This presentation by Bill Winslow, Program Manager of Bernards, outlines the accomplishments of the Measure L Construction Program from 2002 to 2011, as presented to the Citizens’ Oversight Committee on November 29, 2011. It highlights an estimated 350,000 square feet of new facilities and numerous site improvement projects across Chino, Fontana, and Rancho Cucamonga campuses. Key renovations include the Auto Tech Lab, Science Complex, and the Academic Buildings. Financials, schedules, and future projects in planning are also discussed, demonstrating a significant enhancement of the learning environments.
E N D
The ‘Measure L’ Construction Program • Presented By: • Bill Winslow • Program Manager, Bernards Presented to the Citizens’ Oversight Committee November 29, 2011 Presented by Bill Winslow Program Manager, Bernards
Summary November 29, 2011 COC Presentation • Completed Projects 2002-2011 • Chino Campus • Fontana Campus • Rancho Cucamonga Campus • Schedule • Financials • Questions • An estimated 350,000 square feet of new facilities and a multitude of completed site improvement projects have made a significant contribution towards improving the physical learning environment.
Completed Projects 2002-2011 (Partial Listing) November 29, 2011 COC Presentation • Renovate/Paint Auto Tech Lab • Infrastructure/Campus Theme • Environmental Impact Report • Renovate Athletics Office • Scoreboards • Snack Bar • Track & Field Timer • Stadium Flag Pole • Rad Tech Retrofit • San Antonio Comm. Hosp./CNA • Master Plan (Chino) • Vocational Education – Phase I • Wargin Hall – Phase I • Visitor’s Restroom/ADA Access • Science Complex Site work • Theater Fire Alarm • Bookstore Loading Dock • North Parking Lot Irrigation • North Parking Lot Landscaping • ATL Landscaping • Nature Preserve Fence • Central Plant Phase IA • Central Plant Phase IB • College Drive • Softball Field • Ralph M. Lewis Center (Fontana) • Wilson/College Dr.ive Intersection • Marie Kane Center for Student • Services/ Administration • Theatre – Phase I • North Parking Lot • Science Complex • Don Berz Excellence Building • College Drive Landscaping • Maintenance Yard Drainage • Agricultural Demonstration Area • Skills Road Extension • Fire Lane/Science Site Lighting • New Marquee • Physical, Health, and Life Science • Health and Life Science Re-Roof • Main Instructional Building (Chino) • New Elevator Tower • Parking Lot 12 • Health Sciences Bldg. (Chino) • Community Center Bldg. (Chino) • Library Lawn • Landscaping (Fontana) • Physical Science Complex Roof • Replacement • Language Arts/Social Science • Energy Project • Parking Lot Upgrades (Fontana) • Chino Health Science Parking Lot • Data and Telecom Cabling • Sports Center • Visual and Performing Arts Complex • Visual and Performing Arts Complex • Landscape Addition • Math Success Center & Physical • Science Renovations • Physical Education Facility • Gymnasium Renovation • Aviary Landscape • Central Plant Build Out – Phase 1C – • Hot Water Upgrades • Student Services/Administration East • Doors • Fire Alarm Upgrades
District Campuses November 29, 2011 COC Presentation
Chino Campus November 29, 2011 COC Presentation • Library/Learning Resource Center Future Location Projects in Planning
Fontana Campus November 29, 2011 COC Presentation Aerial View September 2011
Fontana Campus November 29, 2011 COC Presentation Projects Completed in 2011 • Academic Building • New 30,400 sq. ft. building includes: laboratories, lecture rooms, dance/yoga room, art studio, library, and bookstore
Fontana Campus November 29, 2011 COC Presentation Projects Completed in 2011 • Academic Building
Rancho Cucamonga Campus November 29, 2011 COC Presentation Aerial View September 2011
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Greenhouse • Estimated Completion: December 2011 Projects Under Construction • Installation of a prefabricated greenhouse structure at the Science Complex
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Business Education Renovation Projects Completed in 2011 • Interior and exterior renovation of the existing Business Education building includes energy and accessibility upgrades
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Michael Alexander Campus Center Projects Completed in 2011 New 16,454 sq. ft. two-story building includes: staff and student dining rooms, coffee bar, kitchen and server, health services, student government, Extended Opportunity Programs & Services, and career services
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Michael Alexander Campus Center Projects Completed in 2011
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Projects in Pre-Bid • Central Plant Build Out – Phase 1C – TES Tank • Installation of thermal energy storage tank and six new boilers at Central Plant • Health Science Pathway • Addition of a concrete pathway from Health Sciences to the Michael Alexander Campus Center • North Parking Lot Drainage • Addition of drainage systems at Parking Lot 4 • Projects in Design • Physical Education Athletics – Parking Lot and Flagpole • Parking lot resurfacing and striping with new flagpole • Community Trail Landscaping • Landscaping and irrigation
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Projects in Planning • Language/Liberal Arts and Letters • Library Remodel/Expansion • Wargin Hall Remodel • Vocational and Student Service Support Remodel
Construction Cost Summary November 29, 2011 COC Presentation Completed Projects 2009-2011
Summary of Funds November 29, 2011 COC Presentation Program Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses) Measure L Bond Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses)
Remaining Funds November 29, 2011 COC Presentation Program Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses) Measure L Bond Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses)