An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Process of Siting and Approving a New Landfill in Ontario BY KYRA BRENNAN

  2. Overview • Introduction • Legislation Involved of Site Selection • Regulatory Requirements for Certificate of Approval: • Design Specifications • Buffer Area • Environmental Assessments • Operations • Limitations & Concerns • Video • Questions

  3. Introduction • Purpose of landfills existing for health and economic reasons recently began to include environmental awareness • Legislative Acts passed in 1990’s to regulate waste management • Environmental Protection Act (EPA), Regulation 347, 232/98

  4. Legislation

  5. Regulatory Requirements

  6. The proposal must explain in detail a design that will account for the landfill from start to finish. Specific elements of the design include: • The proposed site boundaries, buffer area, waste fill area and contours, surface water control works, on-site roads and structures, and final cover design • The design of any liner and leachate collection system or landfill gas control works needed for the site • Monitoring facilities for groundwater, leachate and surface water • A contingency plan for leachate control • Site closure and post-closure care requirements (MOE, 1998) DESIGN

  7. Buffer Zone: area surrounding the landfill • Provides pace for monitoring, maintenance and environmental control • Atleast 100 meters wide at all areas (Certificate of Approval process can reduce space to 30 meters) • Area for potential effects of landfill to be caught before outside of buffer zone. Potential effects are: • Surface runoff • Litter • Vectors • Leachate • Subsurface migration of landfill gas • Aesthetic effects BUFFERZONE

  8. ASSESSMENTS

  9. Other Criteria • Other criteria that must be met in the design proposal: • Leachate disposal and contingency plans • Surface water control • Subsurface migration of landfill gases • Emissions • Designs for engineered facilities • Noise • Operation and maintenance procedures • Financial assurance

  10. Operations • Site Preparation • Record Keeping • Operations Report • Public Liaison Committee • Burning/Scavenging • Leachate Monitoring • Daily/Final Cover • Final Slopes • Closure Report • Annual Post-Closure Report

  11. Implications & Concerns VIDEO

  12. Conclusion Efforts must be made to accommodate the waste, divert more waste from landfills, and begin the process of reducing the overall quantity of waste generated. Thank You

  13. References Canada. Government of Ontario. Environmental Assessment process requirements for certain waste management sites. By Environmental Registry. Ministry of Environment, 2007. Chesed, Mindorff. The Process for Citing and Approving a New Landfill in Ontario. Rep. Brock University, 2006. Environmental Assessment Act. Guide to Environmental Assessment Requirements for Waste Management Projects. By Legislative Authority. Government of Ontario, 2007. Environmental Commissioner of Ontario. 2007/08 Annual Report - Getting to K(No)w. Rep. Speaker of Legislative Assembly, 2008. International LTD, RIS. The Private Sector IC&I Waste Management System in Ontario. Rep. Ontario Waste Management Association, 2005. Lawson, Oates. Status of Disposal Capacity in Ontario and Exports to the US. Rep. Toronto: SWMS, 2006. Ministry of the Environment. Landfill Standards: A Guideline on the Regulatory and Approval Requirements for New or Expanding Landfilling Sites. Government of Ontario, 1998. Unknown Author. "Landfill Sites in Northwestern Ontario: Issues and Opportunities." Review. Workshop Summary 2 Mar. 2005. Unknown Author. "The Environmental Impacts of Ontario’s Small and Aging Landfills – Who Is Keeping Track?" ECO Issues. Feb. 2009. <http://www.ecoissues.ca/wiki//index.php?title=The_Environmental_Impacts_of_Ontario%E2%80%99s_Small_and_Aging_Landfills>. Willms, John. "How Planning Act Strategies Can Compensate for MOE Laissez Faire." Municipal World (1998).