1 / 12

Recent cross-wiring issue and implication for circuits protection

Recent cross-wiring issue and implication for circuits protection. Bozhidar Panev TE-MPE-CP 14.04.2011. Short chronology of the event from 07.04.2011. FPA during pre-cycle on RB.A45 at 07:12:09.270 Energy was extracted without problems. Current in main circuit – 2349A

naida
Télécharger la présentation

Recent cross-wiring issue and implication for circuits protection

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011

  2. Short chronology of the event from 07.04.2011 • FPA during pre-cycle on RB.A45 at 07:12:09.270 • Energy was extracted without problems. Current in main circuit – 2349A • The origin of the trip was found: • DQQDC board_A detected: U_HTS = 3mV and open the quench loop. U_RES in the same moment was ~20mV (threshold 100mV) • The new feature recently introduced in main current lead protection units toggles detector boards (every 25s) allowing to record U_HTS and U_RES also for the redundant channel (board_B)

  3. Short chronology of the event from 07.04.2011 • Unusual behavior has been pointed out between board A and B in respect of U_HTS. • Both two boards were checked through QPS Test Mode, simulating a voltage rise on the HTS and/or Resistive part • Correct performance observed of board A and B • Analysis of the event’s data and results from Test Mode bring the conclusion of abnormal behavior of U_HTS concerning board_B • Eventual short in the cable or inverted pins (Hypothesis of Reiner) • Giorgio also assured no errors found between PE and cold part of leads during ELQA campaign

  4. U_HTS Signals for CL3 and CL4

  5. What was wrong? • Intervention in the Tunnel to check the cabling and discover what was wrong • Cable patch - correct • The Error was found in connector P60 of cable between QPS crate and Proximity cable patch. Pin 15(EE22) and 16(EE42) were inverted.

  6. What was measured?

  7. Verification for correct wiring of 13kA circuits (RB,RQD,RQF) • Due to the available acquisition data from boards A and B. It became possible to check by TIMBER the rest RB, RQD/F circuits for swapped pins. • The only what was necessary to be done was take a look and check how U_HTS and U_RES behave during the rump. U_HTS Board_A I_MEAS U_HTS Board_B

  8. U_HTS Signals for CL3 and CL4 of DFLAS.7L5 • U_HTS stay flat during the rump - indication for problem • Normal behavior of U_HTS of CL3

  9. Verification for correct wiring of all IPDs, IPQs and ITs circuits – 08th of April • A dedicated PNO.a7 which does unbalanced powering was carried out over all IPQs. • As no automatic swap between boards. The test has been done twice. Once at board_A and second at board_B. • For IPDs and ITs a manual rump was done. • Difficulties that were found: • When tried to switch to board_B, some B_board did not give power permit (13 circuits). It has required a local power-cycle. • The analysis of U_HTS signals

  10. Criteria for correct wiring of IPQs, IPDs and ITs • Verification of U_RES and U_HTS for all IPDs, IPQS, ITs • Done for board A and B • Resistive part of leads during asymmetric powering of RQ.8R1 • HTS part of leads during asymmetric powering of RQ.8R1

  11. Conclusion 8th of April • On Thu 7th of April all 13kA circuits were checked for correct wiring. • On Fri 8th April all IPDs, IPQs, ITs also pased verification. • 600A were not checked because its were checked by QPS team before with a correct procedure and dedicated tester – all tests are documented • Green light for powering has been given

  12. END

More Related