An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management in Practice Scheduling The Project

  2. Outline: • Project network diagrams • Identifying critical paths and activities • Determining activity slack times • Gantt charts • Working with Microsoft Project • Uncertainty and risk management • Simulation approach to managing risk Homework: 25, 27, 31

  3. The Big Picture The Planning Process Project Conception Launch Meeting Action Plan WBS Project Master Schedule Scheduling Resource Allocation

  4. The Big Picture Define Activities WBS Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

  5. Project Scheduling Terms • Activity • Event • Node • Milestone • Network • Path • Critical Path – The longest path through a network • Critical Time

  6. Network Diagrams f g e

  7. Network Diagrams

  8. Manual Network Example

  9. Manual Network Deterministic Examples

  10. Project Description Project Table 5-3 • Notes: • Under View, Check Viewbar • Under Tasks, define general working times, use the wizard to • Standard time, 2) Select all 7 days use hours shown in preview, 3) omit, 4) Hrs/day=8, Hrs/wk=40, Days/month=30 • Enter task names (a, b, c, etc.), durations, and predecessors as numbers. • Under Tasks, add columns of custom information, to add ES, EF, LS, LF, and Total Slack (MSP will calculate these automatically) MSP Intro Example 1 of 4

  11. Project Information & Network Layout Notes: Project Project Information Notes: Diagram, Format, Layout Allow manual box positioning Link style = Straight MSP Intro Example 2 of 4

  12. Network Diagram Notes: Diagram, Format, Layout Allow manual box positioning Link style = Straight MSP Intro Example 3 of 4

  13. Gantt Chart Notes: Format Gantt Chart Wizard MSP Intro Example 4 of 4

  14. Project Uncertainty & Risk Management Probabilistic / Stat Examples

  15. Probability of Completing a Path by Time D Z = The number of standard deviations D is from m D = Analyzed project or path completion time m = the sum of the expected path durations Te along a particular path being investigated s = path standard deviation s2 = path variance =NORMSDIST(D, m, s, TRUE), (left area) cumulative probability Probabilistic / Stat Examples

  16. Manual Network Probabilistic/Stochastic Example Probabilistic / Stat Examples

  17. Project Uncertainty & Risk Management Example Chapter 5 22.83 35.17 35.17 44.5 c f 25.33 37.67 37.67 47 0 10.67 10.67 22.83 22.83 28.83 28.83 39.17 d g a b 22.83 28.83 28.83 39.17 39.17 47 0 10.67 10.67 22.83 h 22.83 37.17 e 39.17 47 24.83 39.17 Probabilistic / Stat Examples

  18. Example Chapter 5 What is the probability the project critical path will complete within 50 days? What is the probability the project will complete within 50 days? Follow on question: There is a 95% probability we will complete the critical path in how many days? Probabilistic / Stat Examples

  19. Project Uncertainty & Risk Management Probabilistic / Stat Examples

  20. Simulation Potential Path Completion Times 1000 Trials c f Potential Project Completion Time = ??? d g a b h e

  21. Simulation – Example Chapter 5 (Table 5-8) Project completion time for this particular step / trial

  22. Simulation – Example Chapter 5

  23. Simulation – Example Chapter 5 What is the probability the project will complete within 50 days?

  24. Simulation – Example Chapter 5 There is a 95% probability we complete the project in about 54 days or less.

  25. Exercise DynaTech Equipment Corp. case (45 minutes) • Divide into small groups • Read case (5 minutes) • Assignment: (40 minutes) • List the immediate predecessors and WBS number for each activity • Draw project network diagram (lowest level) • Draw Gantt chart • Determine project completion time