The MPP meeting on August 13, 2008, focused on improving the dependability of the 60 A software interlock and analyzing the results of various spare quench heater reconfigurations in MB magnets. Key topics included the status of 600 A circuits' ramp rates, injection tests in Sector 2-3, and procedures for trajectory measurements and corrections. The meeting highlighted successful trials of single bunch beams and illustrated MPP's contributions to boosting efficiency. The next steps involve conducting injection tests in Sector 7-8 for further enhancements.
E N D
MPPMain Ring Magnet Performance Panel Meeting Wednesday 13 August 2008 Agenda: General information ECR for improvement of dependability of 60 A software interlock. M. Zerlauth Results of the simulations for the different spare quench heaters reconfigurations in MB magnets. N. Schwerg Status of the 600 A circuits ramp rate and acceleration parameters. W. Venturini Delsolaro Matters arising
ETLT Injection test in Sector 2-3 Stopping the beam Stefano Redaelli
Injection test in Sector 2-3 • Main objectives: • Injection • Energy matching • Dispersion measurement • Aperture scans • Trajectory corrections • Intensity threshold for BPM system • BLM measurements • …
Injection test in Sector 2-3 • Tests with beam (single bunch) • Pilot Beam for the most part: • single bunch of 5 - 10 x 109 protons • Beam emittance: 1 µm • Momentum spread: nominal • Nominal tunes, nominal magnetic machine • Total intensity injected: • 1 x 1013 protons
Injection test in Sector 2-3 • Trajectory measurements and corrections
Injection test in Sector 2-3 • Aperture scans
Main issues relevant for MPP • First beam induced quench in RB
Main issues relevant for MPP • Induced quenches in 600A circuits due to FPA
Main issues relevant for MPP • QH Power Supply in RB • Replacement needed • First intervention in the tunnel with RP team • Trip of RQT13 • Discharge of QH in RQD
Summary • The sector test has to be regarded as very successful • Essential step towards circulating beams and the LHC startup • MPP contribution • MPP has significantly improved efficiency of the injection test in sector 1-2 • Contribution was appreciated by other participating teams • Very useful exercise for participating MPP experts