Procurement Equipment under CRS

WELCOME. Procurement Equipment under CRS. 16 th July 2018. Important Points to start Procurement Process. Preparation of Procurement Plan by PI (Offline/ not in PMS) Identify the requirement/specification of the equipment Cost estimate and indicative timelines

mkrystal
Télécharger la présentation

Procurement Equipment under CRS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WELCOME Procurement Equipment under CRS 16th July 2018

  2. Important Points to start Procurement Process • Preparation of Procurement Plan by PI (Offline/ not in PMS) • Identify the requirement/specification of the equipment • Cost estimate and indicative timelines • Selection of the appropriate procurement method • Approval of Procurement Plan from respective Institute Head • Approval by SPIU (Offline/ not in PMS) • Formation/ constitution of Purchase Committee • The committee should consists of the following members : • (a) Head of the institute • (b) TEQIP Coordinator • (c) Procurement coordinator • (d) Co- Principal Investigator (PI) • (e) Principal Investigator (PI)

  3. Procurement Mehods Transparency, Competitive, Justifiable • Methods Applicable : (As per the limit on funding on procurement) • National Shopping • Direct Contracting • Government e-Market (GEM)

  4. National Shopping (NS) - STEPS Identify

  5. Important Points - National Shopping (NS) • Requests should be addressed to more than three firms so as to ensure at least three quotations are received at the time of opening • Request for quotation shall be written and sent by letter, email etc. (with proof of receipt and record keeping) • Advertisement/RFQ should be uploaded in website and may be given in the Newspapers • Minimum of 14 days should be given for quotation submission from the date of issue of request. • The request shall include the complete requirement like Specification/description, quantity of the goods as well as the required delivery time and place for the goods or services, including any installation requirements as appropriate

  6. National Shopping (NS) • Quotation should be submitted in sealed envelope (No email submission) • Validity of quotation should not be less than 15 days. • Institute may impose Liquidated Damage clause • No bid security/EMD • Institute may take Performance Security • Prices must be in Indian rupees • Quotation should be compared (including taxes and all) and evaluated to the final destination.. • Issue of PO (before validity period) to the lowest responsive offer • Award decision and its rationale should be documented and kept for future reviews. • GEM items are permissible and states rules shall be applicable, if any.

  7. Direct Contracting Identify

  8. Direct Contracting • Equipment & LRs, specifically certified as proprietary or where there is sole manufacturer of the item and not obtainable from any other source. • Standardization of equipment or spare parts to be compatible with existing equipment may justify additional purchases from the original supplier • Extension of existing contracts for goods awarded with the prescribed procedures, justifiable on economic grounds • Justification is to be provided for opting Single source • Supplier’s/Manufacturer Proprietary Certificate • Ensure reasonableness of price by seeking additional information like comparison of prices with other similar transactions.

  9. GEM GUIDELINES • Government e-Market place (GEM) in lieu of shopping • Use of GeM is allowed up to US$ 30,000 in catalog mode. • Borrowers will record their assessment on reasonableness of price. • Respective state thresholds values shall be applicable in case GEM.

  10. Procurement Assessment & Monitoring Procurement of each equipment shall be recorded in separate file and shall contain: • Procurement Plan approved by approving authority with the minutes recorded. • The package/ equipment procured should be from the approved procurement plan. • Invitation letter/Tender document, as the case may be (refer format available on website). • Proof of time allowed for submission of bids/ quotation (Minimum 2-4 weeks as the case may be) • The advertisement/ Call for quotation/ Website proof etc. indicating efforts for maximum participation of vendor. • Minutes of pre-bid meeting (if any) with proof for presence of bidders. • Minutes of opening of quotations meeting of Institute Purchase Committee and all relevant documents NATIONAL PROJECT IMPLEMENTATION UNIT (NPIU)

  11. Checklist for verification of Procurement Items • Minutes of bid/ quotation evaluation reports should be signed by Purchase Committee as defined in presentation. • The minutes of meeting and other communications in case of extension in validity of quotations/bids, supply and delivery etc. • PO/ Contract. awarded should be available and PO/ Contract need to have timelines for payments • Separate Stock Registrar Centrally & equipment shown transferred to respective laboratory with the equipment shown in the stock register of laboratory also. • Bank guarantee in case of advance payment • The bills with installation/ commissioning/ testing/ training/ demonstration certified by respective committee as per T&C in PO/ Contract agreement and liquidated damage, penalty etc. recorded appropriately. • The label of TEQIP – III pasted on file (also on Equipment for unique identity). NATIONAL PROJECT IMPLEMENTATION UNIT (NPIU)

  12. Checklist for verification of Procurement Items • Equipment utilization register maintained in the concerned laboratory separately. • If the equipment is not working, communication regarding necessary follow up with the vendor. • Records for availability of EMD, EMD refunded (if any) and Performance Security (if any) are available. • In case of any dispute/ complaints with vendor regarding supply etc., relevant communication on actions taken. • All the documents/ proofs/ claims should be available in file. • All other documents related to Insurance, Bill of lading, customs clearance, license and permits, Cost escalations reasons and explanations etc. • The justification and minutes of PC, if procurement process is cancelled even after receiving adequate response and further repetitions. NATIONAL PROJECT IMPLEMENTATION UNIT (NPIU)

  13. Mechanism for Disposal of Complaints • The grievance/complaint must be given in writing with proper identity • In case of anonymous complaint, the decision of processing such complaint shall depend upon authority based on the severity and proofs attached with the complaint • The complainant has to lodge his complaint to the institute concerned first • If the institute does not take any decision or the complainant still remain aggrieved with the decision, the complainant may approach SPIU and wait for the timeline. • Complainant may approach NPIU further if not satisfied.

  14. Thank you.