An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. It’s Here: The New Revenue Recognition Standard Presented by: Timothy Wilson, CPA, CCIFP September 26, 2014

  2. Agenda • Where Have We Been? • Truth or Myth? • The New Recognition Model • Disclosures • Effective Dates • Q&A Session (If Time Allows)

  3. Revenue from Contracts with Customers―Finally!!ASU 2014-09

  4. Revenue Recognition Standard Where Have We Been? • Revised Exposure Draft Issued November 14, 2011 • Goals • Develop a common revenue standard for all industries, jurisdictions & capital markets • Condense 100+ U.S. GAAP rules into one high-quality standard • Intended to repeal/replace current accounting & reporting guidance (including all existing construction-specific revenue & cost guidance)

  5. Revenue Recognition Standard Where Have We Been? • Revised Exposure Draft comes after receiving substantial comment letter input from original exposure draft―nearly 1,000 comment letters • Nearly 350 comment letters from construction industry submitted in response to Revised Exposure Draft • A number of matters that were of consequence & concern to the construction industry remained • Substantial redeliberations took place throughout most of 2013, with additional meetings through early 2014

  6. Revenue Recognition Standard Where Are We Now? • New Accounting Standard issued on May 28, 2014 • New definitions, terminology & disclosures • Introduces new complexities for construction industry • Financial statement users, e.g., lenders & sureties,are monitoring this closely

  7. Got a lot of things right that we were expecting • How a performance obligation is defined • Clarifying continuous transfer criteria • No preference for inputs vs. outputs methods on measuring progress • Relief from disclosures for nonpublic entities • But … Revenue Recognition Standard

  8. There are some areas that may create unique challenges • Examples include • Claims & unapproved change orders • Time value of money • Estimation of variable consideration • Exclusion of inputs that are not reflective of progress toward completion―waste/rework • Uninstalled materials Revenue Recognition Standard

  9. Revenue Recognition Standard Revenue Recognition Final Standard Let’s Start Looking!!

  10. Truth or Myth? • Did Percentage of Completion go away? • Can you recognize profit on uninstalled materials? • Will most contracts have multiple performance obligations?

  11. Truth or Myth? • Will I have to recalculate all completed contracts under the new standard? • Is cost to cost still valid to determine percentage complete? • Will I have to add 10 pages of footnotes to my audit report?

  12. Revenue Recognition Standard Recognition Model – Steps Involved Identify contract with customer 1 Identify separate performance obligations in contract 2 Determine transaction price 3 Allocate transaction price to performanceobligations 4 Recognize revenue when (or as) performance obligations are satisfied 5

  13. Revenue Recognition StandardStep 1: Identify Contract with Customer • Five criteria for existence of a contract • Commercial substance • Approval by both parties • Identifiable rights regarding assets to be transferred • Identifiable payment terms (even if amount is uncertain) • Probable that you will collect consideration you are entitled to

  14. Revenue Recognition StandardStep 1: Identify Contract with Customer • Combination of contracts • Contracts are negotiated with a single commercial objective • Amount of consideration in one contract depends on the other contract • Goods or services are a single performance obligation • Segmenting • Inherent in identification of separate performance obligations

  15. Revenue Recognition StandardStep 1: Identify Contract with Customer • Contract modifications • New contract if distinct goods or services are at standalone selling price • Prospective accounting • Continuation of contract if remaining goods or services are distinct from existing contract • Prospective accounting • Continuation of contract if goods or services are not distinct from existing contract • Cumulative catch-up

  16. Revenue Recognition StandardStep 2: Identify Separate Performance Obligations in the Contract • Performance obligation: Promise to deliver a good or provide a service • Separately account for a performance obligation if “distinct” • Distinct • Customer can benefit from the good/service on its own • Good/service is separable from other goods/services in contract • All promises for distinct goods or services must be evaluated (even if inconsequential)

  17. Revenue Recognition StandardStep 2: Identify Separate Performance Obligations in the Contract • A whole contract may be one performance obligation―how? • A good or service is not distinct if • Goods & services are highly interdependent & interrelated • Entity provides a significant integration service • Goods or services significantly modify or customize other goods & services in contract As a result, expectation is typically one performance obligation for many (not all) construction-type contracts

  18. Performance ObligationsFact Pattern • Design/build contract for new high-rise building • Contract includes • Engineering • Clearance • Excavation • Soil sampling • Foundation • Procurement of materials • Installation of systems • Overall project management

  19. Performance Obligations • How many different products & services would you separately account for? • One―but why? • Goods & services are highly interrelated & interdependent • Significant service of integrating goods or services is provided

