1 / 42

Market Trials

Market Trials. Weekly Update – Friday Meeting December 6, 2013. Agenda. IDT Debrief: 9:00 – 10:00A IDT Conditions, 9:00-9:10A IDT Report Review: IDT 11/19 and IDT 11/21, 9:10-9:30A IDT 12/3 Preliminary Debrief, slides for reference only IDT 12/5 Preliminary Debrief, 9:30-10:00A

nero
Télécharger la présentation

Market Trials

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Market Trials Weekly Update – Friday Meeting December 6, 2013

  2. Agenda • IDT Debrief: 9:00 – 10:00A • IDT Conditions, 9:00-9:10A • IDT Report Review: IDT 11/19 and IDT 11/21, 9:10-9:30A • IDT 12/3 Preliminary Debrief, slides for reference only • IDT 12/5 Preliminary Debrief, 9:30-10:00A • Analysis: 10:00 – 10:20A • Parallel Ops Participation and QuickStart Reminders, 10:00-10:10A • Scenario Analysis, 10:10-10:20A • Look-Ahead: 10:20 – 10:50A • Announcements and Release Updates, 10:20-10:30A • Look-Ahead, 10:30-10:40A • Updates, 10:40-10:50A • Release Scorecard • Migration Report • Known Issues Log • Settlements: 10:50 – 11:00A

  3. IDT Conditions page 1 of 2 • IDT Conditions posted to spp.org here spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test Casey Cathey

  4. IDT Conditions page 2 of 2 Casey Cathey

  5. IDT 11/19 Report IDT reports to be posted to spp.org here7 calendar days after each IDT spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test IDT 11/21 Report IDT reports to be posted to spp.org here7 calendar days after each IDT spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test Brian Strickland / Carrie Simpson

  6. 12-03-13 Deployment Test Debrief • Overall the Third Deployment test was another great success • Overall SPP BA ACE and frequency were in acceptable ranges throughout the duration of the test • EIS BA’s had no problems switching from EIS setpoints to IM setpoints and back again • No major problems were reported by SPP or the MPs during the test • Able to start and stop the test on time as scheduled with no delay, reduction or extension For Reference only

  7. 12-03-13 Deployment Test Debrief • Though a “Success” there are things we can improve upon • MATCHING EIS and IM Offers – Parallel Operations vs. IDTs • During all of Parallel Operations EIS offers, unit parameters and Ancillary Service plans should closely track to those in the IM • The Parallel Operations MP Guide describes a close tolerance between EIS and IM that applies to all of Parallel Operations • For IDTs SPP needs MPs to start matching offers 4 hours prior to IDTs to allow time to work out any mismatches – by the time the open calls start all mismatches should be worked out • For IDTs getting Ancillary Service plans consistent is critical for all hours of the tests For Reference only

  8. 12-03-13 Deployment Test Debrief • Though a “Success” there are things we can improve upon • Participants need to be on the calls when they start 60 minutes prior to each IDT • When the calls were initiated there were BAs and MPs that needed to be individually contacted to get them to call in and give a “Go” vote. • Minor problems were addressed quickly and didn’t create any reliability concerns • COP True-up wasn’t dealing with a specific unit correctly and SPP worked with the MP to manually get the unit on-line. For Reference only

  9. 12-05-13 Deployment Test Debrief • Overall the Fourth Deployment test was another great success • Able to start and stop the test on time as scheduled with no delay, reduction or extension • EIS BA’s had no problems switching from EIS setpoints to IM setpoints and back again • Smooth entry into the test • No major problems were reported by SPP or the MPs during the test • Saw a number of schedule changes throughout the IDT – no issues • Line came of at 0800 – no issues Brian Strickland / Carrie Simpson

  10. 12-05-13 Deployment Test Debrief • Though a “Success” there are things we can improve upon • Slightly out of balance ~0800 • CPS 2 violation during the test from 0800 – 0810 • MATCHING EIS and IM Offers – Parallel Operations vs. IDTs • During all of Parallel Operations EIS offers, unit parameters and Ancillary Service plans should closely track to those in the IM • The Parallel Operations MP Guide describes a close tolerance between EIS and IM that applies to all of Parallel Operations • For IDTs SPP needs MPs to start matching offers 4 hours prior to IDTs to allow time to work out any mismatches – by the time the open calls start all mismatches should be worked out Brian Strickland / Carrie Simpson

  11. 12-05-13 Deployment Test Debrief • Though a “Success” there are things we can improve upon • SPP wants to understand what is preventing MP Resources from following deployments • Please follow deployments • Please communicate any issues with SPP • Participants need to be on the calls when they start 60 minutes prior to each IDT • All BA’s were on the call on time – Thank You! • 4 MPs needed to be individually contacted to get them to call in and give a “Go” vote. Brian Strickland / Carrie Simpson

