with beam • Increased cavity fabrication capability in US industry • Electron Beam Welder (FY09)

  4. Target 2 ~ 50 M$ for 08, 09

  5. Cavity/CM schedule, Tgt 2

  6. Target 2: Summary of FY08-09

  7. MSU Work Package • Recommended Program • Cavity Autopsy • Single Cell Cavity (R&D) • Advanced Cavity and Material Science studies (R&D) • SRF Infrastructure • Upgrade ultra-pure water and high pressure rinse • Nine-cell structure vertical test dewar • Budget • UPW and HPR: $80k (08), $60k (09) • Vertical dewar: $150k (08), $60k (09) • Cavity Autopsy: $250k/year • Test single-cell cavities: $50k/year • Advanced Cavity and Material Science studies: $135k/year FY08: $635k and FY09: $555k

  8. LANL Work Package • Recommended R&D Program • Cavity Autopsy • SRF Infrastructure (Partly Funded in FY07) • Re establish cavity testing at LANL • 1.3 GHz Power Amplifier • Thermometry provided by Fermilab • Budget • 2.5 FTE FY08,09 : $208k and $214k • M&S FY08,09: $495k and $689k • Indirect Cost FY08,09: $288k and $297k FY08: $991k and FY09: $1,200k

  9. Cornell Work Package • Goal : S0.2 Contributions, Determine if a new cavity is qualified to reach high gradients • Plan: Vertical EP, HPR, test new 9-cell cavities • Background • Proven successful for single cells • EP under development for 9-cells • Scope of Work : Process and test one cavity per month: (Production cavity activities) • Heat treatment and tuning to be carried out elsewhere (need to include cost of those treatments and shipping in overall budget). • Budget: • 2 FTE + 100 K (liquid helium, acids…) • RF power source 300 – 400 Watt (60 K$) (if not funded in 07) • Smaller diameter vertical test dewar (60 K$) (if not funded in 07) • Present dewar was used for very large 200MHz cavities • Reduce liquid helium usage per test • M&S cost = 220 K each in 08, 09

  10. Cornell Work Package (R&D) • Explore basic parameters for HPP with 9-cell ILC Cavity • Qe, Pulse Length, Power Level • Complete vertical test stand insert for HPP of 9-cell cavities (0.5 FTE) • Test stand design started in 06, continue in 07 • Available • About 2 MW, 1.3 GHz source, 250 us pulse length • Waveguide to coax switch and waveguide run to test pit • Input coupler/cold window • Scope: EP, HPR and Vertical tests 9-cell cavities with HPP including vacuum accidents and recovery. 6 tests per year (1 FTE + 50 K M&S)

  11. Cornell Work Package (ACD) • Design 9-cell cavity with HOM couplers to achieve adequate damping (0.5 FTE) • Chose best aperture 60 – 70 mm • Order two 9-cell re-entrant cavities with HOM couplers (250 K) • One with fine-grain, one with large-grain Nb? • Process and test two 9-cell re-entrant cavities (0.5 FTE) • Fine grain with EP, large-grain with BCP • 6 tests per year

  12. Jlab Work Package • Processing and Vertical Testing of 9 Cell Cavity • 30 cy/yr in FY07 (Estimate Based on Previous Slides, additional M&S resources may be needed in 08 and 09) • Process 40 cy/yr in FY08, 32 k per (1.23 M) • 50 cy/yr in FY09 (1.6 M) • $200k per year as an estimate for additional resources contingency • $365k per year Cryogenic cost • Single Cell R&D to improve the Processing (0.25M each year) • Field Emission studies for tracking the contamination (0.1M each year) • ACD: LL Shape Cavities, Large Grain and Single Crystal (0.5 each year) FY08: $2.65M and FY09: $2.62M

  13. ANL Work Package 08 • Electropolish S0.2 ILC cavities- 1.5 FTE, $225 K M&S for full-time operation and throughput of 1 procedure/week • Install new HPR system, $200k • High-pressure rinse S0.2 ILC cavities –1.0 FTE, $60K M&S • Installation of a PLC-based control system for EP - 0.5 FTE, $75 K • Optimize existing EP hardware/Interface with U.S. EP vendors/develop and optimize hardware suitable for large-scale EP (1 FTE)

