1 / 7

UPDATE of RFCC MOUDLE

UPDATE of RFCC MOUDLE. Derun Li, Steve Gourlay Lawrence Berkeley National Laboratory MICE MICO Meeting December 21, 2011. CC Magnets. 1 st CC magnet Cold mass at LBNL First physical (CMM) and electrical measurements complete;

ogden
Télécharger la présentation

UPDATE of RFCC MOUDLE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UPDATE of RFCC MOUDLE Derun Li, Steve Gourlay Lawrence Berkeley National Laboratory MICE MICO Meeting December 21, 2011

  2. CC Magnets • 1st CC magnet • Cold mass at LBNL • First physical (CMM) and electrical measurements complete; • Design of the cooling circuit finalized for Fermilab testing; • Vacuum potting prep underway; • Thermal stress analysis during cool-down complete; • PID (Piping and Instrumentation Diagram) in progress. • Quench protection • Contract signed with MIT; • Preliminary analysis of QP indicated 4 sub-divisions may be adequate (original design has 8); • Design of the stabilization of HTS and SC current and QP leads underway at MIT.

  3. Cold Mass at LBNL CMM measurements complete LH pipe bending complete Ready for machining pipe groove and cold mass support brackets 1st Electrical measurement complete: measured resistance between in-out and QP leads consistent with the design

  4. Update of LH Cooling Pipe Design for the 1st Cold Mass Testing in Progress

  5. CC Magnets • 1st CC magnet • Testing preparation at Fermilab • FSU cryostat; • Testing location identified; • … • SC wires (261 km) ready to be ordered • Review of the cryostat drawings nearly complete; • Modification/updating of the drawings in progress at LBNL • Cryostat fabrication readiness review after next MICE Collaboration meeting (Feb. 8-11, 2012) • Winding procedure review in China (Mar. - Apr. 2012) • Winding of the 2nd coil could start June 2012 or earlier if we decide to mix two different SC wires

  6. MICE RF Cavities • Electro-polishing (EP) set up at LBNL ready; • Waiting for ES&H approval; • Expect to start early 2012. Design

  7. MICE RF Cavities • RF coupler design updated; • Additional welding of cavity support struts complete; • Single cavity vessel fabrication complete and expect to arrive Fermilab this month; • Fabrication of six tuner arms in progress at Fermilab; • Discussions on potential assistance from LBNL on MICE LLRF control initiated.

More Related