1 / 16

Bashewa Rural: Build interconnectors for the Akasia feeder

Bashewa Rural: Build interconnectors for the Akasia feeder. Compiled by: Koena Mojapelo Sune Cotzee 011 747 6504 (Tel) and 021 980 9569 (Tel)

oriana
Télécharger la présentation

Bashewa Rural: Build interconnectors for the Akasia feeder

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bashewa Rural: Build interconnectors for the Akasia feeder Compiled by: Koena Mojapelo Sune Cotzee 011 747 6504 (Tel) and 021 980 9569 (Tel) Mojapek@eskom.co.zaCoetzeSU@eskom.co.za

  2. Contents Background Problem statement Load forecast Proposed alternatives Cost Recommendation

  3. Problem Statement The Akasia feeder is configured in such a way that it is unnecessarily long and as a result the losses in the feeder are high. The minimum MV voltage on the Akasia feeder is 0.85p.u and this is below the permissible limits as per NRS048-2.

  4. Problem Statement p.u sending-end Voltage axis p.u daily load axis • At peak load the sending end voltage on the Bashewa transformer ranges between 0.99-1 p.u.

  5. Background • The Akasia feeder (BA) is supplied from a 1x10MVA, 88/11kV transformer at Bashewa Rural. • There are three feeders in total which are supplied from Bashewa Rural: viz Akasia (BA), Geelhout Feeder (BG), Jakaranda Feeder (BJ). • The backbone of Akasia feeder is 19km long and is built with Mink conductor. • There are 154 customers (residential and agricultural) on the Akasia feeder with an installed load of 8231kVA. • The MD on the BA feeder was 2.7MVA in 2008

  6. Load Forecast • There is no history of MD on the Akasia feeder, MD data is only available from 2006. • The load forecast is based on history of actual installed trfr’s on the feeder over a period of 5yrs since 2004. • The average installed load over the 5yr period was calculated as 348kVA. • Load growth is based on a fixed diversified peak contribution of 113kVA annually.

  7. Proposed alternatives Immediate network change: Change the tap settings of Bashewa substation Trfr. • Set the setpoint @ 103% and the bandwidth at +-1.4% Comments • MD 2008 = 2.7MVA • The minimum voltage is improved from 0.85p.u to 0.88p.u.

  8. Proposed alternatives Alternative 1: Install a voltage regulator on the BA feeder(2009) • Install a voltage regulator at BA80 Comments • MD 2009 = 2.8MVA • The voltage improves from 0.88p.u to 0.95p.u. • The capacity created is insufficient.

  9. Proposed alternatives Alternative 2A: Build inter-connectors on the Akasia feeder (2009) • Build 714m Fox inter-connector from BA60/7/5 to BA147/25. • Open the existing links at BA119 to create a N/O point. • Build a 380m Fox inter-connector from BA60/7/7 to BA177/22. • Open the existing links at BA148 to create N/O point. • Re-stencil the feeder. Comments • The backbone length is reduced from 19km to 12km resulting in a reduction of 100kVA in losses. • The voltage is improved from 0.88p.u to 0.93p.u.

  10. Proposed alternatives Alternative 2B: Build inter-connectors and install a shunt capacitor(2009) • Build 714m Fox inter-connector from BA60/7/5 to BA147/25. • Open the existing links at BA119 to create N/O point. • Build a 380m Fox inter-connector from BA60/7/7 to BA177/22. • Open the existing links at BA148 to create N/O point. • Install a 300kVAr capacitor Comments • PF = 0.96 during peak load. • Voltage improves 92.31% to 93% • Spare capacity created = 0 • The power factor is improved from 0.96 to 0.97.

  11. Proposed alternatives Alternative 2C: Build inter connectors and install a voltage regulator (2009) • Build 714m Fox inter-connector from BA60/7/5 to BA147/25. • Open the existing links at BA119 to create N/O point. • Build a 380m Fox inter-connector from BA60/7/7 to BA177/22. • Open the existing links at BA148 to create N/O point. • Install a voltage regulator at BA55. • Re-stencil the feeder. Comments • The voltage is improved from 0.88p.u to 0.97p.u • Point spare capacity created = 450kVA. • Distributed capacity created = 1.2MVA.

  12. Proposed alternatives Alternative 3: Rebuild the Akasia backbone with Hare conductor (2012) • Rebuild 11km of Mink and Fox conductor with Hare from BA1 to BA156/23. Comments • MD in 2012 = 3.12MVA • Point spare capacity created = 1.5MVA • Distributed spare capacity = 2.5MVA • Maximum stress = 62.13% • From a construction point of view this option is not practical as it is going to involve a lot of break and build and many customers will be affected by the outages. Point Spare capacity = 1.5MVA Distributed spare capacity = 2.5MVA Maximum stress = 62.13% Point Spare 2012 = 425kVA Distributed spare capacity 2012 = 900kVA Maximum stress = 69.56%

  13. Proposed alternatives Blue Horizon 1.8MVA Emri 28MVA Proposed substaton site Alternative 4: Deload a section of the Akasia feeder to a proposed new substation in the Boschkop Area (2012) Background • Three applications were received on the Tweedracht Tiegerspoort (TT) network. • These applications cannot be accomodated on the existing network and it is proposed that a new substation be built to connect them. • If the customers accept the quotes sent to them, the proposed substation can be completed by 2012. • It is proposed that the TT feeder be split into three sections in order to feed Blue Horizon and Borotech. • Akasia feeder has a N/O point with the TT feeder and it is proposed that this N/O point be closed and a section of Akasia be deloaded to the proposed substation via a section of TT. Borotech 800kVA

  14. Proposed alternatives Blue Horizon 1.8MVA Emri 28MVA Proposed substation site Alternative 4: Scope of work • From the proposed substation, build 900m Hare line to inter-connect with the Tiegerspoort feeder at TT130/26. • Install a tri-switch at TT128 to create a N/O point. • Close the N/O point between the Akasia and Tiegerspoort feeder at BA201. • Open the links at BA187. • Relocate the voltage regulator installed at TT62 to TT131/9 • Rebuild 2.3km of Fox conductor from TT130 to TT 130/26. Comments • The TT feeder will be split into three sections, viz TT LZ1, TT LZ2, TT LZ3. • TT LZ1 is the portion that will remain at Tweedracht substation. • A new feeder will be built from the new substation to inter-connect with TT LZ3, and this will form New feeder 1 and Borotech will be supplied from this feeder. • BA LZ2 will be fed from the new substation via TT LZ3. • A second feeder will be built from the new substation to inter-connect with TT LZ2 and Blue Horizon will be fed from this new feeder. Borotech 800kVA Point spare capacity = 600kVA Distributed spare capacity = 1.5MVA Maximum stress = 63.22% Point Spare capacity = 800kVA Distributed spare capacity = 2.4MVA Maximum stress = 52.9%

  15. Cost: Alternative 2C: Build inter-connectors and install a voltage regulator(2009)

  16. Recommendation • Change the Bashewa transformer tap settings as an immediate solution. • Implement Alternative 2C as a short-term solution • Implement Alternative 4 as this is a long-term solution that will allow for future load growth in the area.

More Related