An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 11 November 2003 Sverre Jarp CERN openlabTotal Cost of Ownership openlab 2003

  2. Agenda • Day 1 (IT Amphitheatre) • Introductory talks: • 09:00 – 09:30 Welcome. (W. von Rüden) • 09:30 – 10:15 Setting the scene: A Global View of the plans for the LHC Computing Grid – (L.Robertson) • 10:15 – 10:45 Coffee break • Part 2: • 10:45 – 11:15 Review of calculated cost summary for 2003 (S. Jarp) • 11:15 – 12:00 Estimated LCG Personnel and Materials costs (2004 – 2008) (B.Panzer) • 12:30 – 14:00 Lunch • Part 3 • 14:00 – 14:45 Planning the LCG Fabric at CERN (T. Cass) • 14:45 – 15:30 External Testimony: Michael Levine (Pittsburgh Supercomputer Center) • 15:30 – 16:00 Coffee break • 16:00 – Discussions and conclusion of day 1 (All) • Day 2 (IT Amphitheatre MORNING, 513 1-024 afternoon) • Discussions with HP: • 08:45 – 10:45 One-on-one with HP • Discussions with Intel: • 11:00 – 13:00 One-on-one with Intel • Discussions with IBM: • 14:00 – 16:00 One-on-one with IBM openlab 2003

  3. AIM • Understand • Total Cost of Ownership • “Linux fabric” in the Computer Centre • CPU servers • Disk servers, Tape servers + Silos • To a “sufficient” level of detail • 2003 (July/August) Budget situation • Rather than actual sums across all cost centres • Personnel + Materials • No direct measurement of quality • Nor the fraction of capacity actually in use at a given time openlab 2003

  4. Cost of manpower • Complicated issue • Approach chosen: • Take IT salary budget for staff and fellows • Including direct benefits (pension fund, health care, etc.) • Without counting management overhead • Neither inside IT nor CERN • Actual number: 168.8 KCHF • Excluded: • Associates + Students • In general, paid from the materials budget • Associates: Some do not necessarily spend most of their time at CERN • Students: Avoid very short stays (Summer students) openlab 2003

  5. IT budget categories • In the TCO exercise the total IT budgets were initially split into 9 categories: • Computer Centre Services: • Cost of the Physics Fabric and closely related services, such as internal and external networking, etc. • Grid Development/Deployment • Openlab • Computing Infrastructure (non-physics oriented): • Windows, Mail, Web services, Phone exchange, etc. • Product Support (mainly for Engineers): • Digital electronics, CAD, license office, Solaris support. etc. • Controls for physics experiment • so-called “on-line computing” • Database Services and Applications • Communications Infrastructure for the LHC Accelerator • Divisional Management openlab 2003

  6. IT Division (total) openlab 2003

  7. Box count openlab 2003

  8. Capacity Numbers • Other relevant capacity numbers are: • Total installed PC CPU capacity: • ~1.2 Million SpecInt2000 (SI2K) • CPU capacity purchased by August: • 400 * 1.6 KSI2K = 640 KSI2K • Total disk space: 200 TB • Disk space acquired by August: • 50 TB at required performance (actually: 65 TB) • Tape silos installed: 10 (with 6000 slots each) • Tape drives: • 50 STK9940B (+ 20 STK9840 with low usage) openlab 2003

  9. Cost of Central Services • Batch/Interactive services: • Acquisition costs for batch/interactive servers, software licenses and maintenance • Managed storage: • Tape and disk servers (purchase and maintenance) • Computer Centre Infrastructure: • Various contract staff contracts; Monitoring and Supervision; Remedy • Fabrics: • The budget line only covers the CC upgrade this year. • The two "Operations" lines: • Cover costs associated with the various groups (travel, associates/consultants, workstation purchases, etc.) openlab 2003

  10. Cost of Central Services openlab 2003

  11. Cost of Fabric openlab 2003

  12. Costs beyond the fabric • In many cases non-fabric-related costs dominate • Campus Network: • 2991 KCHF • User Support and Quality Insurance: • 1265 KCHF • Computer security: • 741 KCHF • Etc. • In other words: • The fabric benefits from large demands on other services openlab 2003

  13. CPU part of fabric openlab 2003

  14. Disk/tape part of fabric openlab 2003

  15. Summary • All-in-all: • IT estimates (on average) that it has spent ~(1 + 1) MCHF on basic hardware across • CPU servers • Disk servers + Tape servers • Our calculation shows: • Linux fabric in total: 18.6 MCHF • CPU part: 10.5 MCHF • Disk/tape part: 6.3 MCHF • External networking: 1.8 MCHF • Cost on top of basic hardware: • 14.8 / 2 = 7.4 openlab 2003

  16. Backup openlab 2003

  17. 2003 (replacement) cost • IT main entities openlab 2003