An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FIRE STATION NUMBER 2 Pre-Proposal Conference & Site Visit RFP 2013-012FR August 27, 2013

  2. Project Summary • Goal is to Construct a new, single-story or multistory approximately 8,000 Sq. Ft. Fire Station. • Alt. Bid item for Demo of existing fire station and providing landscape and irrigation. • City of Palm Beach Gardens – Owner

  3. SITE LOCATION 11025 Campus Drive

  4. EXISTING SITE Lot size Approx. 125’ x 840’

  5. Existing Site Conditions

  6. Existing Site Conditions

  7. CONCEPTUAL SITE LAYOUT

  8. PROVIDE ALTERNATIVE SITE LAYOUT POSIBLE SITE LAYOUT

  9. Building Requirements • LEED Certified – per state requirements • 72 hours, self-sustained generator • Reuse existing 2- convault tank for generator and fueling (500 gallons each) • Architecture to match surrounding buildings

  10. Site Requirements • The Existing fire station shall remain open at all times with ingress and egress 24 hours a day. • During construction, all utilities servicing adjacent and off-site facilities shall not be interrupted • Secure staging areas and site at all times with a 6 foot high chain link fence with wind screen • Drainage per SFWMD

  11. Seacoast Utilities Site Site Water & Fire Sewer

  12. Fire Station ProgramGeneral Requirements The City has revised the Design Criteria Package (Attachment A). The draft format will be discussed today and provided as a addendum once we receive input at this meeting and site visit.

  13. Fire Station Program • Site requirements – parking, landscape , etc • Building requirements • Apparatus bay • Watch room • Medical supply room • Officers quarters • Fire fighters bunk rooms – 8 bunks • Restrooms

  14. Fire Station Program • Multipurpose room • Kitchen • Janitorial closet • Weight room • Decontamination room • Bunker gear room • Mechanical, storage, generator enclosure, IT, etc.

  15. Bidding Important Dates • Pre bid meeting & site visit August 27, 2013 • Deadline for questions October 1, 2013 • Bids Due October 4, 2013 • Selection Committee short list November 4, 2013 • Oral Presentations November 15, 2013 • Project Award Presentation to Council January 9, 2014

  16. Bidding Phase Design-Builder is responsible to review all evaluation and selection criteria listed in the bid documents • Design-Builder Team to have at least three (3) completed similar design/build projects from the Design/Build Team. • Qualifications, project approach, and cost will be evaluated for short listing. • Final selection - initial evaluation, ability to meet schedule, team qualifications, approach, similar projects and price. • Award recommendations will be made to Council following oral presentations and negotiations.

  17. Design Phase Design phase of the project will depend on Design-Builder approach to the project and negotiations for award. Owner Assumptions: 120 days for design Typical submittals of 30, 60, 100% City will require Design-Builder to assist in Site plan approval process

  18. Site Plan Approval Process • Designed to Chapter 78 (Land Development Regulations) of the City’s Code • Existing Zoning – Public/Institutional (P/I) • Max lot coverage – 40% • Max build height – 45 ft • A fire station is classified as a Major Conditional Use • Plat will be required

  19. Setbacks

  20. Site Plan Approval Process • Required Meetings • If REZONING IS REQUIRED (Waivers form City LDR’s) • Pre-application • DRC • Planning and Zoning meeting • 2 City Council meetings • *Rezoning to a PUD required if waivers are needed from development regulations in Land Development Code • NO REZONING REQUIRED ( No Waivers) • Pre-application • DRC • Planning and Zoning • 1 City Council meeting

  21. Pre-Construction Phase Contractor obtains permits (City pays) • Pre-Construction Conference • Construction Schedule • Schedule of Values • Material Submittals • Construction Operations and Safety Plan

  22. Construction Phase • Biweekly Progress Meetings • Confirmation Survey • Zero Safety Mishaps Post-Construction Phase • Punch List • O&M Manuals, Training, Spare Equipment and Finishes • As-Built Drawings (electronic) & velum

  23. Fire Station Number 2 • Budget: $2,600,000 • 425 calendar days to Substantial Completion; 30 calendar days to Final Completion • Liquidated Damages of 0.01% of GMP per day • Optional Items: • Demo of existing fire station, landscape and irrigation of old station

  24. Contact and Due Date • Submit questions and requests for clarification in writing by October 1, 2013: kmra@pbgfl.com • Proposals Due Date and Time: October 4, 2013 @ 3:00PM

  25. RFP2013-012FRDesign Build New Fire Rescue Station No. 2Thank You.