1 / 26

viNGN CCI Build Update

viNGN CCI Build Update. Broadband Business and Technology Committee Meeting October 7, 2013. Agenda. Introductions Fiber cable deployment progress FAP construction progress and completion schedule Connecting to CAI’s Undersea cable deployment progress. St. Croix (West). STX15

nixie
Télécharger la présentation

viNGN CCI Build Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. viNGN CCI Build Update Broadband Business and Technology Committee Meeting October 7, 2013

  2. Agenda Introductions Fiber cable deployment progress FAP construction progress and completion schedule Connecting to CAI’s Undersea cable deployment progress

  3. St. Croix (West) STX15 DROPS: 76% CAI: 0/17 STX06 DROPS: 50% CAI: 0/6 STX05 DROPS: 0% CAI: 0/11 STX04 DROPS: 0% CAI: 0/4 STX02 DROPS: 100% CAI: 2/27 STX03 DROPS: 100% CAI: 0/13 STX16 DROPS: 0% CAI: 0/7 Backbone Innerduct Placed Backbone Fiber Installed

  4. St. Croix (East) STX12 DROPS: 0% CAI: 0/1 STX07 DROPS: 0% CAI: 0/4 STX17 DROPS: 0% CAI: 0/22 STX09 DROPS: 57% CAI: 0/14 STX13 DROPS: 0% CAI: 0/7 Backbone Innerduct Placed Backbone Fiber Installed

  5. St. Thomas (West) STT05 DROPS: 0% CAI: 0/7 STT02 DROPS: 88% CAI: 0/8 STT01 DROPS: 44% CAI: 0/17 STT16 DROPS: 70% CAI: 0/30 Backbone Innerduct Placed Backbone Fiber Installed

  6. St. Thomas (East) STT14 DROPS: 95% CAI: 0/43 STT12 DROPS: 84% CAI: 0/19 STT11 DROPS: 88% CAI: 0/17 STT13 DROPS: 0% CAI: 0/6 STT11 STT10 DROPS: 67% CAI: 0/3 STT09 DROPS: 38% CAI: 0/8 Backbone Innerduct Placed Backbone Fiber Installed

  7. St. John STJ02 DROPS: 0% CAI: 0/11 STJ01 DROPS: 0% CAI: 0/20 Backbone Innerduct Placed Backbone Fiber Installed

  8. Splicing the fiber cables into a complete network

  9. Fusion splicing fibers and training a local tech Completed spliced fibers in tray

  10. Splice tray enclosure for pole mounting

  11. Fiber/Facility Access Point (FAP) STT10 (Nadir) Cisco ME 3800 Aggregation Switch (1)

  12. Super FAP STX02 (Frederiksted):Cisco ASR 9006Core Router (1)Cisco ME 3800Aggregation Switch (2)

  13. Community Anchor Institutions • Schools……………………... 82 • Libraries……………………. 7 • Healthcare Providers….. 19 • Public Safety……………… 42 • Colleges……………………. 4 • Government Offices…… 124 • Public Broadcast Sys…. 2 • Community Centers…… 37 • Total 316 • viNGN is bringing a 4-fiber cable and interface to • each CAI at no cost to them and which is capable of delivering at least 1 gigabit service through an ISP of their choosing!

  14. Athalie McFarlane Petersen Public Library-Frederiksted

  15. Building Entry Point Aerial Attachment

  16. Cisco ME 3400 Premise Aggregation Switch Patch Panel

  17. …and 100 megabit+ service becomes a reality in the USVI!

  18. CAI Connection Schedule

  19. Beach Manhole Installations

  20. Summary and Conclusions Construction is proceeding on all aspects of the network. As CAI’s are connected and their segment of the network is lit, gigabit service may begin. Completion of the network build is expected by year end 2013.

More Related