  14. ANL Work Package 09 • Electropolish S0.2 ILC cavities– 2.0 FTE, $337 K M&S for full-time operation and throughput of 1.5 procedures/week • High-pressure rinse S0.2 ILC cavities – 1.0 FTE, $60 K M&S • Optimize existing EP hardware/Interface with U.S. EP vendors/develop and optimize hardware suitable for large-scale EP (1 FTE) FY08: $1.4M and FY09: $1.5M

  15. Target 2: Fermilab Work Package 08 • Order 60 cavities • Heat treat, tune, HPR and Vertical test: 50 cycles/ EP at Argonne • Horizontal test 16 “good” cavities • Work with LANL and MSU to supply thermometry diagnostics for failed cavities • Single cell R&D • Materials R&D collaboration • Continue Testing First cryomodule (type III) assembled in 07 from DESY supplied cavities • Assemble cryomodule #2 (Type III) • Test cryomodule #2

  16. Target 2: Fermilab Work Package 08 • Assemble cryomodule #3 (Type IV) • Order parts for 4 Cryomodule Gen IV – For S2 RF units, & industrialization start • Continue Next Generation CM design, manufacturability, transportability, cost reduction • Involve industry in activities • Test and treatment facility operations • Refrigeration (and misc) for Operation, S0, S1 • Install one additional HTS (48 tests/yr) • Begin to develop a new CM test stand (RF is in X.8) • RF unit infrastructure (NML)

  17. Target 2: Fermilab Work Package 09 • Order 60 cavities • Heat treat, tune, HPR and Vertical test 90 - 100 cycles/ EP at Argonne & FNAL • Horizontal test 24 “good” cavities • Assemble 4 cryomodules (Type IV) • Test 4 CM • Order parts for 4 CM (Type IV) – CM industrialization • Continue Next Generation CM design, manufacturability, transportability, cost reduction • Test facility operations • Involve industry in activities • Single cell R&D • Materials R&D collaboration

  18. Target 2: Fermilab Work Package 09 • Install Next Generation and Pre-Production cavity processing (scanning, EP, BCP, tuning, heating) and preparation (HPR, clean room, baking) infrastructure to handle 100 cycles per year • Install one beam welder for cavity industry, increase number of cavity vendors • Finish installation of cryomodule test stand • Operate RF unit infrastructure with 1 RF unit

  19. Target 1 ~ 25 M$ for 08, 09 • Strategy: • Reduce cavities and CM from Regional Interest, maintain S0/S1 support • Some infrastructure buildup in 08, other deferred to 09

  20. Cavity/CM schedule, Tgt 1

  21. Target 1: Summary of FY08-09

  22. Target 1: Fermilab Work Package 08 • Order 30 cavities • Heat treat, tune, HPR and Vertical test: 50 cycles/ EP at Argonne • Horizontal test 8 “good” cavities • Work with LANL and MSU to supply thermometry diagnostics for failed cavities • Single cell R&D • Materials R&D collaboration • Continue Testing First cryomodule (type III) assembled in 07 from DESY supplied cavities • Assemble cryomodule #2 (Type III)

  23. Target 1: Fermilab Work Package 08 • Order parts for 1 Cryomodule Gen IV – For S2 RF unit • Continue Next Generation CM design, manufacturability, transportability, cost reduction • Involve industry in activities • Test and treatment facility operations • Refrigeration (and misc) for Operation, S0, S1 • Complete RF unit test infrastructure at NML (without beam)

  24. Target 1: Fermilab Work Package 09 • Order 30 cavities • Heat treat, tune, HPR and Vertical test 50 cycles/ EP at Argonne & FNAL • Horizontal test 16 “good” cavities • Assemble 2 cryomodules (Type IV) • Complete RF unit infrastructure at NML (add beam capability) • Order parts for 2 CM (Type IV) • Continue Next Generation CM design, manufacturability, transportability, cost reduction • Test facility operations • Involve industry in activities • Single cell R&D • Materials R&D collaboration • Start construction of new cryomodule test facility