Provo Parking Lot Design

Provo Parking Lot Design. Clifton Hargus , Rachel Bytheway , Derek Noyes. Outline. Background Project Goals Research Drainage Requirements Designs Final Recommendation Cost Analysis. Background. Pavement Severely Failing Not Enough Parking Insufficient Drainage. Goals.

milton
Télécharger la présentation

Provo Parking Lot Design

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Provo Parking Lot Design Clifton Hargus, Rachel Bytheway, Derek Noyes

  2. Outline • Background • Project Goals • Research • Drainage Requirements • Designs • Final Recommendation • Cost Analysis

  3. Background • Pavement Severely Failing • Not Enough Parking • Insufficient Drainage

  4. Goals • The parking lot needs to be designed with better drainage. • Parking spaces need to be arranged to obtain the maximum number possible. • Multiple construction phases should be considered.

  5. Research • Survey of Site • Coring of Asphalt • Inspection of Current Drainage • Drainage Calculations

  6. Drainage Requirements

  7. Curb and Gutter • Provides Excellent Drainage • Protects Landscaping from Automobiles • Aesthetically Pleasing • Significant Earthwork Required to Reverse Existing Slope • Double Amount of Piping • Difficult for Multiple Phases

  8. Curb and Gutter Costs

  9. Channel Drain • Continuous Grate for Quick Drainage • Resistant to Clogs

  10. Channel Drain Costs

  11. Box Drain

  12. Box Drain • Provides Adequate Drainage • Works with Existing Slope • Minimal Construction Impact • Provides No Protection for Landscaping • No Curb and Gutter • Requires some Maintenance

  13. Box Drain Costs

  14. Box Drain System Final Recommendation • Significantly Less Expensive • Provides Adequate Drainage • Minimal Construction Impact • Allows for Construction Phasing

  15. Final Cost Analysis

  16. Parking Space Optimization • 8.5’X18’ Parking Stalls • 56 Spaces Needed • Excavation of 400 Sq. ft. • 57 Spaces Provided

  17. Construction Phases • North or South Side Completed First • Catch Basin and Manhole Tie-in Completed During First Phase • Remainder to be Completed as Funds Allow • Each Subsequent Phase to Tie into Previous Work

  18. Questions ?