1 / 11

Interleaved HW and Beam Commissioning? G. Arduini, M. Pojer, R. Schmidt

Interleaved HW and Beam Commissioning? G. Arduini, M. Pojer, R. Schmidt Discussions with: L. Bottura, M. Giovannozzi, M. Lamont Your feedback is welcome!!. Aim. Delays in the availability of the Sectors (schedule already obsolete...) Determine the minimum conditions required for:

Télécharger la présentation

Interleaved HW and Beam Commissioning? G. Arduini, M. Pojer, R. Schmidt

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Interleaved HW and Beam Commissioning? G. Arduini, M. Pojer, R. Schmidt Discussions with: L. Bottura, M. Giovannozzi, M. Lamont Your feedback is welcome!!

  2. Aim • Delays in the availability of the Sectors (schedule already obsolete...) • Determine the minimum conditions required for: • Sector tests (in particular for Beam 2) • 10/9 type of event: i.e. Injection, circulating beam and RF capture • After this phase? K. Foraz – LMC 3/6/2009 Beam Commissioning Meeting - GA

  3. Day 2 Circuits & 60-120 A • Circuits not required for early commissioning (M. Giovannozzi): • RTQX1 • RCO • RO • RQSX • Circuits not required for Early physics (e.g. no crossing angle and b* >1 m) • RSS • Non linear triplet corrector spool pieces (RCSX, RCSSX, RCOX, RCOSX, RCTX) • 60 – 120 A orbit correctors to be fully commissioned before beam injection to identify polarity errors as soon as possible with beam. • Gain to be expected by fractionated commissioning of these circuits is limited (can be powered in large number in parallel during Phase 1) Beam Commissioning Meeting - GA

  4. 600 A • Minimum commissioning for 600 A might be an option in particular for Sector 34: • not fully tested in 2008 due to DSLC problem • Could be interesting if tuning of the QPS proves to be long (inductance tables, etc) • Otherwise limited gain for other sectors (several 600 A circuits can be powered in parallel during Phase 1, furthermore reduced test programme for UNAFFECTED circuits) • Limit to 200 A (PCS to identify possible weak circuits ASAP) 4h/circuit 3 h/circuit

  5. IPQs • Minimum commissioning for IPQs (Q4 to Q10): • Up to PLI_2 currents (300 to 900 A) > I_injection • Possible in phase 1 but limited to 1 circuit/cryostat 2 shifts/circuit 1 shift/circuit

  6. IPDs • Minimum commissioning for IPD: • Up to PLI_2 currents (~1kA) > I_injection (heaters induced quench) • Can be done during Phase 1 (1 circuit/cryostat) 1 shift/circuit 3 h/circuit

  7. Main Bends and Main Quads • Minimum commissioning for MBs/MQs: • Up to 2 kA (PLI_2) allowing nQPS system check, as well as energy extraction (new time constants!) • Only possible during Phase 2 powering • Sufficient for injection tests and circulating beam and likely for studying the start of the ramp (pre-cycle to 2 kA should be sufficient for getting reproducible injection settings similar to those obtained for ramps to larger energy) • Once this is done, make splice measurement (QPS and calorimetry) up to nominal current so to characterize splices and to complete commissioning calorimetry calorimetry 2 days/circuit 2 days/circuit 3 days/circuit 3 days/circuit

  8. Inner Triplets • Minimum commissioning for ITs: • Up PLI_3 allowing to verify behaviour of the 2 main circuits (RQX and RTQX2) in case of PC failure, slow power abort and quench and to commission the IT circuits above injection levels • Only possible during Phase 2 powering • Once this is done, make splice measurement (calorimetry) up to nominal current so to characterize splices and to complete commissioning • RTQX1 can be postponed calorimetry 1 day/IT 2 days/IT

  9. Pros & Cons of interleaved HWC • Cons: • Delay in the complete commissioning of machine protection elements like the beam dump (tracking require availability of the Sectors 45-56-67-78 which are coming late) • Risks related to the cohabitation of overlapping activities during high power tests: • E.g. need to implement tools preventing powering at high current if vacuum valves opened • Delay in getting a snapshot of the SC splices in the machine. • Risk to lose focus and concentration in the HW commissioning in particular in Phase 2 (high power!) • Remanent radioactivity during interventions required for HWC • Pros: • Early verification of the status of the machine (aperture, polarities, optics, etc.) with possibility of intervention in the shadow of the remaining HWC activities • Possibility of profiting of other sources of downtime in other parts of the machine to complete the HWC commissioning

  10. Proposal • Minimum commissioning scenario can be envisaged for Injection tests and for machine check with beam at 450 GeV/c (circulating beam and RF capture for both beams) and possibly a mini-ramp to ~1 TeV (?): • Only essential circuits • 600 A commissioning limited to PCS for Sector 34 if difficulty in reaching performance • IPQs commissioning limited to PLI_2 (300-900 A  Phase 1, constraint on parallelism) • IPDs commissioning limited to PLI_2 (1 kA  Phase 1, constraint on parallelism) could be interesting if difficulties in reaching 5 TeV settings (e.g. D3/D4 in LSS4) • Main bends and main quads commissioning to 2 kA allowing verification of the nQPS • Provided few sectors (2 or 3, including high luminosity IPs are fully commissioned to exercise a full-scale powering of a sector through the whole phases of the cycle (pre-cycle, injection, ramp, squeeze, ramp-down)

  11. Proposal • This can allow anticipating injection tests and circulating beam by 1-2 weeks likely (exact extent difficult to estimate now, depending on sector availability and maximum achievable parallelism) • Beam commissioning for a predefined time (2 weeks?) • After that: • Commission the machine to nominal and get precise picture of the splices • Final Machine Check-Out • Possibility of leaving behind (for possible unscheduled stops) circuits requiring training (if any) and low priority circuits.

More Related