The SiPM status on R&D in Munich. Nepomuk Otte MPI für Physik München. outline. working principle status in Munich measurement results single photon resolution gain time resolution recovery time crosstalk summary. SiPM – the working principle.

medea
Télécharger la présentation

The SiPM status on R&D in Munich

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The SiPMstatus on R&D in Munich Nepomuk Otte MPI für Physik München

  2. outline • working principle • status in Munich • measurement results • single photon resolution • gain • time resolution • recovery time • crosstalk • summary Max-Planck-Institute for physics Munich

  3. SiPM – the working principle APD in geiger mode is a single photon counting device combine many small pixels into a matrix and connect them in parallel gain dynamic range in addition to single photon resolution Max-Planck-Institute for physics Munich

  4. SiPM status in Munich • SiPM from MEPhI • 1mm2 with 576 pixels are in Munich and are being studied (see results on the following slides) • 9mm2 already in Munich • test station is being setup (cooling needed) • development at HLL • IDEA: use fully depleted Si with backside irradiation (no dead space) • simulations are in progress • APD in geiger mode • APD in proportional mode • test structures at the end of this year • first prototypes at the end of next year Max-Planck-Institute for physics Munich

  5. picture a capacity is discharged by a certain amount of charge slope gives pixel capacity (C = 41fF) gain comparable to PMT‘s gain Max-Planck-Institute for physics Munich

  6. timeresolution imroves with number of fired pixels time resolution J. Barral Max-Planck-Institute for physics Munich

  7. recovery time no well defined deadtime better: “recovery time” pixel is not dead while it is recharging to bias voltage J. Barral with a dark count rate of 106 counts/s at room temperature 1‰ of all pixels will always be “dead” Max-Planck-Institute for physics Munich

  8. single photon resolution very low excess noise factor leads to multiple photon resolution Max-Planck-Institute for physics Munich

  9. crosstalk Hot-Carrier Luminescence 105 avalanche carriers 3 emitted photons A. Lacaita et al, IEEE TED (1993) photons generated in the avalanche travel into a neighbouring cell and initiate another geiger brakedown ways to reduce crosstalk: reduce gain and/or absorb photons between pixels Max-Planck-Institute for physics Munich

  10. quantum efficieny determined by • intrinsic QE of Si • detection efficiency (depending on overvoltage) • active area (≈25%) P. Buzhan et al. NIM A 504 (2003) 48-52 Max-Planck-Institute for physics Munich

  11. summary and outlook • we are developing SiPMs in two different ways: • in collaboration with MEPhI and Pulsar (B. Dolgoshein et al.) • with the semiconductor laboratory attached to MPI (WHI) and MPE • SiPM is a promising replacement candidate for conventional photomultipliers • high gain (106) • QESiPM≈QEPMT; expect boost by the application of microlenses • multiple photoelectron resolution up to ≈ 60 photo electrons • mechanical robust • possibility of mass production  reduction in costs • insensitiv to magnetic fields • low power consumption <40µW per 1 mm2 • dark count rate • crosstalk • R&D goals: increase SiPM size from 1 mm up to (3-5)mm increase in QE up to 70% Max-Planck-Institute for physics Munich

  12. crosstalk at a gain of 5105 Max-Planck-Institute for physics Munich

  13. Dark noise 22°C • noise sources • thermal generation • tunneling • cooling needed to satisfy EUSO requirements • count rate drops below 10kHz when operated at -50°C and gain >106 Max-Planck-Institute for physics Munich

  14. Principle of operation • photon is absorbed in the depleted semiconductor • photo electron drifts into high field region and initiates an avalanche breakdown • passive quenching by resistor • deadtime ≈10-7 s given by the time constant to recharge the pixel‘s capacity P. Buzhan et al. http://www.slac-stanford.edu/pubs/icfa/fall01.html Max-Planck-Institute for physics Munich

  15. Photon detector requirements for EUSO • overall photon detection efficiency > 50% (only about thousand photons per event) • sensitive range 330 nm to 400 nm (fluorescence light of N2molecules) • single photon counting with time resolution <10 ns (to avoid photon pileup) • dynamic range 100 phe/mm2 (to detect the Cherenkov flash) • dark noise < 106counts/s/mm2 (so light of night sky is limiting) • active detector area 4mm x 4mmwith as small as possible dead area (given by the resolution of the EUSO optics) Max-Planck-Institute for physics Munich