  20. Revenue Recognition Standard Step 3: Determining Transaction Price • Transaction price • The amount of consideration to which an entity expects to be entitled to receive in exchange for transferring goods or services • Variable consideration • Examples include awards/incentives, liquidated damages, claims, unpriced change orders • Estimate expected value (probability-weighted) or most likely amount • Constraint: Probable that a significant reversal will not occur • Qualitative assessment

  21. Revenue Recognition Standard • Step 3: Determining Transaction Price • Time value of money • Discounting required only if there is a significant financing component (receivable or payable) • One-year practical expedient • Retention? • Collectability • Estimate bad debt & present separately as a component of SG&A expenses

  22. Revenue Recognition Standard • Variable/Contingent Consideration • Application of constraint concept • When are/will the following be recognized on a contract • Performance award incentive for early completion • Performance award incentive for quality of construction • Performance award incentive for attaining LEED Platinum Cert. • Performance award penalty (contract reduction) for delays • Performance award penalty (contract reduction) for lower-quality material substitution

  23. Revenue Recognition Standard • Claims & Unapproved Change Orders • Requirement for recognition • Refer to the five criteria for contract existence • Key: Approval by both parties • Contractors make changes on the fly … • Contract modifications, including a contract claim, would be approved when modification creates or changes enforceable rights & obligations of parties to the contract

  24. Revenue Recognition Standard • Claims & Unapproved Change Orders • If approved as to scope, even if unpriced, company may be able to recognize estimated margin on change orders • What does this mean? • More focus on treatment of “approved as to scope”? • More focus on rationale for estimated margin?

  25. Revenue Recognition Standard Claims & Unpriced Change Orders • Unpriced change orders • Old rule – Generally reflect if recovery is probable & reasonably estimated • New rule – Generally reflect when contractor expects the price change will be approved & there is not an expectation that the estimate will have a significant reversal in the future • Claims • Old rule – Generally reflect when probable & estimable up to the extent of costs incurred―no margin until realized • New rule – Generally include in transaction price when there is not an expectation that the estimate will have a significant reversal in the future

  26. Unpriced Change Orders • Fact Pattern • Single performance obligation to construct a hospital • Change order is for goods that are a necessary part of contractor’s service of integrating goods/services to construct the hospital • Typically agree on price shortly after work associated with change order begins

  27. Unpriced Change Orders • What is the impact to the transaction price? • History indicates price will ultimately be approved • Therefore, estimate transaction price using variable consideration principles How do you account for this change order? • The goods/services associated with this change order are not distinct • Therefore, account for this change order using a cumulative catch-up adjustment, i.e., “catch up” the amount of revenue recognized as if this change order had been in place since contract inception

  28. Revenue Recognition Standard • Time Value of Money • Requirement for application/discounting • Transaction/contract price adjusted to reflect the time value of money if a significant financing component exists • Considerations • Expected length of time between delivery of goods & services & receipt of payment • Whether amount of payment would differ substantially if cash payment was received in accordance with typical credit terms

  29. Revenue Recognition Standard • Time Value of Money • Exception • Expectation at contract inception • Period between payment & performance < 1 year • Applicable to contracts > 1 year in duration if period between performance & payment is < 1 year

  30. Revenue Recognition Standard • Time Value of Money • Retention • Will depend on contract terms & normal practices • Retainage is generally intended to protect the customer & is typically not a form of financing

  31. Award Fee Fact Pattern • Construct an airport baggage system • One-year contract with due date December 31 • Contract price • $30m fixed fee • $2m award fee if completed by October 31 • Baggage system is “off the shelf” & has been sold before in substantially same form • Contractor has ability to complete job by October 31

  32. Award Fee • What is the most appropriate estimation method? • Most likely amount (best estimate) • Possible outcome is binary―“all or nothing” How much revenue would I recognize & when? • $32m ($30m fixed price plus $2m best estimate) • Outcome in contractor’s control • History of performing similar contracts • Recognize total amount of transaction price as the baggage handling system is constructed, so long as it’s probable a significant reversal will not take place

  33. Claims • Fact Pattern • Customer has caused significant delay on contract • Contractor initiates a claim of $5m to recover costs & profit • Contractor & customer have history of negotiating claims & settling for an amount typically different than initial claim

  34. Claims What is the most appropriate estimation method? • Expected value • Many possible outcomes likely exist When would you include this claim in the transaction price? • When an amount is not likely to undergo asignificant reversal in the future • In its early stages, this might be a portion of the claim When would a contractor know to recognize a “minimum amount”? • One example is when a contract gives the contractor a right to recover costs for customer-caused delays

