1 / 23

Master Production Schedule

Master Production Schedule. Overview. Define M aster P roduction S chedule Explain MPS Discuss How MPS Works Example From “Real Life” Brainstorm: How Can MPS Help Your Firm? Practice MPS. What is MPS?.

davido
Télécharger la présentation

Master Production Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Master Production Schedule

  2. Overview Define Master Production Schedule Explain MPS Discuss How MPS Works Example From “Real Life” Brainstorm: How Can MPS Help Your Firm? Practice MPS

  3. What is MPS? Master Production Schedule – States the requirements for individual end items by date and quantity.

  4. MPS Explained Breaks down, or disaggregates, the production plan into product families Promotes valid order promises Provides a communication medium between Marketing/Sales and Operations

  5. Explanation Continued Proactively control ability to deliver goods to customers Resource availability control Proactively control inventory levels

  6. Objectives of Master Production Schedule (MPS) 1. Keeping the inventories at the desired level by making perfect use of the resources that are available with the company. 2. Setting up due dates for the availability of the end items and also providing the required information regarding resources and also the materials – which act as the supporting pillars of the aggregate planning. 3. Maintaining properly, the desired level of customer service. 4. Setting particular schedules for the production of the parts and the components that are used as the inputs to materials requirements planning, in the end items.

  7. Disaggregate the Sales and Operations Plan The production plan is broken into product families

  8. Promotes Valid Order Promises By validating the capacity for the MPS through rough cut capacity planning, alterative plans can be made when there are more orders than production

  9. Marketing  Operations Marketing communicates demand through customer orders and forecasts Operations communicates capacity through inventory levels and constraints

  10. The main steps in master production schedule can be summarized as –1. Forming a preliminary MPS.2. Performing rough – cut capacity planning.3. Resolving differences.

  11. Resource Availability Control Production shortfalls will be known ahead of time and alternative plans can be made.

  12. Customer Service Proactively control ability to deliver goods to customers

  13. Why is it important to deliver to customers on time or when promised?

  14. Inventory Control • Proactive approach to inventory control • Items are scheduled to arrive when needed • Safety stock has less importance

  15. Planning Organization

  16. A good master scheduler always tries to consider the following five key questions before making any final decision for changing the master schedule – 1. Is there any real change in demand?2. What is the impact on the production plan?3. Is material available?4. Is capacity available?5. What are the risks involved?6. What are the costs involved?

  17. Inputs into the MPS Known Orders Key Capacity Constraints Demand Forecast Master Production Schedule (MPS) Inventory Levels Sister Plant Demand Spares Demand R & D Demand Exhibition/ Promotion Requirements Safety Stock Requirements

  18. How MPS Works • Information needed for MPS logic • Lot Size • Lead Time • Product Demand • Starting Inventory

  19. Summary MPS breaks the Sales & Operations plan into product families Maintains Desired Level of Customer Service Allows proactive control of inventory

  20. Calculating the Master Production Schedule (MPS) Opening Stock = 40 units Minimum Batch Size = 15 units

  21. Exercise 1 Siyabonga Textiles, a manufacturer of women’s garments has compiled the following sales forecast for the months of June and July 2016: The opening inventory for this period was 50 units and the factory can only produce batches of 12 units. Calculate: Projected on hand inventory Master Production Schedule Available to Promise (ATP)

  22. Exercise 2 Nomvete Garments, a manufacturer of women’s garments has compiled the following sales forecast for the months of June and July 2016: The opening inventory for this period was 850 units and the factory cab only produce batches of 1200 units. Calculate: Projected on hand inventory Master Production Schedule Available to Promise (ATP)

  23. Exercise 3 Siyafunda Fashion, a manufacturer of women’s garments has compiled the following sales forecast for the months of June and July 2016: The opening inventory for this period was 650 units and the factory can only produce batches of 1350 units. Calculate: Projected on hand inventory Master Production Schedule Available to Promise (ATP)

More Related