  12. Integrated Marketplace RTBM Submissions • Currently, SPP is having to request updates to IM offers just before IDTs to be consistent with EIS offers • During Parallel Operations, members should keep Integrated Marketplace offers consistent with EIS offers From the Parallel Operations MP Guide: • SPP has begun to track EIS vs IM offer percentages, and will send a reminder email each week to all MPs who are not participating consistently • Market Participants shall update RTBM submissions as follows: • If a unit goes offline or comes online in the EIS market, update RTBM submissions • If a unit’s min/max capacity changes by >10% or 5 MW, whichever is greater, in the EIS market, update RTBM submissions • If a unit’s offer curve changes by >10% or $2 per 5 MW, whichever is greater, in the EIS market, update RTBM submissions Casey Cathey

  13. Quick Start Resources • In Marketplace there a two different types of quick start resources • Quick Start resources similar to “Quick Start Status” in EIS Market • Dispatched only in the RTBM • No Start instruction sent to MPs • Resources that can quickly get online (less than 10 minutes) and qualified for off-line supplemental • Committed by SPP in RUC or Contingency Reserve Deployment process • Start Instructions are sent to MPs Carrie Simpson

  14. Quick Start Resources Carrie Simpson

  15. TRL-01: MP Participation in Parallel Ops • Reminder!Participation in Parallel Ops is still being tracked via Readiness Metric TRL-01 • As of 12/6, the metric is REDdue to insufficient participation by one BA (KBPU) • The status of the Readiness Metrics as of 12/20 will be included in the 12/27 FERC Readiness Filing • The status can go back toGREENif Target Mass participates sufficiently (i.e. in at least 80% of the ODs) during the first part of December • Metric measurement criteria is available in v5.0 of the Readiness Metrics posted in the Readiness folder Erin Jester

  16. OPS-16: MP Response to Deployment Testing • Reminder!Participation in Deployment Testing is being tracked via Readiness Metric OPS-16 • In order to be GREEN, one or more of the MP’s online units must respond to dispatch instructions during a deployment test • Participation in IDT calls (pre, post, and test) is required for MPs with online units • The status of the Readiness Metrics as of 12/20 will be included in the 12/27 FERC Readiness Filing • Metric measurement criteria is available in v5.0 of the Readiness Metrics posted in the Readiness folder Erin Jester

  17. Preliminary Scenario Results • Scenario 24 Re-pricing ran Tuesday Dec 3 • SPP recalculated Real-Time LMP and MCP prices for the interval(s) listed below due to bad or missing SCADA for operating day 12/04/2013 • Substitute prices will be included on the initial settlements statements 7 days from the OD • Repricing on initial settlements statement will be posted on 12/11/2013 • Re-calculated prices are available on the IM Portal in the Public Data section • Intervals (CPT): • 12-04-2013 09:25 12-04-2013 09:30 • 12-04-2013 09:35 12-04-2013 09:40 • 12-04-2013 09:45 12-04-2013 09:50 • 12-04-2013 09:55 12-04-2013 10:00 • 12-04-2013 10:05 12-04-2013 10:10 • 12-04-2013 10:15 12-04-2013 10:20 • 12-04-2013 10:25 12-04-2013 10:30 • 12-04-2013 10:35 12-04-2013 10:40 Alan Adams

  18. Scenario Results • Scenario 15 Commitment Mismatch Part 2 • Successfully executed on Nov 25 for OD Nov 26 • 20 Resources participated • Resources with commit status of “Outage” recommended for Call Off • Scenario results were posted to the UI and notifications were generated and sent • If MPs did not see their commitment due to the COP True Up process, MPs can check their past commitments in the MUI • Resources Offers tab: Date > Resources > Resource Name > Commitment History Alan Adams

  19. Scenario Tracker as of Dec 4 • Summary – Scenarios in Parallel Ops: • 1 Scenario and 2 Partial Scenarios Executed successfully to date: • Scenario 7 Must Offer pending Settlements results • Scenario 28a Successful • Scenario 15 Commitment Mismatch Part 2 • Summary – Retests Pending: • 13 individual retest requests pending • 6 MPs requested retest for Scenario 34 • 3 MPs requested retest for Scenario 2 • 1 MP requested retest for Scenario 3 • 2 MPs requested retest for Scenario 12 • 1 MP requested retest for Scenario 33 Ginny Watson