  35. Revenue Recognition Standard Step 4: Allocate Transaction Price to Performance Obligations • Allocate the amount an entity expects to receive in exchange for satisfying each separate performance obligation • Use standalone selling prices of goods or services (estimated if necessary)

  36. Allocation of Consideration Fact Pattern • Contract to build a school & an adjacent football field for $100m • Assume the school & field are separate performance obligations • Standalone selling price • School: $100m • Field: $11m

  37. Allocation of Consideration

  38. Revenue Recognition Standard Step 5: Recognize Revenue when (or as) Performance Obligations Are Satisfied • Recognize revenue over time when • Customer receives benefits as entity performs • Cleaning services • Creates or enhances an asset that the customer controls, or • Building on land owned by customer • Does not create an asset with alternative use & entity has right to payment for work completed to date • Consulting work

  39. Revenue Recognition Standard Step 5: Recognize Revenue when (or as) Performance Obligations Are Satisfied • Measuring progress toward completion • Output methods or input methods permitted • Examples of input methods • Labor hours/dollars, machine hours, costs incurred, time • Examples of output methods • Units delivered, surveys completed • If input method is used, must exclude inputs that do not depict performance (owner-provided materials, waste, uninstalled materials―key for contractors) • Zero margin may be appropriate in some circumstances, e.g., early stage of contract, uninstalled materials

  40. Revenue Recognition Standard Step 5: Recognize Revenue when (or as) Performance Obligations Are Satisfied • Recognize revenue at a point in time only if control doesn’t transfer over time • Factors to consider • Entity has present right to payment • Customer has accepted the asset • Physical possession of asset transferred • Customer has significant risk & rewards • Customer has legal title to asset

  41. Revenue Recognition Standard Uninstalled Materials • Requirement is to exclude the cost of uninstalled materials that are not reflective of contract progress • If customer obtains control of goods before they are installed, recognize revenue equal to cost of goods transferred • Impacts input method (cost to cost) of determining progress • Effect on bonding/underwriting?

  42. Recognize Revenue Fact Pattern • Two-year contract to build a new football stadium for $600m • Estimated contract cost is $500m. Cost incurred at end of year one is $200m • Specifications are customized • Interim progress payments are agreed upon to coincide with job progress • Physical possession & title do not pass until completion • Contractor determined that there is one performance obligation • Contractor concludes that cost is the best measure of control transfer

  43. Recognize Revenue How much revenue is recognized at the end of year one? • $240m How is that amount calculated? Cost incurred to date: $200m Total cost: $500m Percent complete: 40% Total consideration: $600m Revenue recognized: $240m Doesn’t that look like the percent complete calculation I used to do? • Nowthat you mention it―it does look familiar, doesn’t it?

  44. Recognize Revenue Fact Pattern • Assume same fact pattern as in previous example, except • Estimated contract cost is $500m, including $75m for specialized equipment. Cost incurred at end of year one is $200m • At the end of year one, $75m of the estimated contract cost relates to specialized equipment & is not installed, but customer obtained control of equipment upon delivery to construction site

  45. Recognize Revenue How much revenue is recognized at the end of year one? • $227m How is that amount calculated? Cost incurred to date: $200m Equipment cost: ($75m) Total: $125m Percent complete: 29% (125m/425m); ($425 = $500 expected cost less $75m equip. cost) Total consideration: $600m Equipment cost: ($75m) Total: $525m Progress revenue: $152m Equipment revenue: $75m Total revenue: $227m

  46. Revenue Recognition Standard • Other items • Contract costs • Onerous (loss) contracts • Disclosures • Effective date & transition

  47. Revenue Recognition Standard Contract Costs • Incremental cost to obtain a contract • Must capitalize if expect to recover • May be expensed if amortization period is one year or less • Contract fulfillment costs • Look to other guidance first (inventory) • If not in other guidance, capitalize only if • Relate directly to a contract • Relate to future performance & • Expect to recover

  48. Revenue Recognition Standard Contract Costs • Amortize capitalized costs as control transfers • Caution: Will need to consider impairment

  49. Revenue Recognition Standard Onerous (Loss) Contracts • As with current guidance, contractors would accrue an anticipated loss once identified • Cost of settling performance obligation is more than transaction price

  50. Revenue Recognition Standard Onerous (Loss) Contracts • Challenge lies with interplay between various provisions • Transaction price includes amounts the entity expects to be entitled to • “Expects to be entitled to” can include claim revenue • Even if you don’t yet recognize claim revenue, you might count the claim revenue in the transaction price & in doing so defer a loss