Maryland at Edgerton Channelization. Maryland Avenue – Ramsey County Roadway ADT 20,000 plus Maryland/Edgerton Intersection in top 10 Citywide for Crashes 5 year period ending 12-31-14 134 Crashes - # 7 on City Crash mapping database. Maryland at Edgerton Channelization.

Télécharger la présentation

Maryland at Edgerton Channelization

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maryland at Edgerton Channelization • Maryland Avenue – Ramsey County Roadway • ADT 20,000 plus • Maryland/Edgerton Intersection in top 10 Citywide for Crashes • 5 year period ending 12-31-14 • 134 Crashes - # 7 on City Crash mapping database

  2. Maryland at Edgerton Channelization • Acquire ROW and widen street to south to allow for construction of left turn lane, new traffic signal, etc • Reduce Crashes and Improve Operations • Similar to other safety projects • White Bear @ Maryland, Minnehaha • Maryland @ Prosperity, Rice, Arkwright (2013) Payne (2014)

  3. Maryland at Edgerton Channelization • Ramsey County – Applied for Federal Safety Funds • Public Works requesting total of $750,000 in 2017-2018 for City Share • 50/50 cost split City/County for ROW Acquisition • City Share of Construction Cost • Widening and ROW Acquisition between Edgerton and Payne completed • County plans to proceed with Construction in 2018 or 2019.

  4. Maryland at Edgerton Channelization • Maryland/White Bear Crash History Project Constructed 2007

  5. Phalen Boulevard @ Mississippi Street Traffic Signal • I-35E Cayuga Project to be completed in late 2015 or 2016 • New Interchange at Cayuga • Section of Phalen Blvd/Pennsylvania Reconstructed

  6. Phalen Boulevard @ Mississippi Street Traffic Signal

  7. Phalen Boulevard @ Mississippi Street Traffic Signal • HealthPartners Neuroscience Building and Parking Ramp Proposed • Initial Build Out • 128,000 SF Building • 680 Parking Spaces • Future Build Out • 192,000 SF Building • 960 Parking Spaces

  8. Phalen Boulevard @ Mississippi Street Traffic Signal

  9. Phalen Boulevard @ Mississippi Street Traffic Signal • Phalen Blvd – Projected ADT 14,400 • Mississippi – Projected ADT 7,600 • Construct Traffic Signal in 2017 • HealthPartners to Contribute $150,000 • Requesting $125,000 of MSA Funds to Fund City Share

  10. Phalen Boulevard @ Olive Street Traffic Signal • Same Background Information as signal at Mississippi Street • Phalen Blvd – Projected ADT 14,400 • Olive – Projected ADT 3,000 • Construct Traffic Signal in 2016 • HealthPartners to Contribute $150,000 • Requesting $125,000 of MSA Funds to Fund City Share

  11. Safe Route to Schools Plan Development • Requesting $100,000 of CIB Funds in 2016 and $100,000 2017 • Plan to pursue additional planning funding from other sources • Create/Update Safe Route to School Plans • St. Paul Public Schools • Private Schools • Charter Schools

  12. Safe Route to Schools Plan Development

  13. Safe Route to Schools Plan Development

  14. Safe Route to Schools Plan Development • In past City/School District had robust Safe Routes to School Program • Over time, we have fallen behind due to many changes in schools and Public Works staff reductions • Missing Opportunity for State, Federal and other Funding for Infrastructure Improvements

  15. Safe Route to Schools Plan Development • Requesting $100,000 of CIB Funds in 2016 and $100,000 2017 • Once Plan for Individual schools are established, could then apply for State, Federal and other Funding Sources • Incorporate Infrastructure Improvements in City/County/MnDOT Projects

  16. Safe Route to Schools Plan Development • Ties into City 8-80 Vitality Program • Crossing Improvements benefit entire community • Evolve into Citywide Map • Associated Education Enforcement Efforts benefit Pedestrians and Bicyclists • High School use of Met Transit Buses

  17. Safe Route to Schools Plan Development

  18. Safe Route to Schools Plan Development • Met with School District and they are supportive • Letters of Support • Transit for Livable Communities • Bicycle Alliance of Minnesota • Joan Pasiuk • St. Paul Smart Trips