  20. webMirroring Disabled Dec 16 Casey Cathey

  21. Start Practicing Tags Casey Cathey

  22. MOS 1.9 Functionality • Functionality Coming in 1.9 • FERC Mitigation Changes • Pre-RTBM now has Time Coupled scenarios available (previously just non-time coupled, now both are available) • RTBM DVER MCE Logic • External Interfaces NNLLimits Fixes • RRC Additional Functionality • RTBM EDR Fixes • Markets UI, Validation, and Web Service fixes • Internal Scenario Retests with 1.9 • New Mitigation FERC Changes • Scenarios: 16.1, 16.2, 16.3 • KIL #742 • Scenarios: 5.1, 5.2, 6.1, 6.2 • Known Issues Log Coming in 1.9 • 706, 817, 781, 139, 262, 467, 724, 752, 837, 786, 787, 793, 796, 822, 820, 815, 813, 812, 810, 806, 805, 804, 827, 742, 771, 789, 794, 823, 811, 848 Carrie Simpson

  23. MOS 1.9 Testing Approach • Accelerated installation schedule is planned to comply with the 1/1/14 system wide freeze • All regression testing and defect retesting planned to complete by 12/20 (before Holiday breaks) • Extended hours and weekend work to sprint through testing to make 12/20 goal • 1.9 and 1.9Plus Testing Approach • Full regression of new Mitigation FERC Changes • Full MCE Regression • Standard regression and defect testing across all functional areas • Risks: • Resource time and capacity constraints for accelerated testing schedule • Mitigating risk by working additional hours • SPP has seen approximately a 10% defect failure rate from previous releases • Pending the failure rate of 1.9 and 1.9Plus, and what defects fail in these releases, there is a potential the system freeze will be at risk • If another patch is required after 1.9Plus, it will move testing into January Carrie Simpson

  24. MOS 1.9 Testing Approach • MOS 1.9 Install Schedule • PROD: 12/30/13 • Mos1.9Plus Install Schedule • PROD: 12/30/13 Carrie Simpson

  25. Announcements • Second Dual listener working as of R1.8 • Scenario 29 RSG will be run Monday Dec 16 • Originally scheduled Tuesday Dec 17 Ginny Watson

  26. Announcements • Posting TCR model through True Share now Wendy Reynolds

  27. Announcements IDT Schedule Updates on Parallel Ops Calendar on spp.org spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test (as part of Parallel Ops) • IDT Call on Dec 17 2:30a – 8:30a 4hr IDT begins at 3:30a Originally scheduled 12/17 for 9:30P to 12/18 1:30A • IDT in January to cross midnight (TBD which one) • IDT times listed on the calendar reflect the call start times IDT Calls begin 60 minutes before the IDT officially starts Casey Cathey

  28. Dispatch Simulator • *Scenario document on spp.org here • spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents > Scenarios in Parallel Ops 0:00 12/06 to 23:59 12/09 • MPs should offer their Resources as they expect to do in Production • SPP will not be running any COP True-ups • Commitments will only come from DBDA, DA Market, DARUC, IDRUC, and MP Self Commitments • MPs should be looking at commitment notifications and understand that this is how SPP expects to run at Go Live • SPP will overwrite meter settlement data for the four Operating days Dec 6, 7, 8, and 9 with RTBM setpoint instructions Alan Adams

  29. Look-Ahead: Nov 25 – Dec 1 Parallel Ops Calendar on spp.org spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents • Settlements details on the Settlements Calendar marketplace.spp.org > Public > Settlements > Calendars Dec 9: IDT Prep Call 3P Dec 10: IDT Call 12:30 – 4:30P Dec 11: Scenario 31 BDR Scenario 13 DDR IDT Debrief and Prep Call 3P Dec 12: IDT Call 5:30A – 10:30A Dec 13: Parallel Ops/Go Live Checkpoint & IDT Debrief 9A IDT Sunday Dec 15 Prep Call Non-Functional Scenario 10:00P – 12:00A Dec 15: IDT Call 11:30A – 5:30P Ginny Watson

  30. Scenario 31 BDR w/ Settlements • *Scenario document on spp.org here • spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents > Scenarios in Parallel Ops • Scenario Description • Verify functionality specific to BDRs • MP Activities • Verify that BDRs have valid offer data for all products • Ensure all required real-time measurements are defined and being submitted to SPP via ICCP • Submit hourly DRL forecasts when required for BDR resources • Verify that Dispatch Instructions are received via XML the same as other Resources • Submit meter data for time that BDR is dispatched Alan Adams

  31. Scenario 13 DDR w/ Settlements • *Scenario document on spp.org here • spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents > Scenarios in Parallel Ops • Scenario Description • Verify functionality specific to DDRs • MP Activities • Verify that DDRs have valid offer data for all products • Offers should be such that DDR will clear and be dispatched • Ensure that all required real-time measurements are defined and being submitted via ICCP • Submit hourly DRL forecasts when required for BDR and Calculated DDR resources • Verify that Dispatch Instructions are received via XML the same as other Resources Alan Adams

