1 / 19

Online Summary

Online Summary. Jean-Sebastien Graulich, Geneva. Detector DAQ Controls And Monitoring Online Data Base Bottom Lines. DDAQ Achievements since CM24. DAQ and Controls Review Factor of 5 increase in # of particle triggers per spill Current limit at 250 Particles/spill

pabla
Télécharger la présentation

Online Summary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Online Summary Jean-Sebastien Graulich, Geneva • Detector DAQ • Controls And Monitoring • Online Data Base • Bottom Lines Jean-Sebastien Graulich

  2. DDAQ Achievements since CM24 • DAQ and Controls Review • Factor of 5 increase in # of particle triggers per spill • Current limit at 250 Particles/spill • FADC Firmware upgraded • Factor of 4 reduction in data size • Trigger System Debugged • Problem with Event building under control Jean-Sebastien Graulich

  3. Important Discussion • Double pulse resolution in TOF • Discriminator dead time • Minimum width of logic signal after discriminator: 100 ns • Double pulse resolution: 110 ns • In a given TOF PMT, it is IMPOSSIBLE to see two hits in the same burst ! • Complying with specifications but a real limitation • We need a way to tell monitor the number of particles in a burst • Use BPM ? Use Tracker ? • Upgrade TOF discriminators ? Jean-Sebastien Graulich

  4. DDAQ Main Works in progress • Integration of TOF2 • Requires update in Crate Layout • Integration of CAM/DDAQ • DATE Status in EPICS • Target DAQ • Beam Losses and Target BCD in data stream • Magnet Currents (and more) in Data Stream • Integration of Tracker • EMR Front-End Electronics Jean-Sebastien Graulich

  5. Schedule Milestones • From CM24 • TOF2 Shaper/Splitter Production mid Marchneed testing • DAQ review June 09 • Upgrade of fADC firmware July 09 • CAM data in Online Data Stream June 09 -> Jan 10 • Tracker integrated in DAQ and OLM July 09 ->Jan 10 • TOF TDC Clock Synchronization July 09 -> March 10 • More complicated than first thought. Need a dedicated board • Burst Gate Signal in the Trigger System Need support here • Approval of SW/EMR Front End Electronics In Proto phase • Production of SW/EMR Front End Electronics Sept 2009 -> Jan 10 ------------------------------------- • DATE Status in EPICS Nov 09 • TOF2 DAQ Installation Dec 09 • Target DAQ in Data Stream Dec 09 Jean-Sebastien Graulich

  6. Controls And Monitoring • Good progress on all fronts • Groundwork required to unify MICE control systems & create a user-friendly interface is well underway • Controls effort is ‘significantly understaffed’ (DAQ & Controls Review, June ‘09) • We are always operating at full capacity • ‘Controls & Monitoring’ is such a broad subject that many unexpected additional requirements crop up all the time… • Please be patient! Jean-Sebastien Graulich

  7. CAM Main Achievements since CM24 • Control PCs & servers Reorganization • DL Systems isolated on a single server • Application management Tools created • including GUI • New Target Controller • Set delay, dip depth, etc • Target DAQ software and monitoring completed • Standalone and Interfaced to EPICS (need integration in DDAQ) • EPICS gate way running • CKOV Humidity and Temperature into CAM • Neutron Monitor into CAM • Alarm Handler working and becoming user friendly • Clear Plan for Version Control and System Update • Interface with Configuration Database Jean-Sebastien Graulich

  8. Control PCs & Servers: Current Status miceiocpc1 target1ctl miceioc2 miceioc4 miceioc1 miceioc5 miceecserv miceserv1 target2 miceopipc1 micecon1 See James’ Talk for details

  9. Application Launcher • New application launcher replaces DL TCL script • XML configuration file, easy to add items • Unlimited subcategory levels • Provides real-time display of application status • Configurable response to existing application instances

  10. Target: Controller • Target Controller Stage 1 upgrade underway • Hardware essentially complete • Currently working on Controller firmware (P. Smith) • Software nearing completion • Hardware driver framework in place • Have implemented all EPICS server / client functionality • Tested using ‘virtual’ Target Controller Device • Remaining task: write low-level hardware driver plug-in once firmware is complete • Stage 1 upgrade - Control functionality includes: • Set delays • Set / monitor Target depth • Park / hold, start / stop actuation • Monitor hardware status

  11. Target: Beam Loss • Standalone DAQ system upgrades: • Final algorithm selected for ‘absolute’ beam loss calculation • Thanks to AD for implementation • Standalone event viewer can now follow real-time output of DAQ • Target Beam Loss IOC will read local data archive written by DAQ & serve values as PVs • Enables integration with Alarm Handler & readout of actuation numbers for CDB run data entries • IOC will use same analysis & file access code as standalone DAQ, via C wrapper functions • See PH’s talk

  12. EPICS Gateway

  13. Policy for CAM System upgrades • Next Update in January ! Jean-Sebastien Graulich

  14. CAM Main Works in Progress • Network Status • DATE Status • Environment Monitoring (temperatures, humidity, water flows, ...) • CKOV High Voltage System (CAEN SY127) • Quotation for Cooling Channel Control System (DL) Jean-Sebastien Graulich

  15. DataBase • ConfigurationData Base • Doesn’t Store Data • Doesn’t Archive the parameter read values • Store the Geometry, Calibration Constants, Set values, etc • Use Case example: • Give me the configuration of the experiment at 16:15 on 5th November 2009 • Needed by reconstruction software to analyse the data • Relational AND bi-temporal. • Please see previous collaboration meeting talks for a fuller explanation of this concept and its justification. Jean-Sebastien Graulich

  16. Database Functionality 2 • Since the last collaboration meeting there has been much progress • Geometry- Can now write and read geometries- We can reconstruct what the geometry was known to be for a given time. We have a history of state.We also can update when misalignments are found. We have a history of those updates. You can reconstruct what was KNOWN about the state of the geometry at some set of given times, very easily. • Calibration- Can now write and read calibrations of arbitrary format- One default calibration should be maintained by the detector groups but others can be kept and called specifically • Set Values- Can now write and read set values - EPICS GUI (James Leaver) interfaces with this. Thanks also to Pierrick & Adam for help with cataloguing many set vals.

  17. Configuration Database: User Entry User Entry Client • Not all parameters required for a CDB ‘run’ entry are available through normal EPICS channels • i.e. Relevant IOCs & integration with the DAQ are not yet complete • Currently only beamline magnet currents can be backed up from ‘live’ servers • (Quasi) temporary solution: • Generic EPICS data server hosts PVs for all values missing from existing IOCs, so they can be read by backup/restore client • User entry client allows shifter to enter required parameters before initiating a run • As future work progresses, unnecessary user entry items will be removed • However, shall always require some degree of manual data entry CDB Data Server (miceiocpc1) Backup / Restore Client

  18. Summary • Database is progressing well • Wish to finish database functionality and perform stress tests which could be presented at CM26 • Nevertheless, people should think about integrating DB communication with their applications (contact me for info – d.forrest@physics.gla.ac.uk but this is an action item for others)

  19. Bottom Lines • General Progress • Manpower is very limited and not secured on the long term • More and more integration/unification tasks • Mice Online Group (MOG) is necessary but suffers from a loose leadership • This is a call for help ! Jean-Sebastien Graulich

More Related