DRIE equipment purchase Final steps

DRIE equipment purchase Final steps. Mikko Kataja, Ville Liimatainen, Mohammadrez Soleymaniha , Sasha Hoshian. Timeline for DRIE equipment purchase. Ground work. Specifications. Call for tenders. Review offers. Write contract. Receive the device. Everyday use. 1-2 weeks. 2-3 months.

Télécharger la présentation

DRIE equipment purchase Final steps

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DRIE equipmentpurchaseFinalsteps Mikko Kataja, Ville Liimatainen, MohammadrezSoleymaniha, Sasha Hoshian

  2. Timeline for DRIE equipment purchase • Ground work • Specifications • Call for tenders • Review offers • Write contract • Receive the device • Everyday use • 1-2 weeks • 2-3 months • 6-8 weeks • 1 week • 1 weeks • 3 months or more • Years 2013

  3. Key people in the finalsteps • Person in charge of the purchase (PiC) • couldbehead of dept, orone of the professors • Main users • PhDstudentsorPostdocresearchers • Micronovadirector and secretary • Veli-Matti Airaksinen • Head of department

  4. Evaluation of the offers • Evaluation criteria has been decided before the call for tenders • Decision has to be made according to the published criteria or the rejected suppliers can (and probably will) file a complaint • Price is most likely the most important criterion as long as the technical requirements are met • If no supplier is able to meet the requirements, we can contact the suppliers directly to make a direct purchase. • Evaluation of the offers should bedoneby the person(s) in charge and approved by legal department.

  5. Contract • Contact the Head of Procurement at Aalto Finance services (Antti Laakso) • Should already have been in contact during the tendering • Ask for a contract draft for the DRIE purchase • Contact the lawyer at respective school (e.g. Anna Huuskonen for ELEC) • Will check the contract for any legal issues • Contact the person who is authorized to sign the contract • If the contract is the result of a tendering process, the Dean can sign (e.g. Tuija Pulkkinen for ELEC) • If it’s a direct purchase, the Dean can still sign, but further approvals by the President of Aalto University (Tuula Teeri) and the Chief Financial Officer (Marianna Bom) are needed • Contact the company representative for their signature

  6. Receiving the machine Delivery • Where the machine should be delivered? • Micronova building in Aalto preferably at the installation site • Who is in charge from Aalto side to sign the delivery factor? • Secretaryof Micronova or head of the department Sami Franssila Installation • Installation should be done by engineers from the companybut before that the site should be prepared • Piping and gasingsystem ( Micronovaengineerswillberesponsible) • Cleaningup the location • Exhaust • Electrical connections (Veli-Matti orMicronovastaffwillcontact an electrician) • Who should be present at the installation date? • Director, Aalto Nanofab, Veli-Matti Airaksinen • Head of department, Sami Franssila • Main users of the machine (PhDstudentsor engineers from Aalto)

  7. Acceptance tests • Safety • Leaktest(Company engineers, Micronovastaff) • Technical requirements • Etch rate • Aspectratio • Testsamplesareneeded to verify (fabricatedby the main usersthatarealsotrained to use the machine) • For both etch rate and aspect ratio a TEM can be used. • The PiCfindssomeonewhocan prepare the samples and do the TEM measurements. • Calibration • Otherequipment • Pumps, coolingsystem, software • Willbetestedduringtestsamplefabrication

  8. Everydayuse • Instructions and safety signs • Identify right places to put warning banners and instructions location: main user • Who is responsible for making instruction(English, Finnish): main user • Training of new users • New users: Master degree students or Micronova’s staff • Should be performed by Main users( PhD students) • Upkeep • Everyuserhas to cleanupaftertheiruse • Cleaning, changing gas and waste: To be performed by main users • Main users check the equipment according to the manufacturers specifications • Additional maintenance by the manufacturer (PiC) • Booking and logging systems • Booking: LIMS • Micronova staff will add new equipment to LIMS, main users will take care of adding new users • Logging: PESO • Troubleshooting • First step: Main users • Second step: company troubleshooting service( e.g. remote troubleshooting)