  32. Non-Functional Testing • *Scenario document on spp.org here • spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents > Scenarios in Parallel Ops • Scenario Description • SPP will simulate an outage at the Chenal facility for Reliability and Markets redundancy • Non-Functional Test includes critical Tier 0 and Tier 1 components to demonstrate that those systems can be entirely supported and function independently in the back-up Operations Data Center in Maumelle • Expected Result • EMS is fully functioning with RTGEN for CBA • ICCP is fully functioning and sending setpoint instructions • Marketplace Portal User Interface and API is available for data entry and retrieval • Web Services (RTO_SS) is available • Markets system is fully functioning and solving RTBM for approximately one hour • Email is available for sending and receiving communication Casey Cathey

  33. Non-Functional Testing • MP Activities • MPs should continue normal operations with no expected downtime. • If any unexpected results occur, please submit a detailed RMS Ticket here • Verify the following during Non-Funct Testing Dec 13 at 10P – Dec 14 at 12A CPT • ICCP setpoint instructions are received • XML notifications are received • Marketplace Portal User Interfaces and API’s are available for data entry and retrieval Casey Cathey

  34. Schedule Dec 9 - 15 • Dec 9: IDT Prep Call 3P • Dec 10: IDT Call 12:30 – 4:30P (2 hr test begins at 1:30P) • Dec 11: Scenario 31 BDR • Scenario 13 DDR • IDT Debrief and Prep Call 3P • Dec 12: IDT Call 5:30A – 10:30A (3 hr test begins at 6:30A) • Dec 13: Parallel Ops/Go Live Checkpoint & IDT Debrief 9A • IDT Sunday Dec 15 Prep Call • Non-Functional Scenario 10:00P – 12:00A • Dec 15: IDT Call 11:30A – 5:30P (4 hr test begins at 12:30P) Ginny Watson

  35. Schedule Dec 16 - 22 • Dec 16: Scenario 29 RSG • webMirroring Disabled • IDT Debrief and Prep Call 3P • Dec 17: Scenario 11 EDR • IDT Call 2:30A – 8:30A (4 hr test begins at 3:30A) • Dec 18: CWG • IDT Debrief and Prep Call 3P • Dec 19: IDT Call 5:30A – 9:30A (2 hr test begins at 6:30A) • Dec 20: Parallel Ops/Go Live Checkpoint & IDT Debrief 9A • MP Readiness Cert Form Ginny Watson

  36. Migration and Maintenance Report Migration and Maintenance Report posted to spp.org spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents Wendy Reynolds

  37. Release Scorecard Release Scorecard posted to spp.org: spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents Ginny Watson

  38. Known Issues Log • Please review the Market Trials Known Issues Log on spp.org spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder Carrie Simpson

  39. Known Issues Log Carrie Simpson

  40. Market Trials Useful Resources Integrated Marketplace Parallel Operations Project Documents spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents • Parallel Ops Presentations, Statistics, MP Meetings Folder • Parallel Ops Reference Documents Folder • Scenarios in Parallel Ops Folder > Scenarios Schedule • Parallel Ops Communication Plan • Parallel Ops MP Guide • Parallel Ops Calendar • Known Issues Log • Release Scorecard • Migration Report Integrated Deployment Test (as part of Parallel Ops) spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test • IDT MP Guide • Parallel Ops Calendar Additional documents: • Settlements Calendarmarketplace.spp.org > Public > Settlements > Calendars • Change Trackerspp.org > Integrated Marketplace > Marketplace Documents • Integrated Marketplace Structured/Unstructured Test Project Documents spp.org > Integrated Marketplace > Market Trials > Structured / Unstructured Test> Integrated Marketplace Structured / Unstructured Test Project Documents

  41. Settlements Status • The November ETSE release was moved into production 12/5/2013. • Included the following charge types: DaDRHrlyAmt , DaDRDistHrlyAmt, RtDR5minAmt, RtDRDistHrlyAmt • DaGFAAoAmt, DaGFAAoMnthlyAmt, DaGFAAoYrlyAmt, RtRnuMnthlyAmt, RtRnuYrlyAmt were also included but (as previously communicated) due to recent FERC changes the final version of these will be in the December release • The 12/1 initial and the 11/23 final are the first Operating Days processed using this new release Brent Wilcox

  42. Settlements Status • The December release is due from Alstom today (12/6/2013). This release is what we will take into the code freeze (installed into production early January). Brent Wilcox

More Related