An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Machine Advisory Committee Meeting no.19QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team

  2. Content • Layout • Fabrication status • Installation status • Schedule • Conclusions GR, AT-ACR

  3. QRL layout • QRL is a continuous cryostat of ~3.2 km length • no header (4 or 5) sectorisation 9 vacuum sub-sectors •  vacuum insulation separate from machine • QRL elements in one sector • ~ 38 service modules • ~ 40 fixed point/vacuum barrier elements • ~ 235 straight pipe elements • ~ 10 steps/elbows • ~ 1-2 cryogenic extensions GR, AT-ACR

  4. QRL layout Sector 3-4 8 sectors:- 7 installed by Air Liquide- 1 re-installed by CERN Sector 5-6 • = 650 mm E-F= 50-75 B,C,D = 4-20 K GR, AT-ACR

  5. QRL fabrication status GR, AT-ACR

  6. QRL installation status • External supports (~ 700/sector) Progress: 97 % GR, AT-ACR

  7. QRL installation status • Positioning and alignment (~ 325 elements/sector) Progress: 86 % GR, AT-ACR

  8. QRL installation status • Welding and testing: ~ 325 interconnections/sectors  ~ 2000 inner welds made by orbital welding machine • ~ 180 “O” type interconnections (1 butt-weld per header) • ~ 75 “C” type interconnections (2 butt-welds per header) • ~ 70 “A” type Interconnections (3 welds per header) GR, AT-ACR

  9. QRL installation status “C” type interconnections “A” type interconnections Special interconnections • Inner weld progress: 85 % • Nominal rate: 20 int./w • Achieved rate: 30 int./w GR, AT-ACR

  10. QRL installation status Mounting of superinsulation Welding of external compensators and visual check External weld progress: 81 % - Nominal rate: 20 int./w - Achieved rate: 35 int./w GR, AT-ACR

  11. QRL installation status • NDT tests • Internal (video camera) and external visual control: 100% • Radiography tests: from 100% to 10% as a function of weld quality • Leak tightness tests: 100 % • Helium to insulation vacuum • each weld (header pressurization at 1 bar): < 10-9 mbar·l/s • each sub-sector (header pressurization at 3 bar): < 10-8 mbar·l/s • each sector (in parallel with pressure test): < 10-7 mbar·l/s • Air to insulation vacuum: 10-5 mbar·l/s GR, AT-ACR

  12. QRL installation status • Percentage of defects of inner welds (visual and radiographic inspections) for the 3 types of interconnections: • According to machine parameters two categories are defined (B and CDEF) Air Liquide target value: 3% Main defects: porosity, lack of fusion, metallic inclusions GR, AT-ACR

  13. QRL installation status • Number of internal leaks (helium to insulation vacuum) • on installation welds: 8/12000 • 7 detected with the clamp shells • 1 detected in sector 6-7 during the test of the sub-sector (reason: operator error during the test with clamp shells) • on internal compensators: 2 (sector 3-4) • on backing rings: 2 (sector 4-5) • on service modules (header F): 7 (6 in sector 8-1 and 1 in sector 4-5) • Number of external leaks (air to insulation vacuum) on installation welds: • Sector 8-1: 12/4250 • Sector 4-5: 10/4250 • Sector 3-4: 11/4250 • Sector 5-6: 3/4250 • Sector 6-7: 6/4250 GR, AT-ACR

  14. QRL installation status Sector 8-1: - installation completed - pressure, leak and cold tests successfully performed GR, AT-ACR

  15. QRL installation status • Sector 4-5: • installation completed • pressure and leak test without the JR successfully performed • JR and sub-sector A pressure tested in parallel with the magnets GR, AT-ACR

  16. QRL installation status • Sector 3-4: • installation completed • pressure and leak test successfully performed • - repair of an external leak in sub-sector I under way GR, AT-ACR

  17. QRL installation status • Sector 5-6: • installation completed • pressure and leak test successfully performed GR, AT-ACR

  18. QRL installation status • Sector 6-7: • installation completed • pressure and leak test successfully performed GR, AT-ACR

  19. QRL installation status • Sector 2-3: • 3 teams working in sub-sectors A to I • installation progress: 74.4 % • 3 sub-sectors under pumping GR, AT-ACR

  20. QRL installation status • Sector 1-2: • 3 teams working in sub-sectors E to H • installation progress: 11.7 % GR, AT-ACR

  21. QRL schedule GR, AT-ACR

  22. QRL dashboard Total to be installed contract GR, AT-ACR

  23. Conclusions • Fabrication • Production of pipe elements, fixed points and service modules under completion • Production of steps/elbows foreseen to be completed in CW30 (compatible with installation schedule) • Installation • Installation of the last two sectors under way • Thermo-mechanical validation • Sectors 8-1, 4-5, 3-4, 5-6 and 6-7 (and 7-8 sub-sectors A and B) successfully leak and pressure tested • Sector 8-1 (and 7-8 sub-sectors A and B) successfully cold tested • Schedule • At present installation is about 2.5 weeks in advance (schedule revised in November 2005) GR, AT-ACR