Scott Corey CPAs Project Crashing Homework Assignment

Due December 18 th. MGMT E-5065. Scott Corey CPAs Project Crashing Homework Assignment. Scott Corey CPAs. The Scott Corey accounting firm is installing a new computer system. Several things must be done to make sure the system works properly before all the

oleg
Télécharger la présentation

Scott Corey CPAs Project Crashing Homework Assignment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Due December 18th MGMT E-5065 Scott Corey CPAs Project Crashing Homework Assignment

  2. Scott Corey CPAs The Scott Corey accounting firm is installing a new computer system. Several things must be done to make sure the system works properly before all the accounts are put into the new system. The following table provides information about this project:

  3. Scott Corey CPAs

  4. Scott Corey CPAs • REQUIREMENT: • How long will it take to install the system? • What is the critical path?

  5. Scott Corey CPAs The managing partner of the firm has decided that the system must be up and running in 16 weeks. Consequently, information about crashing the project was put together and is shown in the following table:

  6. Scott Corey CPAs

  7. Scott Corey CPAs • REQUIREMENT: • If the project is to be finished in 16 weeks, which • activity or activities should be crashed to do this • at the least additional cost? • What is the total cost of this? • List all the paths in this network. After the crash- • ing has been done, what is the time required for • each path?

  8. Scott Corey CPAs • REQUIREMENTS: • If the project completion time must be reduced • another week so that the total time is 15 weeks, • which activity or activities should be crashed? • Solve this by inspection. • NOTE: It is sometimes better to crash an activity • that is not the least cost for crashing if it • is on several paths rather than to crash • several activities on separate paths when • there is more than one critical path.

  9. MGMT E-5065 Scott Corey CPAs Project Crashing Homework Assignment