1 / 3

Revised Schedule for SP Pre-Production

Revised Schedule for SP Pre-Production. Continued testing of first two pre-production boards over next 2 weeks Hopefully validate SP04 layout with reworked boards Lev leaves for PNPI Quotes from new vendors in progress; selection this month

nau
Télécharger la présentation

Revised Schedule for SP Pre-Production

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Revised Schedule for SP Pre-Production • Continued testing of first two pre-production boards over next 2 weeks • Hopefully validate SP04 layout with reworked boards • Lev leaves for PNPI • Quotes from new vendors in progress; selection this month • Submit new pre-production order for 2 boards at beginning of April to new vendor • Manufacture 2.5 weeks • Inspection 0.5 week • Assembly 3 weeks • New round of testing begins mid-May • Lev returns from PNPI • Testing should go fast if no problems (software in hand) • Complete by beginning of June D. Acosta

  2. Revised Schedule for Main Production • Submit remaining production of 12 boards June 1 • Boards ready for testing August 1 • Board tests completed October 1 • Full crate tests of 12 SP’s with Muon Sorter takes 2 months, as previously requested • Therefore, full production not fully tested and available until December 2005 • However, 4 other new SP04’s available October 1 • One or more SP02’s available ~now • Critical items are mezzanine cards, TF backplanes D. Acosta

  3. Mezzanine Card Supply • Four SP/MS prototype mezzanine cards made and all in use • Two for Rice MPC/MS production tests • Two for SP production tests • None currently available for Slice Tests or other integration tests at CERN • Possible that one from UF could be supplied to CERN for April • Rice needs 2 continuously? • No Track-Finder at CERN for Slice Tests until current mezzanine card production completed • Connectors must be installed, cards must be fully tested (the BGAs were installed by Conquest…) • Maybe not a problem if no tests can take place at SX5 because of infrastructure issues there for the time being D. Acosta

More Related