1 / 14

SmartMeter TM Steering Committee Update – March 2012

SmartMeter TM Steering Committee Update – March 2012. Agenda. Monthly Updates Release Status Update Deployment Status Update Schedule Update Deployment Update Budget Status – Expenditures by Workstream Budget Status – Benefits Issues / Risks Summary Program Metrics Appendix

neil
Télécharger la présentation

SmartMeter TM Steering Committee Update – March 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SmartMeterTMSteering Committee Update – March 2012

  2. Agenda • Monthly Updates • Release Status Update • Deployment Status Update • Schedule Update • Deployment Update • Budget Status – Expenditures by Workstream • Budget Status – Benefits • Issues / Risks Summary • Program Metrics • Appendix • Project Deployment Plan Progress • Contingency Reconciliation • SmartMeterTM Acronyms

  3. Release Status Update Actions/Status Challenges

  4. Deployment Status Update Challenges Actions/Status * 2012 Schedule and installation targets under review

  5. Schedule Update As of 2/29/12 2011 2012 Apr Jun Nov Dec Mar May Jan Feb Sep Oct May Jul Apr Jun Aug IT Release Deployment Electric ‘head-end’ system upgrade Release 1 Performance & Scalability Improvements Exception Management Improvements Remote Connect Disconnect Release 2 Outage Identify & Scope Release 3 ExceptionManagement Improvements and NEMs deploy Exception Management Improvements and Momentary Outage Tracking Performance & Scalability Improvements SM Operations Center SMOC Phase 1.0 Deploy 9.0M Meters/Modules in service ‘Initial Design’ Network Deployed Field Delivery Begin SmartMeter Opt-Out Program Begin NEMS pilot Benefits Meter Reading Reductions (ITD) 594 Positions Captured Legend Forecasted Milestone (delay) Baseline Milestone Milestone Met Milestone TBD Approved Milestone (delay) Forecasted Milestone (early)

  6. Deployment Update As of March 2, 2012 #s as of 3/2/12 2012 Targets under review

  7. 2012 Budget Status – Expenditures by Workstream * Year-to-Date Variance Explanations: Unfavorable YTD capital variance ($1.5M) primarily due to larger than planned third party installer accruals and payments (#3), along with the timing of IT progress payments (#5). Favorable YTD expense variance ($1.7M) primarily due to lower spending in Customer of $0.8M (#10) and Business Operations/PMO of $0.4M (#7). *Revised based on final 2012 deployment schedule and timing.

  8. 2012 Budget Status – Benefits

  9. Issues Summary

  10. Risks Summary

  11. Program Metrics #s as of 02/29/12 2012 Targets under review

  12. Project Deployment Plan Progress Combined Gas and Electric Plan, Targets, and Actuals (Cumulative) 2012 Targets under review

  13. Contingency Reconciliation

  14. SmartMeterTM Acronyms

More Related